APC mock feedback topics Flashcards
In appointment docs for consultants how is termination handeled?
Client: They may termiante a consultant ot suspend the performance of services any time after 7 days upon written notice to the consultant
Consultant: If client is in material breach of the appointment, and fails to remebedy within 14 days notice from the consultant specifying the issue - the consutlant can termiante the appointment via written notice.
If a consultant is suspended when can a party terminate the engagement?
If a suspension continues for more than three months, either party may terminate the Consultant’s engagement.
Termination of the Consultant’s engagement is permitted in what circumstances?
• unilaterally by the Client on 14 days’ notice to the Consultant
• by either party if the other is in material breach of its obligations under the Appointment and fails
to remedy that breach within seven days of being asked to do so
• by either party if the other becomes Insolvent under sections 123 or 268 of the Insolvency Act 1986
or
• by either party if the Client orders a suspension of the Services and the suspension continues for
more than three months.
Upon suspension of a party are any payments returned?
The client must pay fair and resonable amount for completed fee up to the dat os suspension.
The client must pay reasonable costs/expenses (except those for a breach of care).
The consultant must hand over any completed project works.
What is assignment?
An assignment is the transfer of the benefit of a party’s contractual rights. It does not transfer a party’s obligations.
I.e. A Main Contractor will transfer the benefit (payment) to a subcontractor, but the obligations of the original contract are still with the Main Contractor.
What are partnering agreements.
A partnership agreement is a contract between all parties involved in starting a partnership structured business. The contract covers the rights & responsibilities of each partner.Partnering is a broad term used to describe a collaborative management approach that encourages openness and trust between parties to a contract.
Often used on large, long term, high risk contracts.
What is a framework agreement?
- An agreement with suppliers
- Instead of negociating new contracts every time, an agreement is set up that defines:
1) Prices
2) Programmes / time scales
3) quality standards
Therefore when a new project is found - procurement can begin immediately instead of negociating from scratch.
It’s like having a go-to team ready whenever you need them to build something.
What is partnering
By working together closely and sharing responsibilities, construction partnering agreements help projects run smoother and often result in better outcomes for everyone involved.
Team Formation: First, the project owner (like a company or government) teams up with the main contractor and maybe some key subcontractors or suppliers. They all sit down together and decide to work closely as a team.
Shared Goals: Next, they agree on the goals of the project. This includes things like timelines, budgets, and quality standards. Everyone commits to these goals together.
Open Communication: Communication is key! They make sure to keep each other in the loop about everything related to the project. If there are any issues or changes, they talk about it openly and work together to find solutions.
Risk Sharing: Instead of one party taking all the risk, everyone shares it. That means if something goes wrong, they all work together to fix it, instead of pointing fingers.
Continuous Improvement: Throughout the project, they keep looking for ways to do things better. Maybe they find a more efficient way to lay bricks or a way to save money without cutting corners. They’re always striving to improve.
Can you give (or list) some examples of the approved doucments?
Approved document A - Structure
Approved document B - Fire Safety
Approved document C - Site preperation and resistance to moisture
Approved document D - Toxic substances
Approved document E - Resitance to the passage of sound
Approved document F - Ventillation
Approved document G - Sanitation, Hot Water, Water Effeciency
Approved document H - Combustion APlliances and Fuel Storage
Approved document K - Protection from falling, collision and impact
Approved document L - Conservation of fuel and Power
Approved document M - Access to and use of buildings
Approved document N - Glazing
Approved document P Electrical Safety - Dwellings
How do you assess a EOT claim?
1) Review the contract terms - i.e. JCT contracts define what is a relevant event.
2) Identify the Relevant Event - ensure it’s a defined event
3) Check for causation - review records, correspondance & evidence that supports the claim.
4) Ensure parties were notfied (as soon as resonanbly practical) and in line with notification procedures
6) Obtain agreement on acceptance/rejection of EOT (or dispute resolution if it all goes down hill).
The CA typically has 12 weeks to review the EOT docs after acknowledging them.
