Hackney Conservation Windows Flashcards

1
Q

In Procurement and Tendering, you mention Tender Report - what was the contract sum? What was your analysis of the winning tenderer in terms of price certainty/competitivenss?

A

Contract Sum - ref flashcards on contract sums.
Analysis of winning tenderer (price certainty):
- question overkill???

Analysis of winning tenderer (competitiveness):
-question overkill???

Analysis of winning tenderer (value for money):
-question overkill???

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

In Risk, you mention an operational risk was the management of residents - was this risk evaluated and cost allowances attributed for this? What was the value of the cost allowance allowed for this? How did you go about developing an allowance for this risk?
What sort of additional costs might have arisen if residents weren’t managed effectively?

A

Yes, a risk register was prepared.
The various aspects of the problems that may be encountered were listed (resident management problems; conservation area - planning problems; insufficient quality of execution; supplier problems for high quality materials ie windows/door conforming to designs - approximations of the quantities of these incidents (based on client past experience), approximations of EMV, and this informed the risk allowance.
Value based on Register (make it equivalent to 15% of above contract sum)
How go about - implicit in answer above sentences
Additional costs might have arisen - implicit in answer in above sentences

How well did you know this?
1
Not at all
2
3
4
5
Perfectly