Grounding and Bonding Flashcards
A grounding electrode system is generally required for each building or structure served by a feeder.
True
According to the NEC, that which is built or constructed, other than equipment, best defines which of the following?
Structure
If the overcurrent protective device is located on a generator outside that supplies a separate building or structure, then the feeder is on the load side of an overcurrent device. In this case, the equipment bonding jumper (load side) with the feeder is sized based on the requirements in Section 250.102(C).
False
If the overcurrent protective device is not located on a generator outside that supplies a separate building or structure, then the feeder is on the line side of an overcurrent device. In this case, the supply-side bonding jumper with the feeder is sized based on the requirements in 250.102(C).
True
A structure is constructed or built and does not include electrical equipment.
True
Which of the following electrical systems is required to be grounded?
a. 120V, single-phase system
b. 240V, 3-phase, 3-wire, delta-connected system
c. 480V, 3-phase, 3-wire, delta-connected system
d. 2,300V, 3-phase, 3-wire, delta-connected system
e. 4,600V, 3-phase, 3-wire, delta-connected system
a. 120V, single-phase system
Correct
Which of the following systems is not required to be grounded because, if grounded, the phase-to-ground voltage would exceed 150?
a. 50V, single-phase system
b. 120V, single-phase system
c. 120/240V, single-phase, 3-wire system
d. 480V, 3-phase delta system
d. 480V, 3-phase delta system Correct
Class 2 load-side circuits for suspended ceiling low-voltage power grid distribution systems are required to be supplied by grounded systems.
False
Which of the following systems is required to be grounded?
a. 120V, single-phase system
b. 240V, 3-phase, 3-wire, delta system
c. 480V, 3-phase, delta system
d. 600V, 3-phase system
a. 120V, single-phase system Correct
Where a system bonding jumper for a separately derived system is a wire type, it is required to be sized using Table 250.102(C)(1) or the 12.5% rule based on the size of the largest derived ungrounded phase conductor(s) or the total circular mil (cm) area of all conductors connected to any one ungrounded phase at the source.
True
If a generator is installed on a premises wiring system, it must be grounded as a separately derived system if there is a switching action in the grounded conductor through the transfer switch.
True
The grounding electrode conductor for a single separately derived system is required to be sized using which NEC table?
Table 250.66
The grounding electrode conductor for a single separately derived system in accordance with ? must be sized at a minimum in accordance with the sizes in ? , based on the circular mil area of the largest ungrounded system conductor.
250.33(A)(5)/ Table 250.66
Where grounding electrode conductor taps are used for multiple separately derived systems, each grounding electrode conductor tap must be sized using Table 250.66 based on the largest ungrounded derived phase conductor(s) of the individual derived system it serves.
True
Metal water piping and interconnected metal building framing that exists in the area served by a separately derived system is required to be bonded to the grounded conductor of that separately derived system, and ? is used to size this bonding jumper or conductor.
Table 250.102(C)(1)