Conflict Avoidance, Management and Dispute Resolution Flashcards

1
Q

What is alternative dispute resolution?

A

Traditional dispute resolution sees a dispute put before a judge. Alternative dispute resolutions offer different processes to resolve a dispute often less formal, cheaper and quicker than going through the courts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are some examples of dispute resolution?

A

Mediation,
Adjudication,
Arbitration,
Professional Arbitration on Court Terms,
Independent Expert Determination,
Early Neutral Evaluation
CAP
Dispute Resolution Boards
Dispute Resolution Advisers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is mediation?

A

Mediation is a one or two day process. An independent mediator is appointed by agreement of both parties. Each party has their own private discussion space and a larger space where they both negotiate. Approximately tow thirds of mediations are solved on the day or shortly after.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the mediation process?

A

Documents are exchanged prior to meeting,
Opening statements are made by both parties,
Mediator facilitates discussion on key aspects of the dispute,
Negotiation of a settlement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are some common causes of disputes?

A

Frequent causes of disputes in construction and engineering are:

  1. Errors and/or omissions in the management of the contract
  2. Failure by an employer, contractor or subcontractor to
    understand or comply with detailed contractual obligations
  3. Submission of poorly drafted, flawed and/or unfounded
    claims
  4. Contradictory priorities of contracting parties
  5. Poorly communicated design information and/or employer requirements
  6. Poor contract management
  7. Contract ambiguity
  8. Unclear compensation event procedure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are some drawbacks to mediation?

A
  • Not compulsory;
  • Concerns exist around the enforceability of a mediation agreement;
  • All parties must agree to a resolution as the result is not guaranteed;
  • Can be difficult if either party are withholding information;
  • Mediation may not be appropriate if one of the parties required public disclosure;
  • Utilising the services of an unskilled mediator can contribute to an unproductive resolution;
  • An unwillingness of one or both of the parties to cooperate can make the whole process a waste of time, effort and money;
  • If the dispute cannot be resolved in mediation the cost of mediation will have been wasted;
  • During the mediation process either party can withdraw from proceeding at any time;
  • There is the possibility that information may be given away to the other party during the mediation process that could benefit the other party.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the benefits to mediation?

A
  • Mediation can be carried out relatively quickly compared to litigation, taking on average between 1 to 2 days;
  • If both parties agree to mediation this clearly demonstrates a willingness to achieve a negotiated solution;
  • The appointed mediator will be independent, they will not advise or provide judgement;
  • The mediator is there to facilitate and guide the discussions between the parties, with the primary objective of resolving the dispute;
  • It is the parties involved in the mediation process that arrive at a final solution and not the mediator. Remain in control of their dispute;
  • It is a flexible process that provides parties access to a wide range of outcomes that are not available in litigation. For example, courts will usually order one party to pay money to the other party, whereas in mediation the parties come to their own agreement and other things can be taken into account;
  • If a solution cannot be achieved then other options are still available;
  • The process will attempt to preserve the relationship between the parties;
  • Mediation can allow each party to hear the opposing view in a non-confrontational environment;
  • Both parties must sign an agreement of the final recommendation in order for it to be binding;
  • The parties via the mediator can bring other matters outside of the contract itself into the mediation in order to assist a commercial settlement;
  • It is a confidential process and anything discussed at mediation is considered ‘without prejudice’ and therefore cannot be used as evidence in any subsequent tribunal.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are dispute boards?

A

The term dispute board (DB) is a generic one covering:

  • Dispute review boards (DRB) make recommendations rather than binding decisions.
  • Dispute adjudication boards (DAB) make a binding decision about any dispute referred to it.
  • Combined dispute boards (CDB) rules provide that the dispute board could make a recommendation or a binding decision.
  • Dispute resolution advisor (DRA) is a single person dispute board.

A DB is appointed at the outset of the project. It is most usually encountered on substantial major projects and will comprise three individuals. There are a number of ways that these three could be
appointed, but most usually the employer appoints one member, and the contractor another. Those two members then (with the agreement of the parties) nominate a chairperson.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are some advantages of dispute boards?

