JCT Contract Structure Flashcards
Why would you use a SBC
For larger works designed or detailed on behalf of the employer
Drawings and specification supplied to the contractor which define scope and quality of the work.
The contract is administered via a CA
What are the articles of a contract
It sets out the parties obligations and agreed legal course of action.
1) contractors obligations
2) contract sum
3) Contract Admin / Architect
4) QS
5) Principle Designer
6) Principle Contractor
7) Adjudication
8) Arbitration
9) Legal proceedings
What is included in Section 1 of a JCT contract?
Interpretations
(Basically a table of definitions)
Where are interpretations found a JCT contract?
Section 1 - interpretations
(Basically a table of definitions)
What is included in Section 2 of a JCT contract?
The contractors obligations
1) General obligations
2) possession
3) supply of documents and construction info
4) errors discrepancies and divergences
5) CDP design work
6) fees, royalties and patent rights
7) unfixed materials and goods
8) adjustment of completion dates and relevant events
9) practical completion, lateness and Liquidated damages
10) partial possession
11) defects
Where are the Contractors Obligations found a JCT contract?
Section 2 - Contractors Obligations
What are some key clauses in Section 2 - Contractors Obligations
Clause 2.28 - EOT:
the Contractor shall not be entitled to any extension of time for the completion of the whole or any part of the Works if and to the extent that the delay arose by reason of any default, negligence or breach of contract or breach of statutory duty, whether by act or omission of the Contractor and/or the Contractor’s Persons (or their respective servants or agents).”.
Clause 2.29 - (List of) Relevant events
What is included in Section 3 of JCT contracts?
Section 3 = Control of the works
Contractor providing access to Architect/Contract Administrator
Site management
Co-operation with statutory bodies, CDM
Provision of sub contracts
H&S
Early Warning Notices
Where are the Control of the Works provisons found a JCT contract?
Section 3 = Control of the works
Contractor providing access to Architect/Contract Administrator
Site management
Co-operation with statutory bodies, CDM
Provision of sub contracts
H&S
Early Warning Notices
What are some key clauses in Section 3 - Control of the works.
Clause 3.1.2: “The Contractor shall provide access to enter upon the Site, all facilities and equipment for the Employer, the Landlord and/or the Architect/Contract Administrator and/or any other person(s) authorised by them:
Clause 3.23 (CDM Regulations): “Each Party undertakes to the other that in relation to the Works and the Site it will duly comply with the CDM Regulations.
Clause 3.26 (Early Warning Notice) The Contractor shall give an early warning by notifying the Architect/Contract Administrator in writing within five (5) Business Days of the Contractor becoming aware of any matter which could:
.1 increase the Contract Sum;
.2 delay a Completion Date; and/or
.3 impair the performance of the completed Works.
What is included in Section 4 of the contract?
Section 4 = Payment
Contract sum and adjustments
Interim payments
Payless notices
Retention
Loss and expense
Where are the Payment terms found a JCT contract?
Section 4 = Payment
VAT
Contractor’s Payment Applications and Payment Notices
Interim and final payments – final date and amount
Pay Less Notices and other general provisions
Retention
Relevant Matters
What are some key clauses in Section 4 - Payment.
Clause 4.10 (Contractor’s Payment Applications and Payment Notices)
Clause 4.11 (Interim and final payments – final date and amount)
Clause 4.12 (Pay Less Notices and other general provisions)
Clause 4.22 (Relevant Matters)
What is included in Section 5 of the contract?
Section 5 = Variations
Where are Variations found a JCT contract?
Section 5 = Variations