Heavy Construction Flashcards

1
Q

What type of system do you use to carry water under a road?

A

Culvert

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What business structure is usually time-limited?

A

Joint venture

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How much time does employer have to orally report a work-related accident that results in the fatality of one or more employees

A

8 hours

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the average length of time a slump test takes from start to finish

A

2 1/2 minutes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

If an employee is injured on the job, how long does the employer have to notify office of Worker’s Compensation administration

A

10 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The safety margin used when choosing wire rope is determined by dividing by

A

5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How far should trash be kept from a pump station?

A

10’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The amount a building or structure might settle is governed by the

A

Compressibility of the soil

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What happens to a partnership if one dies?

A

It dissolves and assets must be sold to pay creditors and partners

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How do you increase pressure when using a centrifugal pump?

A

Decrease velocity of liquid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What type of compaction testing requires the drilling of 1/2”x 12” hole?

A

Nuclear

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A device used for lifting a long steel member when the member cannot be lifted from its center is called

A

Balance beam

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

According to OSHA the maximum height of open yard storage of lumber when using a machine is

A

20’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

If the top of a spoils bank is greater than the adjoining surface, what is it called?

A

Embankment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Corrugated metal pipe (draw pipe) comes in what multiple lengths?

A

2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A column that is a integral of a wall, or a column that projects from a foundation wall is called a

A

Pilaster

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What are batter boards?

A

Horizontal bars fastened to posts at strategic points in the building

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

A __________ is used for a test to measure compression strength in concrete.

A

Cylinder

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

How many feet above high tide should a compressor station be put?

A

3’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Adding water to concrete that is already workable will decrease the concretes

A

Strength

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Who would not be paid first under the Louisiana mechanic lien law?

A

General contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Which is not used for the core of a wire rope?

A

BC or AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What would you use to protect the banks around a body of water to prevent washout?

A

Rip rap

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is the best foundation material for skyscrapers or large buildings?

A

Bedrock

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

When you have rebar going in one direction, the temperature bars should be installed

A

At right angles or 90°

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Which one of the following estimating methods is the least detailed?

A

Square foot method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

In highway construction, what is the basis for grading, earthwork, etc?

A

Centerline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

A caisson is similar to what type of pile?

A

Cast in place pile

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Profit margin indicates

A

The after-tax profit on revenues

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Independent contractor payments are reported on form

A

1099

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

How far do combustibles need to be stored from tanks

A

50’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

A concept that is aimed toward reducing conflicts and claims on a project is known as

A

Partnering

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

While dewatering a site using a wellpoint system, you notice muddy water coming from the pump. Which of the following should you do?

A

Set the wellpoints deeper into the water table

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Blue smoke rising from a batch of hot mix asphalt may indicate

A

Overheating in the mix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

When are concrete cylinders tested?

A

At 28 days unless otherwise specified

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

What is the outside diameter for #6 rebar?

A

3/4”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Gas line that connects production facility to transmission lines are called?

A

Gathering lines

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

A chain is measured in what type of increments?

A

Tenths of a foot

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

Plastic pipe used to convey gas can be placed how deep underwater?

A

200’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

What is the name used for the inside bottom elevation of a sewer pipe?

A

Invert

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

Who is responsible for purchasing a builders risk insurance policy?

A

General contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

What would be the best piece of equipment to use in wet clay soil to dig a 40 foot deep trench, with the least amount of movement?

A

Dragline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

The most common gauge of tie wire used in the installation of reinforcing steel is ________ gauge.

A

16

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

How is cost estimates on an excavation job?

A

Based on cubic yards of material to be hauled away

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

The main factor which determines the capacity of or rating of a crane is

A

Point at which crane will tip over

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

What tool is used to remove forms boards?

A

Wooden edge

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

Finally preforated pipes are driven into the ground around the perimeter of an area to be excavated. These pipes are connected to one or more aboveground pipes in order to maintain or reduce water table during the site construction.

A

Well point

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

The board is composed of ______ members

A

15

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

A commonly used method of displaying a project schedule is a

A

Bar chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

Other than sheet pile, what other type of metal pipe is there?

A

Tubular steel pipe

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

What is the name for a legal item that can be placed in a contract that will allow the terms to be dictated prior to acceptance of the contract?

A

Boiler plate provision

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

What is the minimum distance that a burn pit must be from a well or storage tank?

A

100’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

The strength of reinforcing steel is measured in

A

Lbs/in^2 tensile

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

In wet soil conditions, what describes the soil when a scraper or heavy equipment travels over it?

A

Pumping

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

The bottom of an incline is called:

A

Toe of the slope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

When referring to an engineers grading information stake, all measurement will be taken from

A

The hub

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

A motor grader with a pivot in the frame which is controlled by two hydraulic cylinders which control the direction is called

A

Articulated frame

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

What type of tool is used to drive a bolt in between two beams?

A

Maul

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

How far do combustibles need to be stored from tanks?

A

50’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

Who certifies that the project is partially complete for phase payments?

A

Architect or engineer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

When does the percentage of completion method of accounting for long term construction contracts recognize income?

A

Upon completion of specific phases of construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

What and who does a bond protect and give the right to collect additional funds

A

Owner, developer, or governmental agency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

Pipe is sized by

A

ID

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

What can be used to drive a pile in the place of a cushion?

