What is the F10 Notice?
Notifies the HSE that there is a construction site
When is the F10 notifiable?
If the project is more than 30 days, more than 20 workers or longer than 500 person days
Who’s responsible to acquire the F10 Notice?
Under CDM 2015 the Client is responsible buy can instruct the Principal Contractor to do it for them however the underlying responsibility sits with the Client.
Can you tell me a heading from Surveying Safely
Safe Persons concept
What is 5 point PPE?
- Hard Hat
- Hi-vis
- Steel Toe Caps
- Gloves
- Glasses
What’s the major difference in CDM 2015?
Places more responsibility on Key Duty Holders and the CDM Co-Ordinator is now the Principal Desginer.
What does CSCS stand for?
Construction Skills Certification Scheme
What is the purpose of the Health & Safety at Work act 1974?
Ensures Employer’s provide a safe place to work for all employee’s:
Provide correct equipment
Safe environment
Relevant training
Risk assessments carried out
Proper facilities