Instalation, Leveling and Alignment Flashcards
Machine units that do not share a common baseplate and require alignment to
other units should not be mounted directly onto a foundation. They are set and
fastened to.
A) Bedplates C) Foundation plates
B) Soleplates D) Grout
B: Soleplates
Machine units must be installed in a particular order to ensure satisfactory
operation of the equipment. Select the proper order below.
A) Primary equipment, prime mover, transmission unit.
B) Prime mover, primary equipment, transmission unit.
C) Primary equipment, transmission unit, prime mover.
D) Prime mover, transmission unit, primary equipment.
C Primary equipment, Transmission unit, Prime mover
Which one of the following steps is not important when installing machines?
A) Leveling C) Alignment
B) Torquing D) Testing
B Torquing
If attachments to machine units (piping, ducts, etc.) cause misalignment from
the specified tolerances, the attachments should be.
A) Connected with flexible hose C) Installed with baffles
B) Adjusted to eliminate forces D) Isolated from vibration
B; adjusted to eliminate forces
Various methods are employed to mount and secure machines in place. The
method used must support the machine without distorting it as well as…
A) Eliminate soft foot C) Avoid grout pockets
B) Absorb eddy currents D) Absorb vibration
D: Absorb Vibrations
In modern manufacturing facilities, mobility of equipment is very important.
How is this accomplished when installing machines?
A) Self-leveling mounts C) Vibration isolators
B) Adjustable foundations D) Adjustable mounts
D: Adjustable mounts
To prevent the amplification of internal stresses which cause misalignment and
wear of machine elements as well as absorbing vibration these devices are
installed.
A) Self-leveling mounts C) Vibration isolators
B) Adjustable foundations D) Adjustable mounts
C: Vibration Isolators
This procedure in foundation work eliminates concern about foundation
shrinkage as well as providing space for shimming to elevation.
A) Pouring to minus elevation C) Pouring with additives
B) Pouring grout with concrete D) Pre-installing anchor bolts
A: Pouring to a minus elevation
The primary purpose of this component is to secure machine units to the
baseplate, soleplates, or structural steel foundation.
A) Anchor bolt C) Hold-down bolt
B) Hold-down screw D) All of the above
C: Hold down bolt
Straight anchor bolts without deformed ends should be set into the foundation
concrete to a depth of.
A) 4 times their diameter C) 10 times their diameter
B) 8 times their diameter D) 25 times their diameter
D: 25 times the Diameter
When anchor bolts have deformed ends, the length of the bent leg should be?
A) 4 times their diameter C) 10 times their diameter
B) 8 times their diameter D) 25 times their diameter
A: 4 times the diameter
This type of anchor bolt is preferred to fixed anchor bolts as they allow the bolt
to be moved slightly in case of an error in hole layout.
A) Tube anchor bolt C) Grout anchor bolt
B) Flexible anchor bolt D) Canned anchor bolt
A: Tube anchor bolt
Some hold-down bolts are subject to severe vibration and are liable to break at
the thread section. What type of anchor bolt is used in these cases?
A) Extra thick anchor bolts C) Pipe anchor bolts
B) Tube anchor bolts D) Boxed anchor bolts
D: Boxed anchor bolt
Where anchor bolts need to be installed in existing concrete this style of anchor
bolt is most often used.
A) Resin anchor bolt C) Mechanical expansion anchor
B) Hydraulic expansion anchor D) Cementitious anchor
C: Mechanical expansion anchor
This component assists in locating, setting and holding anchor bolts in place
while the cement cures.
A) Baseplate C) Soleplate
B) Bedplate D) Template
D: Template
These lines are established on the machine base or baseplate for both the length
and the width of the machine base and are used to establish the exact position of
the machine.
A) Bench lines C) Permanent lines
B) Center lines D) Foundation lines
B: Center Lines
These lines are used to establish a machine’s elevation and horizontal position.
