7 Project Cost Management Flashcards

1
Q

Project Cost Management includes…

A

All the processes involved in planing estimating budgeting, financing, funding, managing, and controlling costs so that the project can be completed within the approved budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

List processes in Project Cost Management

A

(4)

  1. 1 Plan Cost Management (Planning)
  2. 2 Estimate Costs (Planning)
  3. 3 Determine Budget (Planning)
  4. 4 Control Costs (Monitoring and Controlling)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

List Inputs, Tool & Techniques, and Outputs for:

7.1 Plan Cost Management

A
Inputs
PM Plan
Project Charter
Enterprise Environmental Factors
Organizational Process assets

Tools
Expert Judgement
Analytic techniques
Meetings

Outputs
Cost Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

List Inputs, Tool & Techniques, and Outputs for:

7.2 Estimate Costs

A
Inputs
Cost Management Plan
Human Resource Management Plan
Scope Baseline
Project Schedule
Risk register
EEF's
OPA's
Tools and Techniques
Expert Judgement
Analagous Estimating
Parametric Estimating
Bottom-up Estimating
Three point estimating
Reserve Analysis
Cost of Quality
Project Management Software
Vendor Bid Analysis
Group Decision Making Techniques

Outputs:
Activity cost estimates
Basis of Estimates
Project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

List Inputs, Tool & Techniques, and Outputs for:

7.2 Determine Budget

A
Inputs
Cost Management Plan
Scope Baseline
Activity Cost Estimates
Basis of estimates
Project Schedule
Resource Calendars
Risk Register
Agreements
OPA's
Tools and Techniques
Cost Aggregation
Reserve Analysis
Expert Judgement
Historical Relationships
Funding limit reconciliation

Outputs
Cost baseline
Project Funding requirements
Project Documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

List Inputs, Tool & Techniques, and Outputs for:

7.4 Control Costs

A
Inputs
Project Management Plan
Project Funding requirements
Work Performance Data
OPA's
Tools and Techniques
Earned Value Management
Forecasting
To-complete performance index (TCPI)
Performance Reviews
Project Management software
Reserve Analysis
Outputs
Work Performance Information
Cost forecasts
Change Requests
Project Management Plan updates
OPA Updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Three Point Estimating formulas

A

Triangular - cE=(cO+cM+cP)/3

Beta - cE=(cO+4(cM)+cP)/6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Earned Value Management

A

Methodology that combines scope, schedule, and resource measurements to ass project performance and progress. EVM develops and monitors three key dimensions for each work package and control account: Planned Value, Earned Value, and Actual costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Planned value

A

PV is the authorized budget assigned to scheduled work.. Does not include management reserve. The total of the PV is sometimes referred to as performance measurement baseline (PMB). The total planned value for the project is also known as budget at completion (BAC).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Earned Value

A

EV is a measure of work performed expressed in terms of the budget authorized for that work. It is the budget for the work that has been completed. EV measured cannot be greater than the authorized PV for a component.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Actual Cost

A

AC is the realized cost incurred for the work performed on an activity during a specific time period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly