H&S Questions Flashcards

1
Q

What is the Pre-construction information pack?

A

A Pre-Construction Information Pack is included with the Tender Documents and provides information to bidding contractors on:
- Description of the project
- Client considerations and management requirements,
- Environmental restrictions and existing on site risks,
- Significant design and construction hazards,
- Information on the format / presentation of the health and safety file

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Who is responsible for H&S?

A

The client is responsible for making arrangements for managing their project to ensure that health and safety risks are managed in a proportionate way. They must:
- Appoint competent duty holders.
- Allow sufficient time and resources.
- Prepare and provide relevant information to duty holders.
- Ensure that the Principal Designer and Contractor carry out their duties.
- Ensure welfare facilities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is included in a H&S file?

A

A) a brief description of the work carried out
B) any residual hazards which remain and how they have been dealt with (e.g surveys or info concerning asbestos; contaminated land; water bearing strata; buried services etc)
C) key structural principles and safe working loads for floors and roofs
D) hazardous materials used (for example lead paint; pesticides; special coatings which should not be burnt off etc);,
E) information regarding the removal or dismantling of installed plant and equipment (for example any special arrangements for lifting, order or other special instructions for dismantling etc)
F) health and safety information about equipment provided for cleaning or maintaining the structure
G) the nature, location and markings of significant services, including underground cables; gas supply equipment; fire-fighting services etc
H) information and as-built drawings of the structure, its plant and equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When is a BS a designer?

A

Under the CDM regulations, the BS is described as a ‘designer’ as they carry out work in connection with the structure or parts of the structure, make decisions on which materials will be used and on the preferred construction processes. There are five main responsibilities of designers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is CDM?

A

Construction, design and management regulations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is it and what does it mean?

A

Improves safety on site through design, planning and management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What do CDM regulations state?

A

Approved code of practice which gives advice on how to comply with HSE law.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Do CDM regulations apply to every project?

A

CDM Regulatons apply to all construction projects unless the client is domestic.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is an F10?

A

Notification of a project to the HSE detailing numbers on site, location, which local authority it’s in, when, duration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are your responsibilities under CDM as a BS?

A
  • Eliminate hazards and reduce risks during, design
  • Provide information about remaining risks
  • Check client is aware of their duties
  • Check HSE has been notified,
  • Provide any information needed for the health and safety file, by the end of the project
  • Check own competence,
  • Cooperate with others and coordinate work so as to ensure the health and safety of construction workers
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the CSCS?

A

Construction Skills Certification Scheme

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What safety precautions would you expect to see on site?

A

Accident book, site security, first aid, fire extinguishers, PPE, visitor sign in book (for fire evacuation)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What information do you have to provide the HSE with for a notifiable project?

A

Form F10 rev 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

If the principal designer is negligent who is responsible?

A

The Client, as they have to appoint someone competent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Who is responsible for health and safety pre and post contract?

A

The Client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What can be done on site construction work to prevent accidents?

A

Trips, working at height, confined space, hot permits, joint fire code

17
Q

If you see a sub-contractor not complying with safety regs, what would you do?

A

Tell them to stop and notify the contractor

18
Q

Where is the H&S file kept when the project finishes?

A

Remains with the finished building for use by future tenant/ landlord

19
Q

What is the contractors responsibility regarding H&S?

A
  • check clients are aware of their duties
  • satisfy themselves that they and anyone they employ or engage are competent and adequately resourced
  • plan, manage and monitor their own work to make sure that workers under their control are safe
  • ensure that any contractor who they appoint or engage to work on the project is informed of the minimum amount of time which will be allowed for them to plan and prepare before starting work on site
  • provide workers under their control with any necessary information, including about relevant aspects of other contractors’ work, and site induction (where not provided by a principal contractor) which they need to work safely, to report problems or to respond appropriately in an emergency
  • co-operate with others and co-ordinate their work with others working on the project
  • ensure the workforce is properly consulted on matters affecting their health and safety; and, obtain specialist advice
20
Q

How do CDM regulation influence the preparation of an estimate?

A

CDM influences the preparation of an estimate by requiring the Cost Manager to make adequate provision to ensure all obligations are priced unless specifically excluded.

21
Q

What are the latest asbestos regulations and who is the duty holder?

A

Control of Asbestos Regulations 2012. The duty holder is the owner of the premises or the person or organisation that has clear responsibility for the maintenance or repair of the premises.

22
Q

Who would need to be informed if the contractor found contaminated land

A

Environmental Agency should be informed of any land contamination that is found.

23
Q

When do the CDM regulations not apply

A

CDM regulations apply to all construction projects except domestic clients.

24
Q

Who is the principal designer?

A

The principal designer is appointed by the client and is responsible for managing H&S pre-consruction. They :
- Plan, manage, monitor and coordinate health and safety (pre-construction).
- Identify, eliminate or control foreseeable risks.
- Ensure Client and designers are aware of their duties and advise the Client on bringing together the pre-construction information.
- Provide relevant information to other duty holders.
- Liaise with Principal Contractor in the planning management, monitoring and coordination of the construction phase

25
Q

Is there any additional responsibilities upon the client under the CDM regulations?

A

The Client must take reasonable steps to ensure there is adequate time and resources to enable the construction work is carried out without risk to health and safety. Also to ensure that adequate resources is assigned to ensure any structure designed for use as a place of work can be used without risk to health and safety. The Client must also provide all reasonably expected information which is relevant to health and safety for the those involved in the project e.g. soil investigations, asbestos surveys, existing services routes, capacities and conditions, existing structure information.

26
Q

What are the categories of duty holders under the CDM Regulations?

A

Commercial clients, Domestic clients, Designers, Principal designer, Contractors, Principal contractor, Workers

27
Q

What constitutes a designer under the CDM Regulations?

A

Organisations or individuals who as part of a business, prepare or modify designs for a building, product or system relating to construction work.

28
Q

What types of contract are not covered under the CDM regulations

A

All construction is covered by CDM regulations except works which are to be undertaken by a domestic client.

29
Q

What are the 5 steps to risk assessment?

A

• Step 1 - Identify the hazards.
• Step 2 - Decide who might be harmed and how.
• Step 3 - Evaluate the risks and decide on precautions.
• Step 4 - Record your findings and implement them.
• Step 5 - Review your assessment and update if necessary.

30
Q

What does RIDDOR stand for?

A

Reporting of Injuries, Diseases and Dangerous Occurrences Regulations 2013. (RIDDOR) requires the ‘responsible person’ to notify any death, reportable injury, disease or dangerous occurrence to the HSE (on-line or by phone for death and serious injuries). The responsible person is the employer or, for the self-employed, the contractor or principal contractor.

31
Q

What is the role of the HSE?

A

To prevent work-related death, injury and ill-health

32
Q

What is the considerate contractors scheme?

A

CCS was set up in 1997 & is responsible for improving the image of construction. It monitors all registered sites and ensures best practices are carried out in particular on items such as engaging with local communities and site cleanliness.

33
Q

What is the Health and Safety at Work Act 1974?

A

This is the primary piece of legislation governing H&S in the United Kingdom. It places a statutory duty on all employers to provide and maintain equipment and systems of works that are safe and without risk to the health and safety of employees, or others who may be affected by their undertaking.