19.5 Integrated Planning New Flashcards
What influences the amount of content in the PMP?
Size and complexity of the project
Name the core 3 things the PMP demonstrates
-Essential management processes
-Project team intentions
-How the project will be managed
Name the 7 contents of the PMP
-Scope
-Cost
-Resources
-Time
-Benefits
-Delivery
-Management
What does the Scope element consult and what does it detail?
PBS and WBS
Acceptance criteria
What does the Cost element demonstrate?
CBS
What does the Resources element demonstrate?
Roles and responsibilities - OBS
What does the Time element demonstrate?
Timeline and deliverables aligned to the life cycle approach
What does the Benefits element consult and demonstrate?
Business Case
The value the project will deliver
What does the Delivery element demonstrate?
The delivery location and requirements etc.
What areas does the Management element cover?
-Quality
-Risks and issues
-Communication
-Project controls
Give 6 reasons why the PMP is important
-Communicates to stakeholders
-Key stakeholders are involved in production
-Reference for all stakeholders
-One source of the truth
-Contract between PM and PS
-Guides the team and is the baseline for measurement