A

Ring collar

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

What would be power injected into soil to improve its stability?

A

Lime

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

When concrete sewer pipe is installed at the end of the day what should be done to the exposed end of the pipe?

A

Watertight plug is installed to prevent dirt, rocks, or debris from entering system

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

What device is bolted to the blade of a grader to help when grading a road around curbs?

A

Curb shoe

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
73
Q

When Crosby-type wire rope clips are used assisting a u-bolt in a set, the U portion must be on _________

A

The dead end of the rope with all the clips in the same direction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
74
Q

Using fiber mesh in concrete will result in

A

Thinner thickness with less shrinkage cracks or control joints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
75
Q

Which is the best grade pipe?

A

A53 seamless Grade B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
76
Q

What is the minimum distance that a burn pit must be from a well or a storage tank?

A

100’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
78
Q

What increments to telephone poles come in?

A

5’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
79
Q

Whose responsibility is it to maintain project records and reports?

A

Super intendant

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
80
Q

Who would be paid first under the mechanics lien law?

A

Laborer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
81
Q

The piece of equipment most commonly used for placing concrete under water is

A

Tremie

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
83
Q

An overhead traveling crane is primarily used where

A

In a wastewater treatment plant

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
84
Q

What color are inflatable indicator vest?

A

Green

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
85
Q

How far should a spoil pile be placed from a trench?

A

2’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
86
Q

When is bull floating performed?

A

Shortly after screeding when there’s no visible surface water

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
87
Q

What should you do before applying primer to pipe?

A

Remove the mill scale

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
88
Q

What is the standard industry markup percentage added to an estimate?

A

15%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
89
Q

A copper wire is installed underground alongside a nonmetallic water main to ___________.

A

Locate a pipe at a later date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
90
Q

The density of soil is measured in

A

Maximum density

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
91
Q

Most accidental overturns in mobile cranes are a result of

A

Lifting a load with the wheels down

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
92
Q

What material is used for anodes?

A

Zinc or aluminum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
93
Q

In order for a scrapper operator to make a deeper cut, what would he do?

A

Lower the bowl

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
94
Q

Why do you put a breast board in between two beams?

A

To maintain spacing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
95
Q

What is the volume change called that occurs while excavating earth materials from the compacted position?

A

Soil swell

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
96
Q

Without a $10,000 net worth, how might a contractor obtain a license?

A

A letter of credit from a bank or surety bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
97
Q

What is not a type of pile?

A

Ring

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
98
Q

The laser used inside the sewer pipe installation is subject to change due to temperature variations along the length of the piping. What should be done to insure proper laser readings?

A

Blow air through the pipe

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
99
Q

Which ASTM designation is an all purpose carbon steel used widely in the industry?

A

A36

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
100
Q

At what height does OSHA require the use of a safety net if a safety lanyard cannot be attached to a secure point

A

25’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
101
Q

When driving a pile underwater what do you use?

A

Follower

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
102
Q

The largest size of a standard size rebar that can be lapped spliced is

A

11

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
103
Q

What law provides the legal means for filing a lien?

A

Private works act

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
104
Q

Caissons are:

A

Shafts with or without casings sunk to the desired depth and filled with concrete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
107
Q

The most important part of the estimating process that requires a complete take off of all materials that will be required in the project is

A

Detailed survey

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
108
Q

A contractor with _____or more employees must have a working and operational safety plan

A

11

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
109
Q

What is the minimum diameter of wire rope allowed when securing a barge?

A

7/8”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
110
Q

Wide flange beams driven vertically to retain material are known as

A

Soldier beams

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
111
Q

Where must a notice of contract be filed?

A

With the recorder of mortgages of the parish in which the work is performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
114
Q

Outrigger scaffold beams shall extend not more than ____ feet beyond the face of the building

A

6 feet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
115
Q

A tremie is used to pour concrete underwater. The bottom of the pipe should be

A

Submerged in concrete at all times

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
116
Q

Whose responsibility is it to prepare budgets for a project?

A

Project manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
117
Q

When using a dragline to unload/load a barge how long does a 180° swing take?

A

6-7 seconds

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
118
Q

What is true if a water reducing agent is added to concrete?

A

They reduce the water but retard the set time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
119
Q

What term defines the stake whose top issue is a known point of reference to establish elevation and distance?

A

Hub or benchmark

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
120
Q

Which of the following types of bonds guarantees the owner that the project will be completed according to the plans, specifications, and terms specified in the contract?

A

Performance bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
121
Q

The reason for lowering a footing in certain areas is

A

The temperature is low

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
122
Q

When does a contractor need to apply for the renewal of his license without a penalty?

A

Within 15 days of expiration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
123
Q

What type of pile can support no vertical load?

A

Sheet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
124
Q

What is the best material used under railroad tracks?

A

Gravel

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
125
Q

On a railroad track what material is not good for a foundation beneath the track?

A

Sand

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
126
Q

What would be used to check the air content of plastic concrete?

A

Air meter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
127
Q

Concrete contains ______ percent aggregate

A

60-75

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
128
Q

What is used to prevent movement of the load when using shackles?