How would you go about setting a strategic programme?
1) Define project objectives
2) Divide project into phases
3) Establish as critical path
4) Establish durations
5) allocate resources
7) Set milestones
8) Communciate and review with team
9) Monitor and update programme regularly
Some key differences bettwen NEC and JCT?
NEC collaborative procurment style (I.e. framework agreements)
JCT traditional procurement style
NEC - Programme is a contract document
JCT - programme is not a contract document
NEC - emphasize collaborative disbute resolution
JCT - includes provisions for dispute resolutions: mediation, adjudication, arbitration, or litigation.
NEC - more equal risk allocation
JCT - most placed on contractor (associated with design, construction, and site conditions.)
NEC Administered by PM
JCT administered by CA / EA
What are the steps in an adjudication process?
1) Notice of adjudication - One party issues aformal Notice of Adjudication to the other party.
2) Appointment - an agreed neutral third party. Review process begins
3) Exchange of information - typically 7 days for both parties (depending on complexity)
4) Adjudicator hearing - both parties present thier case.
5) Adjudicators give a decision after 28 days - can then be extended by 14 days
Adjudicators decision is legally binding
Adjudicators may be predefined in Section 9 of the JCT contract.
(Section 9: Settlement of disputes, Mediation, Adjudication)
What are the steps in a mediation process?
Cases usually settle within 4 weeks.
Not usually legally binding unless legal documents drawn up.
1) Initiation - both parties agree to participate voluntarily
2) Appointment - an agreed neutral mediator. Review process begins
3) Preparation of information - pre discussions, exchange relevant info.
4) Mediation hearing - both parties present their case.
5) Facilitated negotiations - The mediator facilitates open and constructive communication between the parties
6) Negotiation and agreement - both parties work to agree a resolution based on mediators
7) Documentation - Once an agreement is reached, the terms are documented in a written agreement signed by both parties. This agreement is legally binding and serves as a formal resolution of the construction conflict.
Mediators may be predefined in Section 9 of the JCT contract.
(Section 9: Settlement of disputes, Mediation, Adjudication)
What is contained within the Conflict Avoidance and Dispute Resolution Guidance Note
It outlines the following:
1) Minimum level of service:
2) Conflict avoidance processes: Good management, Clear docs, record keeping, good payment practices
3) 3 pillars of dispute resolution
4) ADR - anything other than litigation
5) Standard contracts
6) Dispute escalation clauses -
7) Claim evaluations, I.e.
-Time (delay, extensions of time and liquidated damages)
- Money (changes of the scope of works, disruption, prolongation etc) and Quality (predominately defects)
What are types of pile foundations
- Precast: driven into the ground with impact hammers (end bearing)
- Precast - drilled then concrete poured (end bearing)
- Screw piles - screwed into place
- Sheet piles - basements, excavations
- Contiguous bored piles - a retaining wall consisting of concrete bored piles
How do you set up an RICS regulated firm?
1) Understand RICS rules of Conduct, RICS Professional Statement and relevant guidance and codes of practice
2) ID business structure and register with the appropriate regulatory authorities
3) Ensure at least one principal or director (minimum 25% of top brass) is a member of the RICS.
When is a firm required to register with the RICS?
- When a firm provides surveying services to the public
- The firm must operate in Regulated Area A (the UK)
- at lease 50% of the firms principals are RICS members
When is a firm eligible to register with the RICS?
a) the Firm provides surveying services to the public and
b) at least 25% of the Firm’s Principals are RICS Members
What is the procedure for registration with the RICS?
a) provide information to RICS in such form as prescribed by the Standards and Regulation Board
b) agree that RICS may share relevant information about the Firm with government or other regulatory bodies as appropriate and
c) agree that if RICS declines to register the Firm, RICS may publish its decision.
What are the obligations of RICS registration
Rules, Laws, Money
1) Comply with the rules of conduct
2) Act in accordance with RICS charter and bye laws
3) Pay annual fees
What voltage are tools?
110V (Note main eletricity is 230V)
What is the process for agreeing a valuation?
