Earned Value Formulas Flashcards
PV
Planned Value
The authorized budget assigned to scheduled work.
EV
Earned Value
Measure of work performed expressed in terms of the budget authorized for that work.
EV=sum of the planned value of completed work.
AC
Actual Cost
The realized cost incurred for work performed on an activity during a specific time period.
BAC
Budget at Completion
The sum of all budgets established for the work to be performed.
CV
Cost Variance The amount of budget deficit or surplus at a given point in time, expressed as the difference between earned value and the actual cost. CV=EV-AC Positive = Under planned cost Neutral = On planned cost Negative = Over planned cost
SV
Schedule Variance Amount by which the project is ahead or behind the planned delivery date. SV=EV-PV Positive = Ahead of schedule Neutral=On schedule Negative=Behind schedule
VAC
A PROJECTION of the amount of budget deficit or surplus. VAC=BAC-EAC Positive = Under planned cost Neutral = On planned cost Negative = Over planned cost
CPI
Cost Performance Index A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost. CPI=EV/AC >1.0 = Under planned cost =1.0 = On planned cost <1.0 = Over planned cost
SPI
Schedule Performance Index
A measure of schedule efficiency expressed as the ratio of earned value to planned value.
SPI = EV/PV
>1.0 = Ahead of schedule
Exactly 1.0=On schedule
<1.0 =Behind schedule
CPI Interpretation
>1.0 = Under planned cost =1.0 = On planned cost <1.0 = Over planned cost
SPI Interpretation
> 1.0 = Ahead of schedule
Exactly 1.0=On schedule
<1.0 =Behind schedule
CV Interpretation
Positive = Under planned cost Neutral = On planned cost Negative = Over planned cost
VAC Interpretation
Positive = Under planned cost Neutral = On planned cost Negative = Over planned cost
SV Interpretation
Positive = Ahead of schedule
Neutral=On schedule
Negative=Behind schedule
EAC Definition
Estimate at Completion
The expected total cost of completing all work expressed as the sum of the actual cost to date and estimate to complete.