A

Pack pin with washers to center

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
129
Q

When concrete for a caisson is poured on to a footing, how are the two attached?

A

Deform rebar

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
130
Q

Company overhead usually averages up what percentage of revenue?

A

5 to 20%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
131
Q

How deep should a pipeline be buried below water under the ground?

A

48”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
133
Q

NPS ____ and __________ has outside diameter equal to the nominal pipe size.

A

14, larger

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
134
Q

What is the name used for the inside bottom elevation of a sewer pipe?

A

Invert

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
135
Q

Open yard storage of hazardous waste cannot be stacked higher than?

A

20’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
136
Q

What type of insulation has the highest value?

A

Poly foam

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
137
Q

What is used to guide a pile?

A

Leads

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
138
Q

Who must file a notice of contract?

A

The general contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
139
Q

Which trenchless excavation insert a carrier RCP into the horizontal shaft?

A

Augering

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
140
Q

Scaffolding should be rated at____________ times its intended use.

A

4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
141
Q

Floating concrete is done when

A

After the surface water has left

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
142
Q

According to Louisiana revised statutes, contractors are required to pay subcontractors and suppliers within how many days?

A

14 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
143
Q

How many members of the board shall have the majority of their experience as a licensed contractor in the field of Highway and street construction

A

4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
144
Q

How far should trash be kept from the Pumpstation

A

10’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
145
Q

What is a jeep used for on a pipeline?

A

To find holidays

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
146
Q

What is a crab?

A

Small hand winch

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
147
Q

Approximately how long does it take to unload a barge when using a dragline to unload?

A

7 hours

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
148
Q

What is the best most economical method to de-water a swamp?

A

Divert

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
149
Q

If a welder is working on a large interstate gas transmission line how often must he be requalified?

A

Every calendar year

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
150
Q

Cast-iron pipe is generally used in which of the following piping systems?

A

Low-pressure systems

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
152
Q

What does the structural steel designation HP14x73 mean?

A

Bearing pile section 14 inches deep, 73 pounds per foot

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
154
Q

From a pump station how far should a fire pit be placed

A

50’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
155
Q

What is the requalification period for a welder working on gas transmission lines?

A

12 months

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
157
Q

When preparing a road base, what soil reacts best to vibration?

A

Sand

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
158
Q

In the accounting process, what is the first step?

A

Bookkeeping

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
159
Q

A ropes strength will be reduced by ___% if it is put in a sharp bend or tied in a knot

A

60

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
160
Q

What is Payline?

A

A line outside the building line that marks additional space to be excavated for working

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
161
Q

What is the minimum diameter of wire rope allowed when securing the upstream end of a barge?

A

1 1/4”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
162
Q

A centrifugal pump works best when it is placed

A

As close to the water level as possible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
163
Q

A transmission line is constructed over unlevel ground but the changes in elevation do not show in the conductors, this is an example of a

A

Well graded line

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
164
Q

What should be added to mortar to increase the compressive strength?

A

Cement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
165
Q

When measuring for a link belt change the distance between the rollers is called the

A

Pitch

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
166
Q

What is the maximum job you can do without the respective license?

A

$75,000 residential, $50,000 commercial, $7500 home-improvement, one dollar hazardous material

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
167
Q

What is the function and chief component of a slurry trench?

A

Water cut off and bentonite

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
168
Q

What moves a polyurethane pig through a pipe?

A

Oil and water

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
169
Q

According to OSHA the maximum height of open yard storage of lumber when manually storing is

A

16’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
170
Q

How far from a wellsite do you store batteries, fuel, or any other hazardous material?

A

100’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
171
Q

A ___________ is used for a test to measure compression strength in concrete

A

Cylinder

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
172
Q

What fastening device is used with threaded rods to plumb and tension parallel structure steel members?

A

Turnbuckle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
173
Q

What is the term used to describe a progress payment that is held by the owner as security for one guarantee of the contractors full and complete performance

A

Retainage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
174
Q

On schedule 40 pipe, when does the standard wall thickness change?

A

10”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
175
Q

What is the minimum gauge PVC pipe that can be threaded?

A

Schedule 80

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
176
Q

By what date must a company’s annual summary of occupational injuries and illnesses for the past year be posted?

A

February 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
177
Q

How is the turnbuckle secured?

A

Safety latch

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
178
Q

The projecting arm on a heavy crane that is attached to the bone is called what

A

Jib

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
179
Q

What type of weld is used for an H pile?

A

Fillet and butt weld

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
180
Q

What is a girt?

A

A horizontal member attached to columns to support siding or exterior cover

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
181
Q

At what depth of an excavation does OSHA require a ladder?

A

4’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
182
Q

What is the stake height for a slab on grade form?

A

Below the form

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
183
Q

Earth taken for hauling to a job site which is short of earth needed for fill, comes from _____________?

A

Borrow site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
184
Q

If the qualifying party terminate employment, the board must be notified within

A

30 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
185
Q

What is the peak sound pressure level that OSHA will allow

A

140 db

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
186
Q

In the installation of slip joint piping, you should:

A

Lubricate the spigot end and the gasket

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
187
Q

What does the structural steel designation S18 x 70 mean?