A

Confidentiality – issues arising between parties are not rehearsed in public. The way matters are resolved and outcomes of decisions and recommendations remain private
Expertise – the members of a DB are selected for their subject matter knowledge and expertise in negotiation and conflict management.
Flexibility – the parties can agree the procedure and timetable for utilising a DB to their contract in advance, and can agree any changes to it during the course of the project.
Prevention of disputes – the existence of a DB which is wholly informed and aware of all matters relating to the project can prevent frivolous claims. A DB encourages parties to work collaboratively, and incentivises them to strive for negotiated resolution of issues without the need for the DB to intervene.
Relationships – the DB process is usually underpinned by a commitment by the parties to collaborate and ensure conflict situations do not arise and, if they do, that they are resolved quickly and amicably.
Information and communication – Regular site visits and document reviews give a DB a high level of knowledge of how a project is progressing and foresight of potential problems in the future. If there is disagreement between the contracting parties on any matter, the DB will have a deeper understanding of what is going on than any arbitrator or tribunal, who would be appointed after a dispute has arisen.

The intelligence acquired by a DB can be used to ensure parties are fully informed. This helps parties to avoid disputes and resolve issues early and quickly.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are some disadvantages of dispute boards?

A
  • Cost. The cost of establishing and maintaining the dispute board for the duration of the project.
  • Binding nature of decision. Depending on the nature of the board, the decision may not be binding on the parties.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is adjudication?

A

The Housing Grants, Construction and Regeneration Act 1996 imposes a right to adjudication in construction contracts. If parties to a construction contract do not agree an adjudication procedure, then one is imposed by the Scheme for construction contracts. In adjudication, the decision is the responsibility of a third party adjudicator selected by the parties to the dispute. Adjudication decisions are binding unless and until they are revised by subsequent arbitration or litigation after practical completion, or by agreement between the parties (hence the term ‘pay now argue later’). There is no right of appeal and limited right to resist enforcement. Generally, adjudicators do not have the power to award costs (other than their own fees and expenses). Adjudication must adhere to strict timescales and typically takes up to 28 days.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are some advantages of adjudication?

A

-The parties can select the expert or the characteristics of the expert.
-The expert can act as an investigator.
-Seldom lengthy oral arguments or legal submissions.
-No cross examination or formal evidence.
-Streamlined, speedy (28 days) and flexible procedures as agreed between the parties.
-Less expensive.
-Can ratify or dismiss by agreement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are some disadvantages of adjudication?

A

-The expert cannot go beyond the jurisdiction specified in the contract.
-The expert determination is not supported by statute.
-The expert powers are limited.
-The expert’s determinations must be enforced by commencing court proceedings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What introduced statutory adjudication?

A

The Housing Grants, Construction and Regeneration Act 1996

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What did the case Enviroflow Management Ltd v Redhill Works 2017 establish?

A

Enviroflow Management Ltd v Redhill Works 2017 made it possible to recover adjudication cost but only if previously stipulated in writing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is arbitration?

A

Arbitration is a private, contractual form of dispute resolution. It is a procedure in which both sides agree to let an impartial third party, the arbitrator, decide the case in a tribunal. The arbitrator may be a lawyer, or may be an expert in the field of the dispute, or in some cases, an arbitration panel. The arbitrator’s decision, known as an award, is legally binding and can be enforced through the courts. Normally, there is no appeal, however there are exceptions in which appeals may be accepted. Arbitrators have the power to ascertain facts rather than just listen to submissions, and to order costs.

For arbitration to apply, the contract between the parties must contain a written agreement to arbitrate. Where it applies the parties might choose to refer to or incorporate an arbitration procedure, such as the Construction Industry Model Arbitration Rules. Alternatively, the arbitration can simply be covered by the applicable legislation, such as the Arbitration Act 1996. Many jurisdictions around the world contain legislation dealing with arbitration, often based upon the United Nations Commission on International Trade Law (UNCITRAL) Model Arbitration Law.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What are some advantages of arbitration?

