JS Quantification and Costing Flashcards

1
Q

L2 - Can you tell me some rules within NRM2 for measurement of finishes on BP Phase West

A

For painting, if the girth is under 300mm thick, it is measured as a linear length. If it is over 300mm thick it is measured as a m2
Any fabric finishes, so the wall papers I had to measure to certain rooms, if the area was less than 1m2 it was measured as a linear length, over 1m2 was a m2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

You describe using NRM2 to produce a Bill of Quantities, what does this look like?

A

Three parts; general, rules for measurement including info required, how to produce a BoQ, then 3 section is tabulated rules

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

On Gillingham House, how did you measure the steel

A

length x weight /1000 = tonnage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How did you measure the brick façade on Gillingham House?

A

Measured to the centre line on the GA plans then worked out the height on the elevations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Gillingham House

How did you build up the costs for the brickwork?

A

Different options around the façade; one option was a PCC option and the other SFS; I built up the costs for the SFS by costing the frame, brick slip, movement joints and membranes etc. The PCC I had a meeting with a supplier who provided costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Q&C - On Walstead, what was your advice to the client?

A

My advise was that, the type of cost estimates will change depending on the level of design that is available at the time of costing. I advised the type of cost estimate that would be most appropriate when there is limited design, in this case I advised a FUM would be the most appropriate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Can you talk me through your advise on the Amazon Commercial Fit Out Project

A

I advised the client of bespoke elements of the design such as internal planting, the staircase and joinery items before advising the client of the costs to inform them if they were in or out of budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

L2 - Amazon - You mention about obtaining quotes for bespoke elements; what was your process?

A

I spoke to 3 to 4 suppliers in order to obtain quotes, who supplied a supply and install cost. I then added % add on for prelims and OHP for the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Can you give me an example of how you assessed a rate on Henry Dickins?

A

There was a cost submitted to unblock a internal rainwater outlet. The QS submitted a lump figure so I went back and asked for more detail. Once he sent the costs for the labour 2nr x 300 per day and a break down for locating the blockage, cutting into the cast iron stack, removing the blocking and replacing pipework i was able to view the rates and make an assessment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How to assess whether the rates are fair and reasonable?

A

I look at the build up of the rate; supply of material, install costs including labour and benchmark any rates where possible against other projects. I also ask the quantity surveyor to obtain a number of quotes to ensure value for money is being achieved

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Can you give an example of when there was an adaptation to the rate?

A

There was an item in the pricing document to DOFF clean all elevations to the block of flats. The client requested that the external garden walls were to be DOFF cleaned as well. The contractor submitted a rate for the DOFF clean which had increased from the contract rate. I advised my client that, due to the area of the wall being a lot smaller, and increase is acceptable due to economies of scale.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Can you name some other reasons why a rate may increase?

A

Quality of the product, for example, hardwood and softwood doors, method of fixing, conditions of the site and time of year

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What do you mean by in or out of scope?

A

I would check to see whether the items of work there were raising were all ready included within the pricing document or whether they were a variation to it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

You have mentioned GIA - Where are they defined? What do these initials GEA, GIA and NIA stand-for?

A

Code of Measuring practice, 6th edition applies to all building classes except offices and residential buildings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How did you present ve to the client? What headings were included in the VE schedule?

A

Function / Element
Cost
Alternative to current design
Cost, quality and function analysis
Recommendation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is Value Engineering?

A

a ‘systematic approach’ to delivering the required functions to the required quality at the least cost

17
Q

What does the RICS Valuing Change Guidance Note say about change?

A

In the first instance, use contract rates, then fair and reasonable assessment, day works and schedule 2

18
Q

What are the options for pricing documents and when would you use each of the types?

A

Activity schedule, schedule of works, BoQ

19
Q

What is IMPS 1

A

The sum of areas from the outer perimeter of the external features

20
Q

What is IMPS 2

A

The sum of area measured to the internal dominant face

21
Q

What is IMPS 3

A

The floor area available on a exclusive basis

22
Q

How did you build up your external wall rate

A

Had a supply and install cost for the brickwork itself, installation, brick ties, internal wall, mortar

23
Q

Why did NRM replace SMM

A

SMM was more focused around the production of BoQ, meaning that there was confusion and inconsistency around measurement as cost estimates and cost plans were more common

24
Q

What is the structure of NRM 1

A

Introduction
Measurement rules for cost estimating
Measurement rules for cost planning
Tabulated measurement rules for elemental cost planning

25
Q

If a client wanted to utilise a BoQ, what would advise

A

It is a lot longer and costly process due to the detail in the BoQ. Also, the client would take the risk on quantities if the BoQ is not approx quantities.

26
Q

When undertaking high level feasibility studies for clients how do you manage the risk of the lack of design detail in the cost plan?

A

Design development contingency

27
Q

What is a typical design development contingency

A

10%

28
Q

What is IPMS?

A

Internal National Property Standards ensure that properties are measured in a more consistent way

29
Q

What are the main types of classification under IMPS

A

Commercial, Residential, Retail and Industrial

30
Q

Under IPMS 2, what is meant by internal dominant face?

A

inside surface area comprising more than 50 per cent of the lowest 2.75 m measured vertically

31
Q

What is ICMS 3?

A

benchmarking and reporting of construction project cost and. carbon. Used for carbon life cycle costing

31
Q

What things do you consider when taking rates from other tenders?

A

The time of the tender and the location, weather i ned to adjust them to London rates

32
Q

What sub elements are containined with frame under NRM1?

A

Steel frames, space frames and decks, concrete casings for steel frames, concrete frames, timber frames, specalist frames

33
Q

Confidential Resi Project

How did you applie the funcitional unit method?

A

I split the costs between houses and apartments and got a benchmark unit rate for a house and a benchmark unit rate for an apartment, then multiplied the total by the amount stated in the architect’s UMS. I then applied a % for OHP and any risk allowances.

34
Q

Amazon POP

What information did you provide to the subcontractors

A

I provided a quantited take off for them to insert rates, including a count of each of the spoke joinery items and a description, also included floor plans, CGI of the bespoke items

35
Q

Henry Dickins

Can you give me an example of a variation and how you measured it?

A

Talk about the levelling screed