A

Amer. Standard beam 18” deep X 70#/LF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
188
Q

Which type of Portland cement is designed to produce high compressive strength concrete at an early period

A

Type III

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
189
Q

Waste water station pump sizes are usually designated by the pumps

A

Discharge nozzle diameter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
190
Q

Which of the following documents enables contractors to change some of the general conditions without rewriting the entire contract?

A

Special conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
191
Q

What is the definition of a gabion?

A

A cylindrical or rectangular container filled with earth and stone used in constructing dams, erosion breaks, and foundation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
192
Q

And untreated pile must be driven to__________to prevent decay

A

Below ground water level

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
193
Q

What are not standard types of concrete pipe?

A

Square

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
194
Q

If you want to increase the slump in concrete what should you add?

A

Superplasticizer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
195
Q

When lifting a load with a crane where is the best point of zero gravity?

A

Below the hook but above the lowest point of the load

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
196
Q

What is the first transaction in the bookkeeping process?

A

Source documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
197
Q

What type of supports are used on power poles set in sandy and swampy areas

A

Guys, braces, or cribbing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
198
Q

When is final payment due to a contractor?

A

After finishing the punch list items

199
Q

What test do you use to find the maximum density of soil?

A

An unconfined compressive strength test

200
Q

What type of equipment uses a gantry?

A

Dragline

202
Q

What is the distance of the last posted sign closest to the actual construction site?

A

500’

203
Q

The optimum moisture content of a soil is the amount of moisture at which

A

Maximum density is obtained

204
Q

Working capital is

A

The difference between current assets and current liabilities

205
Q

What is the acronym use for organic material according to AASHTO?

A

SVOC, TOC, VOC

206
Q

What type of insurance is considered to be an important part of the risk management program of a partnership in case of the death of a principal?

A

Key man

207
Q

What is the minimum age for a worker in a non-hazardous job?

A

14 years

208
Q

A concrete joint which allows both vertical and horizontal movement is best known as

A

Isolation

209
Q

Where do you obtain the centerline of the road?

A

Profile view

210
Q

The increase in bulk of soil when it is being dug or blasted is known as

A

Soil swell

211
Q

What type of pile is created by driving a woodpile to ground level then attaching a steel beam to the wood. Driving is continued with a shell or mandrel to the desired depth. The shell is then removed and the shaft is filled with concrete

A

Composit

212
Q

What is used to measure water pressure?

A

Piezometer

213
Q

If a gas pipe transmission line is placed under a river, how much soil cover is required?

A

48”

214
Q

On new industrial pipe installation, what is installed in front of pumps before flushing the system?

A

Temporary strainers

215
Q

Pipe turn 90° using 5 sections of pipe. What is that called?

A

5 piece mitered elbow

216
Q

In the accounting cycle, where do the cash receipts fall?

A

The disbursements journal

217
Q

What is side cast?

A

The material that comes off the end of the blade on a piece of earthmoving equipment

218
Q

A sand cone test is used to measure

A

Compaction

219
Q

At what depth does OSHA require a trench to be shored on the sides?

A

5’

220
Q

What is a “cloud” contract?

A

Lien contract

221
Q

What is used as a temporary set of walls to keep soil and or water from entering the excavation?

A

Cofferdam

222
Q

Any tree that would reach within 5 feet of a point underneath the outside conductor of a transmission line if it fell is known as a

A

Danger tree

223
Q

Which of the following is grouted when installing a piece of equipment?

A

Base plate

224
Q

What is the average size pipe used for a tremie?

A

10”-12”

225
Q

What is another name for the markers which establish the boundaries of a lot

A

Monuments

226
Q

Aggregate from a sand or gravel pit that has not been processed is known as

A

Pit run

227
Q

In moving dirt during an excavation, where is the unused dirt stored for future use?

A

Stockpile

228
Q

Which of the following types of soil would be the most expansive or swell the most?

A

Clay

229
Q

What is the standard size of a piemeters opening?

A

60 microns

230
Q

What is used to determine the density of asphalt?

A

Nuclear density test

231
Q

What moves a polyurethane pig through a pipe?

A

Liquid

232
Q

What is the standard size of a piezometer?

A

3/4”

233
Q

How often should wire rope be inspected?

A

After every use

234
Q

Before a license can be issued by the board for hazmat work, what agency must issue certification for the contractor?

A

Louisiana Department of environmental quality

235
Q

How deep do you set a utility pole that is 40 foot long?

A

6 foot

236
Q

Specified by its outside diameter and wall thickness expressed in BWG or thousandths of an inch.

A

Tube

237
Q

If a contractor is doing work with hazardous materials, when is he required to have a license?

A

If the contract is more than one dollar

238
Q

What is used as a spacer when layering rebar three times?

A

Metal spacer

239
Q

The Miller Act requires a contractor to provide performance and payment bonds on public work projects. What is the minimum amount of a contract at which Miller Act requirements apply?

A

$100,000

240
Q

What is the minimum safety factor for wire rope?

A

3

241
Q

Who locates the boundary markers?

A

Contractor

242
Q

How often does the board meet?

A

Once a month

243
Q

What is the name for the pile that is formed by driving a casing into a set depth and removing the casing while filling the hole with concrete?

A

Shell-less

244
Q

How are railroad track ties placed?