A
  • It is private - there is no public record of any proceedings, although not necessarily confidential.
  • Speed, although this depends very much on the manner in which the arbitrator conducts the arbitration.
  • The parties can agree on an arbitrator with relevant expertise in the matter. The arbitrators award can be enforced as a judgement of the court.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What are some disadvantages of arbitrations?

A

-The parties must bear the costs of both the arbitrator and the venue.
- Sometimes arbitration simply mimics court processes and so you do not get the advantage of informality and speed.
- Limited powers of compulsion or sanction if one party fails to comply with directions of the arbitrator, which can significantly slow down the process.
- The arbitrator has no power to make interim measures, such as for the preservation of property.
Limited appeal rights.
- Pacific Basin Ltd vs Bulkhandling HandyMax 2011

19
Q

What is PACT?

A

Professional Arbitration on Court Terms (PACT)
Commercial lease renewal dispute delegated to independent 3rd party expert who can act as arbitrator or independent expert without need of court proceedings. On agreement of both parties are as part of terms of lease renewal. Bound by result. No longer need to have court consent in all circumstances.

20
Q

What are the civil procedure rules?

A

Proceedings in the TCC are governed by the Civil Procedure Rules (CPR) and supplementary Practice Directions. CPR Part 60 and its associated Practice Direction deal specifically with the practice and procedure of the TCC.

CPR Rules provide that a TCC claim is a claim which:

Involves technically complex issues or questions (or for which trial by a TCC judge is desirable) and
Has been issued in or transferred into the TCC specialist list.
The TCC Practice Direction identifies the following as examples of the types of claim which it may be appropriate to bring as TCC claims (this list is not exhaustive):

  • Building or other construction disputes, including claims for the enforcement of the decisions of adjudicators under the Housing Grants, Construction and Regeneration Act 1996.
  • Engineering disputes.
  • Claims by and against engineers, architects, surveyors, accountants and other specialised advisors relating to the services they provide.
  • Claims by and against local authorities relating to their statutory duties concerning the development of land or the construction of buildings.
    etc
21
Q

What is the TCC?

A

TCC - The Technology and Construction Court (TCC) is a specialist court, which deals principally with technology and construction disputes.

Proceedings in the TCC are governed by the Civil Procedure Rules (CPR) and supplementary Practice Directions. CPR Part 60 and its associated Practice Direction deal specifically with the practice and procedure of the TCC.

22
Q

What is the pre-action protocol?

A

The Pre-Action Protocol for Construction and Engineering Disputes applies to all disputes in that category, including professional negligence claims against architects, engineers and quantity surveyors. A claimant must comply with the Protocol before commencing proceedings in the court, subject to some exceptions. In summary, the procedure requires:
- the claimant to issue a claim letter and attach copies of key documents such as the contract
the defendant to reply within 28 days, although that period can be extended
- the claimant to reply to any new issues within 14 days.
- The parties should then meet in order to discuss the issues in dispute and attempt to reach settlement on at least some aspects of the dispute.

The Pre-Action Protocol for Construction and Engineering Disputes also recommends that the parties should consider whether some form of ADR is more suitable than litigation. This accords with the Court of Appeal’s recognition in Burchell v Bullard that mediation should act as a track to a just result running parallel with that of the court system.

23
Q

What is CAP?

A

The RICS Conflict Avoidance Process (CAP) is a contractual mechanism which helps parties avoid prolonged and damaging disputes. The purpose of CAP is to enable contracting parties to identify and dispose of emerging disputes early. CAP involves the introduction of a panel of one or three impartial professionals (lawyers, surveyors, engineers, etc.) who are credible experts in the subject matter at the heart of an emerging dispute. The CAP Panel will work collaboratively alongside the parties, but may also conduct their own enquiries. They will within an expediated timetable agreed with the parties provide the contracting parties with a fully reasoned CAP Report containing recommendations for resolution of the matters which divide them. The CAP Panel will normally deliver the report at a face-to-face meeting with the parties. This enables the parties to discuss the report and recommendations in detail with each other and the CAP Panel.

