ITTO Flashcards
“Initiating
4.1 Develop Project Charter ITTO”
“I: 1.Project statement of work 2.Business case 3.Agreements 4.Enterprise environmental factors 5.Organizational process assests
T&T: 1.Expert judgment 2.Facilitation techniques
O: 1.Project charter”
“Planning
4.2 Develop Project Management Plan ITTO”
“I: 1.Project charter 2.Outputs from other processes 3. Enterprise environmental factors 4.Organizational process assets
T&T: 1.Expert judgment 2.Facilitation techniques
O: 1.Project management plan”
“Executing
4.3 Direct and Manage Project Work ITTO”
“I: 1.Project management plan 2.Approved change requests 3. Enterprise environmental factors 4.Organizational process assests
T&T: 1.Expert judgment 2.Project management information system 3.Meetings
O: 1.Deliverables 2.Work performance data 3.Change requests 4.Project management plan updates 5.Project documents updates”
Monitoring and Controlling
4.4 Monitor and Control Project Work ITTO
INPUT
- Project management plan
- Schedule forecasts
- Cost forecasts
- Validated changes
- Work performance information
- Enterprise environmental factors
- Organizational process assets
TOOLS:
- Expert Judgment
- Analytical techniques
- Project management information system
- Meetings
O:
- Change requests
- Work performance reports
- Project management plan updates
- Project documents updates
“Monitoring & Controlling
4.5 Perform Integrated Change Control ITTO”
” I: 1.Project management plan 2.Work performance reports 3.Change requests 4.Enterprise environmental factors 5.Organizational process assets
T&T: 1.Expert judgment 2.Meetings 3.Change control tools
O: 1.Approved change requests 2.Change log 3.Project management plan updates 4.Project documents updates”
“Closing
4.6 Close Project or Phase ITTO”
“I: 1.Project management plan 2.Accepted deliverables 3.Organizational process assets
T&T: 1.Expert judgment 2.Analytical techniques 3.Meetings
O: 1.Final product, service, or result transition 2.Organizational process assets updates”
“Planning
5.1 Plan Scope Management ITTO”
“I: 1.Project management plan 2.Project charter 2.Enterprise environmental factors 4.Organizational process assets
T&T: 1.Expert judgment 2. Meetings
O: 1.Scope management plan 2.Requirements management plan”
“Planning
5.2 Collect Requirements ITTO”
“I: 1.Scope management plan 2.Requirements management plan 3.Stakeholder management plan 4.Project charter 5.Stakeholder register
T&T: 1.Interviews 2.Focus groups 3.Facilitated workshops 4. Group creative techniques 5.Group decision-making techniques 6.Questionaires and surveys 7.Observations 8.Prototypes 9.Benchmarking 10.Context diagrams 11.Document analysis
O: 1.Requirements documentation 2.Requirements traceability matrix”
“Planning
5.3 Define Scope ITTO”
“I: 1.Scope management plan 2.Project charter 3.Requirements documentation 4.Organizational process assets
T&T: 1.Expert judgment 2.Product analysis 3.Alternatives generation 4.Facilitated workshops
O: 1.Project scope statement 2.Project documents updates”
“Planning
5.4 Create WBS ITTO”
“I: 1.Scope management plan 2.Project scope statement 3.Requirements documentation 4.Enterprise environmental factors 5.Organizational process assets
T&T: 1.Decomposition 2.Expert judgment
O: 1.Scope baseline 2.Project documents updates”
“Monitoring & Controlling
5.5 Validate Scope ITTO”
“I: 1.Project management plan 2.Requirements documentation 3.Requirements traceability matrix 4.Verified deliverables 5.Work performance data
T&T: 1.Inspection 2.Group decision-making techniques
O: 1.Accepted deliverables 2.Change requests 3.Work performance information 4.Project documents updates”
“Monitoring & Controlling
5.6 Control Scope ITTO”
“I: 1.Project management plan 2.Requirements documentation 3.Requirements traceability 4.Work performance data 5.Organizational process assets
T&T: 1.Variance analysis
O: 1.Work performance information 2.Change requests 3.Project management plan updates 4.Project documents updates 5.Organizational process assets updates”
“Planning
6.1 Plan Schedule Management ITTO”
“I: 1.Project management plan 2.Project charter 3.Enterprise environmental factors 4.Organizational process assets
T&T: 1.Expert judgment 2.Analytical techniques 3.Meetings
O: 1.Schedule management plan”
“Planning
6.2 Define Activities ITTO”
“I: 1.Schedule management plan 2.Scope baseline 3.Enterprise environmental factors 4.Organizational process assets
T&T: 1.Decomposition 2.Rolling wave planning 3.Expert judgment
O: 1.Activity list 2.Activity attributes 3.Milestone list”
“Planning
6.3 Sequence Activities ITTO”
“I: 1.Schedule management plan 2.Activity list 3.Activity attributes 4.Milestone list 5.Project scope statement 6.Enterprise environmental factors 7.Organizational process assets
T&T: 1.Precedence diagramming method (PDM) 2.Dependency determination 3. Leads and lags
O: 1.Project schedule network diagrams 2.Project documents updates”
“Planning
6.4 Estimate Activity Resources ITTO”
“I: 1.Schedule management plan 2.Activity list 3.Activity attributes 4.Resources calendars 5.Risk register 6.Activity cost estimates 7.Enterprise environmental factors 8.Organizational process assets
T&T: 1.Expert judgment 2.Alternative analysis 3.Published estimating data 4.Bottom-up estimating 5.Project management software
O: 1.Activity resource requirements 2.Resource breakdown structure 3.Project documents updates”
“Planning
6.5 Estimate Activity Durations ITTO”
“I: 1.Schedule management plan 2.Activity list 3.Activity attributes 4.Activity resource requirements 5.Resource calendars 6.Project scope statement 7.Risk register 8.Resource breakdown structure 9.Enterprise environmental factors 10.Organizational process assets
T&T: 1.Expert judgment 2.Analogous estimating 3.Parametric estimating 4.Three-point estimating 5.Group decision-making techniques 6.Reserve analysis
O: 1.Activity duration estimates 2.Project documents updates”
“Planning
6.6 Develop Schedule ITTO”
“I: 1.Schedule management plan 2.Activity list 3.Activity attributes 4.Project schedule network diagrams 5.Activity resource requirements 6.Resource calendars 7.Activity duration estimates 8.Project scope statement 9.Risk register 10.Project staff assignments 11.Resource breakdown structure 12.Enterprise environmental factors 13.Organizational process assets
T&T: 1.Schedule network analysis 2.Critical path method 3.Critical chain method 4.Resource optimization techniques 5.Modeling techniques 6.Leads and lags 7.Schedule compression 8.Scheduling tool
O: 1.Schedule baseline 2.Project schedule 3.Schedule data 4.Project calendars 5.Project management plan updates 6.Project documents updates”