A

21 1/4” apart

245
Q

What bond would cover faulty workmanship or materials after the job is complete?

A

Maintenance bond

246
Q

What is the term to describe a transmission line running level while the ground undulates?

A

Grading

247
Q

What type of pile is used when there is no bearing foundation? (Sand or earth with no bedrock)

A

Friction pile

248
Q

What type of bond may be used in place of a performance and payment bond?

A

Completion bond

249
Q

On any structure a footing supports the

A

Dead load

250
Q

What are jetting chains used for?

A

Cleaning pipes

251
Q

Identified by nominal pope size, with wall thickness defined by schedule number, API designation, or weight.

A

Pipe

252
Q

What is considered an immaterial breech of contract?

A

A delay in work

253
Q

What is the minimum distance for posting construction signs on a construction site?

A

1500’

254
Q

Not a basic field test used for quality design and control?

A

Cement content and density

255
Q

How long must an employer maintain records about work-related injuries?

A

5 years

256
Q

How do you increase the slump of concrete?

A

Add water

257
Q

What is used for a base plate share?

A

Leveling nut

258
Q

In obtaining proper soil compaction, it is important to

A

Control the amount of water in the soil

259
Q

A sand cone test is used to measure

A

Compaction

260
Q

If a Workmen’s Compensation notice is posted in the workplace, how long does an employee have to report a work-related injury to the employer?

A

30 days

261
Q

What is the upper part of a pile called after it was driven?

A

Head

262
Q

What type of soil would you use a grab hammer drill in?

A

Rock or any other soil

263
Q

Who is responsible for providing the survey, plot, and plans?

A

Owner

264
Q

While trenching and excavating, OSHA requires at least ________ feet of clear unobstructed distance from the trenches edge to the toe of the soil pile

A

2

265
Q

What is the worst material used under railroad tracks?

A

Clay

266
Q

When using two sections of scaffolding when do you tie it off?

A

20 feet

267
Q

What color is used to mark electrical utilities by LA one call?

A

Red

268
Q

Pipe can be stacked no more than ____ feet high

A

6

269
Q

Fiberglass reinforced pipe should be used for

A

Alkaline, acidic, or oxidizing chemicals

270
Q

If you want to pour a column faster what do you do

A

Pour using stiffer concrete

271
Q

The test for the tensil (flexurial) strength of concrete uses a _______?

A

Beam

272
Q

A person shall not be the qualifying party for more than ________

A

1 company and 2 subsidiaries

273
Q

How far should a spoil pile be placed from a trench?

A

2’

274
Q

What is the standard width of crossarms on an overhead power pole?

A

6

275
Q

What would you feel the drum of a sheep’s foot roller with?

A

Water and sand

276
Q

What is the main ingredient used when pickling pipe?

A

Hydrochloric acid

277
Q

What does a blue signal light mean to a train engineer on the railroad?

A

That people are working on the line and that access is not allowed on that portion of track

278
Q

What method can you use to transfer a grade from one side of a road to the other without the use of a builders level?

A

Sweding

279
Q

A point indicating where the fill slope stops and the roads or shoulder grade begins is called

A

Hinge point

280
Q

The datum point, property lines, grade lines, & utilities easements are shown on the _________ plan.

A

Plat

281
Q

A contract must contain which of the following elements to be considered valid?

A

Offer (proposal), acceptance and consideration

282
Q

When reeving a block, the loose or dead end of the rope is placed in a

A

Becket

283
Q

What percent retainage is commonly withheld from progressive payment?

A

10%

284
Q

Which form is used to apply for an EIN?

A

SS – 4

285
Q

When time is of the essence, a construction project that allows construction to begin before completion of all the drawings and utilize multiple prime contractors is called

A

Phased or fast track construction

286
Q

How do you decrease the slump of concrete?

A

Add superplasticizers

287
Q

When laying asphalt how does the roller operator know when to stop compacting

A

After finishing the rolling pattern

288
Q

A chain usually comes in standard length of

A

50’ and 100’

289
Q

In a wastewater treatment plant the two most commonly used types of pumps are centrifugal and

A

Pneumatic ejector

290
Q

Planks on scaffolding should extend _____ beyond the ends of their supports

A

6”

291
Q

Which power excavating machine is designed to operate against the face of the bank that it displaces as it moves forward?

A

Dragline

292
Q

What does a dredging screen do?

A

Preevent silt from exiting the area

293
Q

What type of business can sell its assets without selling the business itself?

A

Union

294
Q

When must a notice of contract be filed?

A

Before the work begins on any contract exceeding $25,000

295
Q

What is a wicket?

A

A small door usually mounted as part of a larger one

296
Q

What lengths are utility poles cut or sold in?

A

5’

297
Q

Wastewater station pump sizes are usually designated by the pump ____________

A

Discharge nozzle diameter

298
Q

What is the minimum depth to set a utility pole

A

5’

299
Q

What indicates a curvature in a horizontal line to a higher or lower elevation?

A

Vertical curve

299
Q

The spill off from the ends of a dozer or grader blade which forms a ridge of loose material is called

A

Windrow

299
Q

What type of pile displaces a large amount of soil?

A

Any pile other than a drilled pile

299
Q

Which ASTM designation is an all purpose carbon steel used widely in the industry?