24
Q

What did Pacific Basin Ltd v Bulkhandling Handymax 2011 determine

A

Pacific Basin Ltd v Bulkhandling Handymax 2011 found that despite an arbitrator error the decision was not overturned

25
Q

What is a surveyor advocate

A

a surveyor advocate is appointed by a party to present the case for the client using argument showing the tribunal why the clients case should be preffered.

You will need to follow the requirements of, and have regard to, the RICS practice statement and guidance note Surveyors acting as advocates. Your primary duty will be to your client, but it is also subject to some important duties to the tribunal that place limits on what it is proper to do in pursuit of your client’s interests.

You may act only in matters where you have:
(a) the experience, knowledge and expertise appropriate to the case; and
(b) the resources to carry out the assignment to the required timescale and to the appropriate standard.

Can be both an advocate and expert witness in some exceptional circumstances.

26
Q

What civil procedure rule applies to expert witnessess

A

Civil procedure rule 35 sets out some requirements for expert evidence

27
Q

What are some differences between adjudication and arbitration?

A

Finality - The decision of an Arbitrator is final and cannot be overturned in the courts (unless an appeal is expressly agreed beforehand). Whereas an adjudication decision can be enforced by using civil procedure rule 9 it can be appealed.

Speed - Adjudication tends to be quicker than arbitration as documents are shared faster and a decision is met over weeks rather than months.

Statutory - Statutory adjudication can be entered at any point during a dispute through means of the Housing Grants and Regeneration Act 1996. Whereas arbitration must be entered by agreement.

Awarding costs - Arbitrators have the power to award penalty costs whereas adjudicators can only recover their own fees.

28
Q

What is Early Neutral Evaluation

A

ENE is voluntary, confidential and conducted on a without prejudice basis by a TCC judge.
The evaluation is non-binding and aims to help clarify and define legal and factual issues in the dispute, identifying risks and likely outcomes before further significant resources are spent on the dispute. It can identify -
- Whether or not they have a good case. Potential financial consequences of pursuing a matter through litigation.
- Whether or not to settle and, if so, on what terms. The balance between what can be achieved through negotiated settlement and the likely costs and potential outcomes of litigation.

The evaluation draws on the evaluator’s previous experience in dealing with similar issues, and evaluating the law and facts in actual cases. It is the evaluator’s immense experience as a judge, arbitrator or similar that makes ENE valuable and evaluations so persuasive.

29
Q

Any RICS Guidance on Expert Witnesses?

A

See Surveyors acting as expert witnesses - RICS practice statement and guidance note

30
Q

What pre-requisites are there to surveyors acting as expert witensses?

A

You must only act as an expert witness and give expert evidence where you have:
- the ability to act impartially in the assignment (Refer to the
RICS guidance note Conflicts of interest).
- the experience, knowledge and expertise appropriate for the assignment; and
- the resources to complete the assignment within the required timescales and to the required standard.

31
Q

What happens if the surveyor is a poor expert witness?

A

The UK Supreme Court decision in Jones v Kaney (2011) made it possible to sue experts in negligence, marking a departure from the immunity that experts previously possessed. The decision raised the standards and accountability for expert witnesses and emphasised the importance of maintaining high professional standards.

32
Q

What is the RICS Dispute Resolution Service?

A

RICS Dispute Resolution Service (DRS) is the world’s oldest and largest provider of alternative dispute resolution (ADR) services in the land, property and construction industries.

They offer a range of dispute resolution and avoidance services, and inspire confidence in parties through impartiality and the quality of dispute resolvers.

33
Q

What is the RICS Expert witness service?

