IDPX 6 - Contract Administration Flashcards

1
Q

What is a performance bond?

A

This is a statement by a surety company that obligates the surety company to complete construction of hte owner’s project if the contractor defaults.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the purpose of a labor and material payment bond?

A

This is used to guarantee payment for labor and materials on a project if the contractor defaults or otherwise fails to make payments.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

At an owner’s request, a contractor may include alternates in teh bid documents. What is an alternate?

A

This is a construction item that could, at the owner’s discretion, be substituted for a similar item in the base bid to reduce project costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a unit price?

A

This is a set cost for providing a portion of the construction work that is based on an individual quantity, such as per unit or per square foot.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is an allowance in interior design?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are four types of written modifications that can be made after the execution of a contract?

A

Four examples of this are

  • a change order
  • an amendment to the contract
  • a written order for minor changes in the work
  • a written interpretation by the interior designer
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is retainage (also called holdback in Canada)?

A

This is a percentage (usually 10%) of each payment to a contractor or vendor that is withheld by the owner for th epurpose of protecting the owner against incomplete or defective work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What form does a vendor or contractor use to request a payment from the owner?

A

An application for payment form is used for this.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

In regard to interior design, what is substantial completion?

A

In a construction project, this is the stage when the work, or a designated portion of it, is sufficiently complete according to the contract documents that the owner can occupy or sue the site, even though a few minor items may yet need to be finished or corrected.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Who has the authority to stop construction?

A

On a construction project, only the owner can authorize this action.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a change order?

A

This is a form used to authorize a change in contract time, contract cost, or both, made after the execution of the contract. It is generally prepared by the interior designer and must be signed by the designer, contractor, and owner.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are shop drawings?

A

These are detailed drawings, diagrams, and other data, prepare by a subcontractor or supplier, that show exactly how the provider intends to supply and install work to meet the contract requirements. They are submitted to the contractor and interior designer for approval.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the basic process for getting approval on submittals from subcontractors or suppliers?

A
  • First, the submittal is sent to the general contractor, who reviews it and sends it to the interior designer for approval.
  • If the submittal also requries a review by one of the designer’s consultants, it is sent ot the consultant for review.
  • The submittal is then sent back to the contractor, who returns it to the party who originally made the submittal.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the interior designer’s obligations during construction observation?

A

During this phase of the work, the interior designer msut

  • become generally familiar with the progress and quality of the work
  • keep the owner informed about the progress of the work
  • endeavor to gaurd the owner against defects in the work
  • determine, in general, if the work is progressing in such a way that it is in accordance with the contract documents
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Who has the authority to reject work that does not conform ot the contract documents?

A

The interior designer can reject work that does not conform to these.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a claim in interior design?

A

This is a demand or assertion by the contractor or owner seeking payment of money, an extension of time, or an adjustment or interpretation of the contract terms.

17
Q

What are two common types of construction claims?

A

Two common types are

  • claims for additional time
  • claims for concealed or unknown conditions
18
Q

What are six things the interior designer is NOT responsible for during contract administration?

A

During this phase of a project, the designer is NOT responsible for

  • the means, methods or techniques of construction
  • safety on the job site
  • fabrication, shipment, or installation of construction elements or furnishings
  • acts or omissiosn of contractos, subcontractors, or suppliers
  • stopping the works if there are problems
  • receipt, inspection, ad acceptance of furniture or fixtures
19
Q

What is a construction change directive?

A

This is a written order, prepared by the interior designer, directing the contractor to make a chagne before the owner and contractor have agreed onthe amount of adjustments in cost, time or both.

20
Q

What are six common reasons why a designer might withhold payment to a contractor?

A

This action might be taken because

  • the work is defective
  • the contractor failed to pay the subcontractors
  • the contractor has damaged the property of the owner or another contractor
  • third-party claims have been filed
  • evidence existing that the work will not be completed on time
  • the contractor failed to conform to the contract documents
21
Q

What is a punch list (known in Canada as a deficiency list)?

A

This is a list of items made by the interior designer during hte final inspection. It includes anything that needs to be completed or corrected by the contractor if not in accordance with teh contract documents.

22
Q

What is a purchase order?

A

This is a document sent to a manufacturer or vendor that lists all the items to be purchased along with the prices, catalog numbers, and shipping information.

23
Q

What is required from a manufacturer after it receives a purchase order from the designer?

A

A confirmation or acknowledgement is required from the manufacturer after receiving this from the designer.

24
Q

What is a packing list?

A

This is a detailed list of item descriptions and quantities in a shipment that is attached to one of the items shipped.

25
Q

What is a drop ship order?

A

This is a request to ship furniture or other goods to an address different from the address of hte company placing the order.

26
Q

What is a bill of lading?

A

This is a document that lists the contents of a shipment from a manufacturer or vendor.

27
Q

What is a freight bill?

A

This is the invoice from a shipping company?

28
Q

What is a sales agreement?

A

This is a document signed by the client that obligates the client to pay for the various items listed in the agreement.

29
Q

If all bids on a project exceed the owner’s budget, what four options are available to the owner?

A

If this happens, the owner can

  • rebid (or renegotiate) the contract
  • authorize an increase in construction costs
  • work with the designer to reduce the scope of a proejct
  • abandon the project
30
Q

What are seven of the items the contractor must submit to the owner during project closeout?

A

During this phase of a project, the contractor must give the owner

  • the bonds
  • all warranties
  • any extra stock of materials
  • a set of record drawings
  • teh certificate of occupancy
  • documentation required by the final application for payment
  • maintenance contracts and equipment operating instructions
31
Q

What are the five basic activities of project management?

A

The task involves five basic activities.

  • planning
  • monitoring
  • coordinating and directing
  • documenting
  • closing out a project
32
Q

What are the two common ways to notify prospective contractors that a project is being bid?

A

The two common ways to accomplish this are to

  • advertise for bids in local newpapers and trade journals
  • send invitation to bid forms to prospective bidders
33
Q

What is an addendum?

A

This is a written or graphic document issued by the interior designer before the execution of the contract that modifies or interprets the bididng documents by additions, deletions, clarifications, or corrections.

34
Q

Under what conditions can a contractor propose substitutions during bidding?

A

Bidders must request written approval of these at least 10 days before bid opening. The request must include documentation showing that the proposal meets the requirements of the contract document.

35
Q

What seven types of information are typically included in the instructions to bidder?

A

This document typically gives information about

  • procedures for submitting bids
  • where to obtain bidding documents
  • procedures for opening bids
  • submittal required with the bids
  • bidders’ representation statements
  • required bonds
  • procedures for issuing addenda and other modifications
36
Q

What is bid security?

A

This is a certified check, cashier’s check, or bid bond requested by the owner to ensure that teh successful bidder will fulfill the contract.