A

A36

299
Q

What does grade “40” on a piece of re-bar mean?

A

40,000 pounds per square inch tensile

299
Q

Compressibility of soil involves ___________

A

Rearrangement of the soil grains to a denser, thinner layer, usually involving the squeezing out of water when a load is placed on the soil.

299
Q

From any point on a transmission line to a vertical point on a conductor is called the

A

Sag

299
Q

Concrete strength is designated in pounds per square:

A

Inch, compressive

299
Q

A line that carries gas from a current production facility to a transmission line or main is called a

A

Gathering line

300
Q

Which of the following railroad bolts are not permitted?

A

Ribbed Bolts

301
Q

What type of railroad bolts should be used?

A

Unfinished or turned bolts with single self locking nuts or double nuts unless otherwise specified.

302
Q

For which type of railroad bolt must the threads be entirely outside the holes?

A

Turned Bolts

303
Q

For railroads, what does not need to be coated with rust-inhibiting grease?

A

Bolts

304
Q

The maximum mass or force which the product is authorized to support in a particular service

A

Working load limit

305
Q

A test applied to a product solely to determine injurious material or manufacturing defects

A

Proof test

306
Q

The average load or force at which the product fails or no longer supports the load

A

Ultimate strength

307
Q

And industrial term denoting a products theoretical reserve capability

A

Design factor

308
Q

The minimum design factor for chain slings and end attachments

A

4/1

309
Q

The minimum design factor for wire rope slings, synthetic slings and their end attachments

A

5/1

310
Q

At an angle of loading (horizontal sling loading) of 30°, the tension on each sling is ________ compared to its single leg straight line hitch capacity.

A

Doubled

311
Q

Angular loading of a shouldered eye bolt will result in

A

Decrease in capacity

312
Q

Fittings must be removed from service if

A

Any significant deformation can be detected

313
Q

Tie backs are anchored to ______ when used with soldier beams

A

Earth or rock outside the wall

314
Q

According to OSHA, all trenches over _______ feet must be shored regardless of how solid the ground appears

A

5’

315
Q

The side rails of a ladder should extend _____ above the roof

A

36”

316
Q

Planks on scaffolding should extend _____ beyond the ends of their supports

A

6 inches

317
Q

When should wire ropes be replaced?

A

When 5% of their wires per lay are broken

318
Q

Torches, bottles, regulators and other welding/cutting equipment should be kept free from

A

Oil

319
Q

According to OSHA, what is the maximum developed length in feet of a lanyard safety line?

A

6’

320
Q

A pile is being driven with a double action steam pile driver. The head of the pile starts to bloom and split. Which of the following would you do?

A

Decrease the steam pressure at the boiler and at the hammer

321
Q

To perform a hydra static test on pipe with cement lined on the inside you should

A

Hold pressure for 45 minutes then begin testing

322
Q

When concrete for a caisson is poured onto a footing how are the two attached?

A

Deformed rebar

323
Q

What should be added to mortar to increase the compressive strength?

A

Cement

324
Q

When LaOneCall is used, what determines their start and stop points for marking?

A

The area the contractor designated that he is working in

325
Q

Along the coast, when can you not install an above ground gas valve for an underground line?

A

In a protected area

326
Q

I have a project as hazardous materials what must a contractor have in place

A

Action plan

327
Q

What is used to determine flexural strength?

A

Beam

328
Q

What is used to lift a long object that cannot be lifted from the center

A

Spreader bar/balance beam

329
Q

At what height working from a scaffold board does OSHA requires someone to wear a safety lanyard

A

10’

330
Q

When lifting a 45 foot long bundle of rebar from one location to the next it should be picked up using what

A

2 slings and a choker

331
Q

When on a scaffold, what height from the next level is the owner required to provide a safety harness?

A

6’

332
Q

When drilling in sand with an auger what should it be pumped to help the auger along

A

Water

333
Q

Where is a safety lanyard placed on a person?

A

Center of the back

334
Q

When do you start jetting?

A

Simultaneously when you start drilling

335
Q

What is a jeep used for?

A

Checking for cracks in the coating

336
Q

After dredging and forming an island you have excavation work to perform on site, what should be done to ensure the density is adequate?

A

Pentrameter check

337
Q

Rebar is spliced when _______

A

Bars are not long enough to cover the specified distance

338
Q

What is a bull float designed to do?

A

Push aggregate down and allow moisture to rise to the surface

339
Q

What happens to the concrete during a cone test when the cone is removed?

A

The cement will begin to slump/fall

340
Q

Which is the following is the primary reason to place a heat trace in a water pipe

A

To prevent freezing of the pipe

341
Q

According to OSHA what is required when working in a bell trench

A

Lifeline

342
Q

When mooring a barge to a dock where do you tie it off?

A

Both front and back

343
Q

How many whistles does a drainage received when being approached or when it is moving in reverse

A

3 whistles

344
Q

How is the thickness of concrete measured?

A

Probe

345
Q

What is a skirt used for?

A

To keep material in a designated area

346
Q

What is a common thickness of asphalt?

A

5-7 inches

347
Q

How high are form boards in relation to the slab

A

Level with the slab height

348
Q

What is the common thickness of asphalt?

