Integration Management Flashcards

1
Q

What is a business case?

A

necessary information to get the project initiated

why a business should do this project

-cost-benefit analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

Develop project charter

A

a document that formally authorizes the project or phase and documents initial requirements to satisfy stakeholders

defines the authority of the PM

senior management’s written approval to start the project

links the project to the overall company goals

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the methods that can be used to select a project?

A

benefit-cost ration (BCR)
internal rate of return
opportunity cost
payback period
economic value added (EVA)
Present Value (PV)
Net present value (NPV)
return on investment (ROI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Benefit management plan

A

describes the main benefits that the project will produce once it is completed

generally created by doing a cost-benefit analysis of whether the project should proceed or not and using different business cases as to why the project is needed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Agreements

A

contracts

should be signed before the project starts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a project charter?

A

document that officially authorizes the project to get started

contains:
-project justification and purpose
-name of project manager
-assignment of authority to the project manager
-signature of sponsor (senior management) or others authorizing the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Develop a project management plan

A

process of creating the project management plan that includes all subsidiary plans and baselines

only an approved change request can change a plan once it has been approved

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a change management plan?

A

outline how change requests will be collected, assessed, authorized, and incorporated into the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a configuration management plan?

A

outline how the various components of a project can be configured

how are you going to update the plan once the deliverables are given

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is performance measurement baseline?

A

checks the performance of the project as it is being executed

integrates scope, schedule, and cost into a single baseline that is used to track performance of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the 2 components that the project management plan is broken into?

A

-management plans

-baselines

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is knowledge management?

A

the main objective so the PM can use the knowledge that is gaoined throughout the project

explicit or tacit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is information management?

A

ensures that all info is avaliable to stakeholders when needed

Ex: websites, articles, libraries, documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly