Health and Safety Flashcards
What is CDM 2015?
The main piece of health and safety legislation for the construction process and applies to all construction projects. It identifies dutyholders under the regs what each each must do to comply with the law to ensure projects are carried out safely
What are the roles referred to under CDM 2015?
Clients, domestic clients, designers, principal designers, contractors, principal contractors and workers.
What is a principal designer?
The designer appointed in writing by the client. They can be an organisation or an individual.
What is a principal designer responsible for?
They have 7 duties under regulation 11 of CDM 2015.
They have control of the pre-construction phase of the project.
They may have separate duties as designers.
They influence how the risks to health and safety should be managed and incorporated into the wider management of a project.
They should focus their work on ensuring the design work in the pre-construction phase contributes to the delivery of positive health and safety outcomes.
They must ensure as far as responsibly practicable that foreseeable risks to health and safety are identified. They prepare the health and safety file.
A principal designer must have…
- Technical knowledge of the construction industry relevant to the project.
- Skills to manage and coordinate the pre-construction phase.
- Where they are an organisation, have organisational capability to carry out the role.
What should the principal designer do when the pre-construction information is prepared?
- Assess the adequacy of existing information to identify any gaps
- Provide advice to the client on how gaps can be filled
- Provide, as far as they are able to, the additional information to help designers and contractors.
Risks should be addressed by…
General principle of prevention - Eliminate, reduce, control
If the principal designer’s appointment finishes before the end of the project, the health and safety file must be passed to…
The principal contractor
A project is notifiable if…
A construction project is notifiable if the construction work is expected to:
- last longer than 30 working days and have more than 20 workers working at the same time at any point on the project or
- exceed 500 person days
The HSE can be notified by filling out an electronic F10 form.
What is a client?
anyone for whom a construction project is carried out.
There can be more than one client but must be agreed which one is responsible for carrying out the requirements of CDM 2015.
What should clients consider when making appointments?
They must ensure those they appoint have the skills, knowledge, experience, and (if an organisation) the organisational capability to manage health and safety risks.
What is a designer?
Anyone who prepares or modifies a design for a construction project (including the design of temporary works); or arranges for, or instructs someone else to do so.
A designer must not start design work unless…
They are satisfied the client is aware of their duties under CDM 2015.
What is a risk assessment?
A risk assessment is a systematic method of looking at work activities, considering what could go wrong, and deciding on suitable control measures.
What is a hazard?
A hazard is something with the potential to cause harm
to someone. The harm could be an injury or ill health.
What is a risk?
Risk is the likelihood (whether high or low) of the harm being realised.
What types of risk assessment are there?
- Qualitative Risk Assessment
- Quantitative Risk Assessment
- Generic Risk Assessment
- Site-Specific Risk Assessment
- Dynamic Risk Assessment
How can risks be controlled?
- Elimination - Redesign the activity or substitute a substance so that the hazard is removed or
eliminated. - Substitution - Replace the materials used or the proposed work process with a less hazardous one.
- Engineering Controls - Use work equipment to reduce risk.
- Administrative controls - These are all about identifying and implementing the procedures needed to work
safely. - PPE - Only after all the previous measures have been tried and found ineffective in
controlling risks to a reasonably practicable level must personal protective equipment
(PPE) be used.
What are some examples of using engineering controls to reduce risks?
Use work equipment or other measures to prevent falls where you cannot avoid
working at height. Install or use additional machinery such as local exhaust ventilation
to control risks from dust or fumes. Separate the hazard from operators by methods
such as enclosing or guarding dangerous items of machinery/equipment.
What is qualitative Risk assessment?
A qualitative risk assessment will look at the risk of somebody being injured, and if that is high, medium or low. The risk is calculated by the severity of harm x likelihood of harm.
What is a Quantitative Risk Assessment?
The quantitative risk assessment is used to measure risk by assigning a numerical value. Often qualitative risk assessments might assign numbers to different levels of risk such as a 5x5 matrix. These are often colour coded to indicate the severity of the hazard.
What is a Generic Risk Assessment?
A generic risk assessment will often be used for similar activities or equipment across different sites, departments or companies.
What is a Site-Specific Risk Assessment?
A site-specific risk assessment is a risk assessment that has been completed for a specific item of work, that takes account of the site-location, environment, and people doing the work
What is a Dynamic Risk Assessment?
A dynamic risk assessment is a process of assessing risk in an on the spot situation. This type of risk assessment is often used to cope with unknown risks and handling uncertainty. Workers need to have the skills and awareness to recognise and deal with danger.
For example, before embarking on the
planned activity, continually re-evaluate:
- Is the activity still safe to continue?
- Is the working environment still safe for the activity to
continue?
- Are all those working still within their limit of
competence (skills, knowledge and experience)?
If not, they should assume the authority to remove
themselves and their colleagues from danger.
- Are there appropriate control measures in place?
- Can everyone still get to a place of safety in an
emergency?
What are the steps to undertaking a risk assessment?
here are typically 5 steps to a risk assessment;
Step 1: Identify hazards, anything that may cause harm.
Step 2: Decide who may be harmed, and how.
Step 3: Assess the risks and take action.
Step 4: Make a record of the findings.
Step 5: Review the risk assessment.
Step 6: Advise all those affected of the outcome of the assessment and methods of work, or other control measures necessary, to minimise or eliminate risk.