A

5-7 inches or 3-4 times the size of the largest aggregate used

349
Q

Why are electric charges sent through pipe lines that fluid is transported in

A

Keep bacteria out of the system

350
Q

What is true about geotextile when laid out beneath rip rap from the flow of a culvert in a stream

A

Overlay geotextiles 6”

351
Q

What size are the openings of 6x8 12w wire mesh?

A

6x8

352
Q

What is used to ensure she piles are installed perfectly horizontally?

A

Piles on both side

353
Q

When erecting a steel building what is done last?

A

We’d it together

354
Q

How do you increase the slump of concrete

A

Add water

355
Q

How do you decrease the slump of concrete

A

Add super plasticizers

356
Q

What would be the last step when aligning a pump and motor?

A

Shim motor feet

357
Q

When driving a spiral pile what permanent structure is typically used to protect it near water

A

Caissons

358
Q

When driving a spiral pile what temporary structure is usually used to protect it near water?

A

Cofferdam

359
Q

How is a Jeep propelled?

A

Electricity

360
Q

Why would a cloth be placed over the top of a metal pile when driving?

A

To prevent sparks from falling on workers

361
Q

How do you treat hot asphalt that is in direct contact with the skin?

A

Apply cold water to the skin

362
Q

At a railroad crossing how are the green and red lights positioned?

A

Vertical green over red

363
Q

How are base plates attached to beams?

A

Welded at the shop

364
Q

When rebar is delivered at a job site, how is its use marked (slab, walls, etc)?

A

Tags placed on bundles

365
Q

When lifting a 40 foot bundle of rebar what type of strap/sling would most likely be used?

A

Wire rope sling with spreader bar

366
Q

When grubbing is being done and must be transported on the water ways who should you contact?

A

Louisiana Department of Agriculture

367
Q

When scaffolds are hanging overhead how much should it be rated for?

A

6 times

368
Q

When a welder welding on pipeline what should he be certified under

A

API

369
Q

When is bull floating performed?

A

Shortly after screeding when there is no visible surface water

370
Q

When cold pouring concrete what curing method/compound is used?

A

Do not use any but monitor the temperature

371
Q

What is the best material used under railroad tracks?

A

Gravel

372
Q

What is used to prevent movement of load when using shackles?

A

Pack pin with washers to center

373
Q

When lifting a load with a crane where is the best point of zero gravity?

A

Below the hook but above the lowest point of the load

374
Q

In what soil is a well point least useful?

A

Clay

375
Q

What do you put around and auger?

A

Water

376
Q

What is a jeep used for on a pipe line?

A

To find holidays

377
Q

When driving a pile underwater what do you use?

A

Follower

378
Q

What is the location of a load with wire rope?

A

Under hook and center of gravity below

379
Q

Where do you obtain the centerline of a road?

A

Profile view

380
Q

How is a marsh buggy moved around a job site so that it will not get stuck?

A

Move within tracks coming in and out

381
Q

What type of insulation has the highest value?

A

Poly foam

382
Q

If a project has hazardous materials, a contractor must have?

A

MSDS

383
Q

What is the term to describe a transmission line running level while the ground undulates?

A

Grading

384
Q

Which of the following is an expansion joint when pertaining to transmission lines?

A

Bundling

385
Q

When do you replace wire rope?

A

When there are three broken wires on one strand

386
Q

What is the minimum safety factor for wire rope?

A

3

387
Q

How do you increase pressure when using a centrifugal pump?

A

Decrease the velocity of liquid

388
Q

How far from a Wells site do you store batteries, fuel, or any other hazardous material?

A

100’

389
Q

What is the minimum distance that a burn pit must be from a well or a storage tank?

A

100’

390
Q

What is the standard size of a piezometer?

A

3/4”

391
Q

Approximately how long does it take to unload a barge when using a dragline to unload?

A

7 hours

392
Q

What is used for railroad track ballast?

A

Crushed stone

393
Q

How is a 12” pipe measured according to NPS?

A

ID

394
Q

How is a 16” pipe measured according to NPS?

A

OD

395
Q

When concrete sewer pipe is installed at the end of the day what should be done to the exposed end of the pipe?

A

Watertight plug is installed to prevent dirt rocks or debris from entering system

396
Q

According to OSHA fall protection is required when working on scaffolding about how many feet?

A

10’

397
Q

What is required on scaffolding if overhead work is being performed?

A

2 inch planking or material of equivalent strength laid tight

398
Q

If you want to pour a column faster what do you do?

A

Pour using stiffer concrete

399
Q

For a long well point where expansion is a consideration what material is beat suited?

A

PVC

400
Q

What materials are used for anodes?

A

Zinc or aluminum

401
Q

What is a stake height for a slab on grade form?

A

Below the form

402
Q

Which of the following is the strongest steel brace?

A

Angle support

403
Q

What is used for a base plate shim?

A

Leveling nuts

404
Q

What is the abbreviation for a steel beam with a wide flange?

A

W beam

405
Q

What is used as a spacer when layering rebar three times?

A

Metal spacer

406
Q

What does a dredging screen do?

A

Prevent silt from exiting the area

407
Q

How is the thickness of asphalt determined?

A

Probe

408
Q

How far do combustibles need to be stored from tanks?