A

Dispute Resolution Service (DRS) has developed the Expert Witness Accreditation Service (EWAS) to provide reassurance to parties who instruct expert witnesses that their experts are appropriately experienced in the relevant subject matter. To provide reassurance to parties who instruct expert witnesses that their experts are:
- Appropriately experienced in the relevant subject matter
- Trained and assessed by RICS in the roles and duties of an expert witness
- Subject to the comprehensive quality control regime managed by RICS DRS

There are two different levels of RICS expert witnesses:
- RICS Registered Expert Witness
- RICS Accredited Expert Witness
These qualifications signal high standards of expertise and professionalism for expert witnesses underpinned by regulation. For more information on EWAS including what criteria must be met to reach Accredited status please visit here: Expert Witness Accreditation Service (rics.org).

DRS also offers an Expert Witness Referral Service and can nominate an appropriate expert witness or provide the contact details for three expert witnesses.

34
Q

How is CAP different to other forms of ADR?

A

CAP draws on methodologies used in other forms of dispute management and resolution, but it is not quasi-adjudication or arbitration, and it is distinguishable from Dispute Boards, whether standing or ad hoc.

Being a pay-when-needed service, CAP costs substantially less than maintaining a standing Dispute Board. It also enables parties to benefit from CAP panel members who are selected from the breadth of the RICS President’s Panel because they possess the specific skills and experience needed to deal with the dispute which has arisen. They can therefore bring a far more focused range of expertise to bear than that which can normally be provided by a traditional three-person standing Dispute Board, appointed in advance and acting for the duration of the project. CAP panellists are thus less likely to need additional expert reports, as they are selected specifically for their own expertise. As far as ad hoc Dispute Boards are concerned, a CAP serves a similar function, but does so in the context of an established RICS service with a superb track record, using panellists who genuinely understand and implement a significantly different approach to dealing with disputes.

35
Q

How are arbitrators?

A

Arbitrators can be appointed either by:

  • The disputing parties directly.
  • A combination of the parties (i.e. one party appoints one arbitrator, the other party appoints another, and both arbitrators appoint a third).
  • An external party (e.g. the court, or an individual/body nominated by the parties, such as a professional institution).

The selection process is one of the advantages to arbitration, in that someone can be appointed who has specialist knowledge and a solid understanding of the issues at hand. This is opposed to litigation, where there is no guarantee that the seating judge will have the required specialist knowledge.

36
Q

How do you avoid disputes in the first place?

A
  • risk management
  • Early warning systems
  • partnering techniques
  • Clear and robust project briefing
  • good record keeping
  • Good contract management
  • Clear compensation event procedure
37
Q

What are some benefits of ENE?

A

Faster than more traditional forms of dispute resolution.
Cannot be cited in litigation.
Highlight and clarify the issues in dispute
Encouraged by the TCC as it is included within their “Court Guide”

38
Q

What are some drawbacks of ENE?

A

Too short or informal to deal with complex technical disputes.
Cannot be cited in litigation.
“One party may become more entrenched in their views”

39
Q

What did Lomax v Lomax 2019 establish?

A

Lomax v Lomax 2019 Judges do not have the power to order early neutral evaluation without the consent of the parties

40
Q

What is a single joint expert

A

appointed by the tribunal, an expert is instructed to prepare a report for the tribunal on behalf of the parties.

41
Q

What are the duties of an expert witness?

A
  • Act independantly and impartially,
  • Assist the tribunal,
  • Provide a range of options where the evidence requires it,
  • Define and agree issues between the parties,
  • Help quantify or assess the amount of any sum in dispute,
  • Give expert evidence to the tribunal,
  • Conduct enquiries when instructed by the tribunal.
42
Q

What civil procedure rule applies to expert witnesses

A

Civil procedure rule 35 sets out some requirements for expert evidence

43
Q

What is the RICS expert witness accreditation service

A

EWAS is designed to raise the standards as there had not previously been any quality control. It sets universal standards for expert witnesses across the property and built environment sector