A) Benchmarks C) Center lines
B) Foundation lines D) Piano lines
A: Benchmarks
This component placed under each leveling screw or bolt prevents the end from
digging into the foundation and stops the machine from moving out of position
(walking) when it is tightened down?
A) Leveling washers C) Leveling isolators
B) Leveling wedges D) Leveling shims
A: Leveling washers
This component supports the weight of the machine that is set directly to the
floor and not grouted in place. It screws into threaded holes provided in the
machine base.
A) Anchor bolt C) Leveling bolt
B) Hold-down bolt D) Leveling screw
D: Leveling screw
This component is often used to raise machine units so that shims may be
inserted or removed when aligning and leveling units vertically.
A) Jacking screws C) Leveling screws
B) Leveling bolts D) Elevator bolts
A: Jacking screws
Flat metal plates that provide a permanent firm adjustable support at points
where weight will be concentrated (anchor bolt locations) are known as !!!
A) Wedges C) Leveling washers
B) Shims D) Bench plates
B: Shims
A structural filler that is the critical connection that links the bed or soleplate to
the concrete foundation is known as !!!!
A) Resin C) Grout
B) Epoxy D) Concrete
C: Grout
The major advantage that polymeric structural filler has over other types is.
A) Moisture resistant C) Corrosion resistant
B) Vibration resistant D) All of the above
D: All of the above
During the installation of transmission, primary and prime mover units it is
sometimes necessary to ensure permanent alignment. This is accomplished by
using???
A) Epoxy resins C) Rigid couplings
B) Grout D) Taper dowel pins
D: Taper doewl Pins
Why is concrete mix not used to grout anchor bolts in machine foundations?
A) It is too rough when cured C) It cures too slowly
B) It can’t withstand compression D) It shrinks when cured
D: It shrinks when it cures
Normal cement concrete reaches 100% of its compressive strength within how
many days?
A) 28 days C) 10 days
B) 17 days D) 3 days
A: 28 Days
Normal cement concrete reaches its desired working strength in how many
days?
A) 28 days C) 7 days
B) 18 days D) 3 days
C: 7 Days
Air-entrained concrete should be used where the hardened concrete will be
subjected to….
A) Vibration C) Excessive moisture
B) Freezing & thawing D) Shock loading
B: Freezing and thawing
What type of concrete is easier to pour and place and requires less working to
assume the shape of the form?
A) Wet consistency C) Stiff consistency
B) Dry consistency D) Medium consistency
A: Wet consistency
The foundation of a machine which is subjected to critical alignment is poured
with the concrete level at a minus elevation. What is that minus elevation?
A) ½” to ¾” C) 7/8” to 1 9/16”
B) ¾” to 1 ½” D) 1” to 1 5/8”
B: 3/4” to 1 1/2” 19mm - 38mm
What type of misalignment is always corrected first?
A) Horizontal parallel (offset) misalignment
B) Horizontal angular misalignment
C) Vertical parallel (offset) misalignment
D) Vertical angular misalignment
D: Vertical angular misalignment
If during normal operation the driven machine expands due to thermal
conductivity, the drive unit must first be aligned in what manner?
A) Within normal limits C) Higher than the driven unit
B) Lower than the driven unit D) In the horizontal plane
C: Higher than the driven unit
The condition within machinery that causes reduced bearing life, coupling
damage, high vibration levels and reduced seal life is referred to as?
A) Resonance C) Critical speed
B) Soft foot D) Misalignment
D: Misalignment
These items (usually placed in packs) are placed under the mounting feet of the
drive unit to align it in the vertical plane?
A) Wedges C) Feeler gages
B) Shims D) Pack gages
B: Shims
The devices used to push the equipment from side to side on the horizontal plane
to correct alignment are called?
A) Jacking bolts C) Leveling screws
B) Alignment screws D) Elevator bolts
B: Alignment screws
Sometimes machining errors cause coupling runout. When the coupling bore is
machined at an angle to its axis it is called?
A) Angular runout C) Eccentric runout
B) Wobble D) Total runout
A: Angular runout