JS Construction Tech Flashcards
What methods or processes were used to gather data for your cost comparison on the strip foundations and piled foundations?
I used in house benchmarking in order to obtain a cost /m2 GIFA allowance, given the stage of the project. I also then compared these costs against a recent tender I had received for mini piles
Why did the Structural Engineer propose to switch from strip foundations to mini piles?
The amount of cut and fill on site meant the subsoil was a lot weaker in areas there there was a high quantity of fill. This meant mini piles had to be used in order to reach a firm strata.
What was the outcome of the cost comparison?
Walstead Park fnds
A mini pilled foundation was more expensive so there was an increased costs. However, the structural engineer advised it was too unsafe and unstable to use a strip foundation
How did you do the cost comparison?
Walstead Park fnds
I considered the different cost items in a strip foundation which included concrete, rebar, formwork, excavation and compared it against the cost for a mini piled, using benchmarking where possible
On Gillingham House, can you tell me what you did?
Brickslips
The client had proposed a precast concrete system for the brick-slips and the client asked for a cost comparison against a traditional method. Although the traditional was cheaper, a rate of £450 a m2 was provided to me by the subcontractor, the brick-slip was preferred due to ease and speed of construction, and quality assurance. The client then asked me to provide a cost comparison against s SFS system
What were the cost differences between the SFS and PCC
I had a rate of £1,4750 for the SFS system, which was built up of the frame, brick slip, fire barriers etc and a rate of £1,593 for the PCC system, which was provided by a supplier
How did undertake your cost analysis on Wandon Road
As the current roof space just had plant located on it, I spoke to the MEP team about the scope that would be required. This included relocating the all the heavy plant equipment elsewhere. The MEP consultant confirmed the cabling and pipework can stay if a timber deck was placed over. There would also be costs to provide some new MEP such as external lighting. I then spoke to the SE about any structural strengthening works that would be required
Other than MEP, architectural and structural, was there anything else you needed to consider?
There are regulations regarding roof gardens as part of the Building Reg. Part B. If the client wanted to proceed with this option they would have to consultant the fire consultant.
L2 - How did you build up the costs for the new roof garden?
Wandon Road
On another project, I had the same type of scope where an existing roof was to be made into a roof garden, so I was able to benchmark a lot of the items using rates the tenders had returned. There would also be a requirement for new safety measures to allow footfall onto the room.
Did the client want to go with this option?
Wandon Road
It was very much a nice to have item, as the costs were way above the budget, the client proposed not to go with it.
What was the basis for your advise that underpinning would be required?
How did you present your assumptions to the client on the Horiato’s?
I issued the client a report, with the costings and our assumptions listed out. As the client had no construction background, and where a charity, I spent time explaining the different construction methods required and what we have costed.
Are we, as QSs, in a position to be advised on design?
No, I made it clear within the report that any further action on the project should include the appointment of a structural engineer and architect. I was only presenting the costs and listing out the different assumptions I had made.
How did you cost the works if there was no design?
Horatios Garden
For the lift itself, I spoke to the market to obtain 3 quotes for a new platform lift, which included works required to facilitate the lift, such as new foundations. For other works I had assumed, I was able to get costs from other projects of a similar nature and allow for provisional sums within the costings for these works. I also spoke to different colleagues of mine for advise on my costings and other elements of works required.
What’s the difference between bored piles and driven piles?
Bored a hole is excavated and concrete is then poured into it, driven are usually precast and driven into the ground