4 Business Case and Success Criteria Flashcards
Define success criteria
-Satisfaction of stakeholder needs for the deployment of a project
-Different to benefits which focus on the strategic intent and delivering of beneficial change
What are the 5 elements of the business case?
SECFM
-Strategic context
-Economic analysis
-Commercial approach
-Financial case
-Management approach
What are the 3 tools/techniques used for the business case?
-PESTLE
-SWOT
-VUCA
What does PESTLE stand for?
-Political
-Economic
-Sociological
-Technological
-Legal
-Environmental
What does SWOT stand for and what is it in relation to?
-Strengths
-Weaknesses
-Opportunities
-Threats
The organisation (e.g. opportunities outside of the organisation that the project could exploit)
What does VUCA stand for?
-Volatility (e.g. price of materials)
-Uncertainty
-Complexity
-Ambiguity (e.g. unidentified risks)
Give 6 reasons why it’s important to review the impact of changes in a project on the business case
-Business case justifies the initial and continued investment in the project
-Allows project manager to agree success criteria with the sponsor and stakeholders
-Record of decisions
-Periodic reviews and decision gates ensure investment remains aligned to expected benefits
-Definition and development phases - reviewed against progress made
-Used to form PMP
What will happen if the benefits defined are no longer viable?
Senior management may stop the project
Define outcome
-The changes, circumstances or behaviour that results from the use of an output
-Leads to realisation of benefits
Who owns the business case and when is it developed?
Project Sponsor
Concept phase
What does the success criteria define and how is it set?
What the project manager has to achieve and how
-Beginning of the project
-What’s being delivered (captured as part of requirements management process)
-Which criteria needs to be achieved by project end (documented as measurable objectives - e.g. delivered within budget)
Give 3 techniques used to monitor KPIs
-Gantt chart
-Milestone chart
-Network diagram
Give 3 benefits of keeping the business case up to date
-Ensures continuous justification
-Improves stakeholder confidence
-Enhances risk management