JS Project Finance Flashcards
What forms a cost report?
Talk through contents
Why is change control important?
Level 1
Change control ensures changes to scope or deliverables are recorded, evaluated and authrosied by the client
What is the importance of a cash flow forecast?
Checks budget
Forecast final account
Track progress against cashflow
What things do you need to consider when putting together a cash flow
Method of payment; staged, periodic, milestone
Type of contract; contract procedures such as timeframes for payment, payment schedules
Type of cash flow; project or construction
Retention - deduct as per the agreed contract and release after PC and DLP
Bank and public holidays
What does it show if a contractor’s cash flow is behind schedule?
Poor conditions on site
Adverse weather conditions
Slow progress on site
Inaccurate forecast
Re-sequencing of works
What does it show if a contractor’s cash flow is ahead of schedule?
Front loading
Variations
Ahead of programme
Materials off site earlier than expected
Contractor acclerating the works
What are provisional sums?
Allowances for works where the design or specification is unknown at the time of contract
What should a provisional sum have to be defined?
contractor has been provided sufficient detail to make allowance for them in their price and programme. This detail could include a certain level of design, an understanding of construction phasing, likely quantity and any specific restrictions are known.
BP Phase East
How did you identify risk items?
I had weekly risk meetings with the construction manager where we ran through a risk register. I took these items and included them within my risk section.
BP Phase East
Give me an example of a risk item within your project?
BP Phase East
Give me an example of a provisional sum in your cost report?
Henry Dickins
How did you initially calculate the cash flow and advise on the expenditure
I took the contractor’s cash flow they produce each month and and provide comments as to the monthly expenditure
Henry Dickins Court, Residential Refurbishment, London - Cash Flow
What did you advise?
My advise was that the contractor’s cash flow is a forecast and the actual monthly spend is usually different to the cash flow.
On this occasion the scaffolding erection was slightly behind programme due to slow progress.
Henry Dickins - Scope Omission
Why did you not VE the works?
There wasn’t really scope to VE, a lot of the works were refurbishment works, re pointing of brickwork, brickwork replacement, new double glazed windows and front secuirty doors, re tiling and waterproofing so there was minial scope to actually VE