IDPX 1 - Project Coordination Flashcards
What is building commissioning?
This is the process of inspecting, testing, starting up, and adjusting building systems and then verifying that the systems are operating as intended ane that they meet the design criteria.
How does an independent furniture rep differ from a manufacturer’s rep?
This type of furniture representative is self-employed and may represent more than one manufacturer.
What type of schedule is this?
This is a graphic representation of a critical path method (CPM) schedule.
What type of scheduling chart looks like a bar graph?
A gantt chart looks like this.
What client-approved document should be available to the designer before the schematic design process begins?
Good business practice requires that a client-approve program be available before this phase of work begins.
What are five of the most common variables that can affect the cost of a project when bidding occurs?
This aspect of a project bid can be affected by the
- actual costs to the contractor and subcontractors
- current competitiveness of the market
- project schedule
- desire of a contractor to get the job
- level of profit required by the contractor
On an interior construction project, who is responsible for the final electrical drawings?
On an interior construction project, the electrical engineer is responsible for this aspect of the plans.
Which consultant is responsible for designing new openings in the floor of an existing building?
The structural engineer is responsible for designing openings in the floor of this type of building.
Which consultant must assist the interior designer when a project requires the installation of heavy equipment?
A structural engineer must assist the interior designer in determining the installation requirements for this type of equipment.
Who may design a building’s sprinkler system?
This building component may be designed by either a mechanical engineer, a fire protection engineer, or in some cases, a fire protection contractor.
In determining the total time required for a project, who is responsible for estimating the construction time?
The contractor is responsible for this aspect of the total project schedule.
Who is responsible for determining the accuracy and completeness of dimensions, details, and quantities on shop drawings?
The contractor is responsible for these items on shop drawings.
Who is responsible for providing any laboratory tests, inspections, and reports required by the contract documents?
When these procedures are required by the contract documents, the owner must provide them.
What is involved in generating a fee project?
In this process, the total fee the designer will receive, after amounts for profit, overhead, and other expenses are deducted, is allocated to the schedule and to the various staff members who will be completing the project.
What four tasks does the interior designer normally perform during the schematic design phase of a project?
During this phase of a project, the designer
- Prepares diagrams and drawings showing the general functional relationships required by the project
- develops preliminary space plans
- prepares design concepts, including colors, finishes, and furniture
- prepares a preliminary statement of probable project costs