A

50’

409
Q

If moving a cmu block what must be done?

A

Use new mortar

410
Q

What does LaOneCall place blue marking flags for?

A

Potable water

411
Q

What color are inflatable indicator vests?

A

Green

412
Q

When demolishing a building where are the utilities cut off at?

A

At the building line

413
Q

If workers must pass under scaffolding what should be done prior to use?

A

Provide a screen between the toeboard in the guard rail, extending along the entire opening, consisting of number 18 gauge US standard wire 1/2 inch mesh or the equivalent

414
Q

If you want to decrease the slump in concrete what should you add?

A

Superplasticizer

415
Q

What is a pig used for?

A

Check for obstructions within the line

416
Q

Which of the following is grouted when installing a piece of equipment?

A

Base plate

417
Q

Jetting is least useful in what type of soil?

A

Gravel

418
Q

When digging in unstable soil how should you install a shoring box?

A

Dig the soil a little more narrow than the box and push it in

419
Q

What are the acronym is used for organic material according to AASHTO?

A

SVOC, TOC, VOC

420
Q

Open yard storage of hazardous waste cannot be stacked higher than

A

20’

421
Q

From a pump station how far should a fire pit be placed?

A

50’

422
Q

If reshoring is necessary when should reshores be placed?

A

As the original forms and shores are removed

423
Q

If you are dredging with in the Louisiana coastal zone who must you notify?

A

Office of coastal management

424
Q

When setting a pile using a winch line where is it lifted from?

A

1/3 from the top

425
Q

When reusing form boards when should they be inspected?

A

Before every use

426
Q

According to OSHA the maximum height of open yard storage of lumber when using a machine is

A

20’

427
Q

According to OSHA the maximum height of open yard storage of lumber when manually storing is

A

16’

428
Q

What type of weld is used for an H pile

A

Butt and fillet weld

429
Q

What do you do with the rebar that sticks out horizontally?

A

Nothing

430
Q

What is the definition of a gabion?

A

A cylindrical or rectangular container filled with earth and stones used in constructing dams, erosion breaks, and foundations

431
Q

When installing pipe by the end of the day pipe that has been laid should be

A

Buried

432
Q

When using a concrete vibrator what is a sign that the vibrator should be withdrawn?

A

When air bubbles are no longer coming to the surface

433
Q

What is used to determine the density of asphalt?

A

Nuclear density test

434
Q

What is used to measure water pressure?

A

Piezometer

435
Q

What is the standard size of a piezometers opening?

A

60 microns

436
Q

When should you inspect erected shoring equipment?

A

Before the pouring is started, during the pouring process, and immediately after the concrete is poured

437
Q

Of reshoring is necessary when should reshores be placed?

A

As the original forms and shores are placed

438
Q

What lights are required for a barge that is secured along the bank?

A

Two white unobstructed all round lights

439
Q

If you dredge an area and plan to move your equipment to the spoils site what test is used to determine the bearing ability?

A

An unconfined compressive strength test

440
Q

How far are railroad ties placed?

A

21 1/4” apart

441
Q

If you have a dent in a ladder, what do you do?

A

Mark or tag”Do not use” and remove from use

442
Q

If you have a dent in your hardhat what should you do?

A

Remove from service and replace

443
Q

When working in a swamp or marshy area what should be done to a bulldozer?

A

Increases the pad width

444
Q

When reusing form boards, when should they be inspected?

A

Before every use

445
Q

Floating concrete is done when

A

After the surface water has left

446
Q

What moves a polyurethane pig through a pipe?

A

Oil and water

447
Q

What would be used to pickle or clean metal pipe surfaces?

A

Phosphoric acid

448
Q

Fiber-glass reinforced pipe should be used for?

A

Alkaline, acidic, or oxidizing chemicals

449
Q

How should concrete pipes be unloaded from trucks?

A

Run padded chains around the pipe and use slings to unload off the truck

450
Q

Pipe can be stacked no more than ___ feet high

A

6’

451
Q

According to OSHA a hard hat should be worn to protect from overhead falling objects as well as

A

Electric shock

452
Q

Outrigger scaffold beams shall extend not more than _____ feet beyond the face of the building

A

6’

453
Q

What would be used to find unlevel spots in an asphalt paving matt or roadway?

A

Rolling straight edge or (profiligraph)

454
Q

What would be used to check the air content of plastic concrete?

A

Air meter

455
Q

What type of pile is used when there is no bearing foundation?

A

Friction pile

456
Q

What is the most common problem with wood piles?

A

Insects

457
Q

At how many feet off the ground does OSHA requires the use of safety nets?

A

25’

458
Q

The safety margin used when choosing wire rope is determined by dividing by

A

5

459
Q

What type of soil would you use a grab hammer drill in

A

Rock or any other soil

460
Q

When lifting a load with two cranes at the same time, which of the following is true?

A

Use one signal man for both cranes

461
Q

And untreated pile must be driven to ____ to prevent decay

A

Below ground water level

462
Q

What is not part of the ductile iron pipe joint?

A

Weld flange

463
Q

From any point on a transmission line to a vertical point on a conductor is called the

A

Sag

464
Q

At what height does osha require the use of a safety net if a safety lanyard cannot be attached to a secure point

A

25’