JCT contract section 4 - payment
1st – contractor submits application for payment
2-8th day – QS undertakes valuation
8th day – due date for CA to receive valuation (7 days after)
13th day (5 days after) – I issue payment certificate as the CA
17th day (8 days after) – client issues pay less notice if applicable (5 days before the due date).
22nd final date for payment (14 days after due date of valuation cert). JCT contract states 14 day time period between due date and final date for payment
However this is often amended to 21 or 28 days for some clients
What is the base date in a contract?
The “base date” is a crucial reference point that establishes various aspects of the contract, including:
1) the commencement of the contract,
2) the calculation of time periods,
3) the determination of rates and prices,
4) the impact of change
5) Documentation and records - key reference point for maintaining accurate records, correspondence, and documentation related to the contract.
Can you describe what the following terms mean?
1) Shell and core
2) Category A
3) Category B
Shell and core refers to the basic structure and external envelope of a building, including the main structural elements, exterior walls, roof, and common areas such as lobbies, stairwells, and elevators. Does not include M&E, finishes, partitions. Basic unfinished
Category A refers to the basic level of fit-out provided by a landlord or developer within a building’s interior spaces. It includes the installation of basic finishes, fixtures, and M&E services. Typically includes items such as raised floors, suspended ceilings, basic lighting, heating, ventilation, and air conditioning (HVAC) systems, fire detection and alarm systems, and basic sanitary facilities. Category A fit-out is intended to provide a neutral and flexible base for tenants to build upon and customize according to their specific needs and preferences.
Category B refers to the tenant-specific fit-out and customization of interior spaces within a building. It includes the design and installation of interior partitions, finishes, fixtures, and fittings to meet the specific requirements and preferences of the tenant. Category B fit-out may include items such as partition walls, floor finishes, ceiling finishes, lighting, power and data outlets, IT infrastructure, furniture, and signage, tailored to the tenant’s layout, branding, and operational needs.
What is a Special Purpose Vehical (SPV)?
a Special Purpose Vehicle (SPV) in finance is like a separate box or container set up by a company for a specific job. It’s not part of the company itself, but it’s created to handle certain tasks or projects.
SPVs are used for different reasons, like raising money for a specific project, keeping risky assets separate to protect the company, or making complex financial deals. They’re like tools that companies use to organize their finances in a smart and efficient way.
How would you ensure the Employers Requirements are captured in the brief?
1) Discuss with the client
2) Review documentation (businees structure docs, potential site information).
3) Engage with stakeholders
4) Workshop and interviews to gain in depth knowledge
5) Develop a brief
6) Client Review and Approval
7) Set document control process to manage revisions
8) Continuous Communication and Review:
What are the stages in obtaining planning permission?
1) Pre-Application Stage: Engage with local planning authority for pre app advice.
2) Site assessment and Design: Conduct a through assessment of the site
3) Preperation of application: Prepare a comprehensive planning application package, including completed application forms, site location plans, existing and proposed site drawings, design and access statements, environmental assessments
4) Submission to local planning authority (and pay any fees)
5) Public consultation: The planning officer will assess the planning application against relevant planning policies, statutory requirements, and local development plans
6 Decision and appeal: The LPA will make a decision on the planning application within a specified timeframe, usually within eight weeks for most applications (or 13 weeks for major developments). The decision may be approval, approval with conditions, refusal, or deferral for further information.
If a client was prepared to pay in advance for your services, how would you do this
Set up separate client account, clearly identifying persons name
Send them a statement of account
Agree bankking terms of conditions interest rates, handling costs
Prior to drawing money, send a statement of amount to be withdrawn and amount to withdrawn from it
Once complete share final statement ensuring everything is complete and transparent
Send professional note
What is a project audit?
Internal review of project processes and controls
Something you could do mid way through – is there anything else we should be doing to achieve our objective
Any lessons learnt – should be completed at the end of the job – part of professional competence
What is ISO 9001
International standard for quality control
Demonstrate consistently being able to meet client requirements