What’s the difference between ROCE and OCE?
Rough Order Cost Estimate is based on Stage 0 information whereas an OCE is based on RIBA Stage 1 information.
What is the degree of accuracy?
These are usually based on areas and £/sqm basis and give a rough indication of viability of a scheme for a Client.
What is the purpose of NRM
Provide a standard form of measurement and guidance across the UK for construction projects
What are the measurement rules for pricing internal walls for an OCE under elemental method?
OCE - £/sqm
Cost Plan - measure the centre line and £/sqm
Thameside House - how did you evaluate the value of the space
Calculated the net:gross area on a floor by floor basis. It was efficient on every floor but it was poor in the basement with plant and a bin store taking up the space. These areas are not lettable spaces so therefore do not offer value for money as the Client could not profit from the space.
Why might costs be different to a benchmark?
Factors such as location, design, materials