Frustration Flashcards
Frustration intro
Following the formation of a valid contract, frustration occurs when there is an event that is not the fault of either party, but has significant impact on the obligations contained in the contract. English law will consider that such an event results in the frustration of the contract, with the consequence that the parties are relieved from further obligations, and may be able to recover money, or property and compensation for the work done prior to the frustrating event. The situation with which the doctrine of frustration is concerned is where a contract, as a result of some event outside the control of the parties, becomes impossible to perform.
Development of frustration cases
Paradine
Taylor v Caldwell
Davis Contractors Ltd
Paradine v Jane
contracts were absolute and subsequent events could not justify non-performance. In this case, the defendant has leased the land from the claimant which was not used for the defendant for three years because of the English civil war. The defendant then did not pay the rent for three years and claimant sued. The Kings bench held that the defendant was liable to pay rent even though he had not used the land during the war. If he wanted to be exempt from this rent he should have inserted a clause to that effect
Taylor v Caldwell
The Paradine approach however, proved to be too strict and potentially unjust. Therefore, the rule began to be relaxed and the modern doctrine of frustration began to develop and expand. This was seen through the case Taylor v Caldwell. Taylor ran a music hall for a series of concerts. A week before the first show was to take place the hall was destroyed by fire. Taylor sued the hall owner for breach of contract as he was unable to use it for the concerts. The court held that in contracts in which performance depends on the continued existence of a given person or thing, a condition is implied that the impossibility of performance arising from the purging of the person or thing shall excuse the performance.
Davis contractors Ltd
Claimant contracted to build 78 houses for the defendant for less then £100,000 within 8 months. However, due to a shortage of skilled labour the work ended up taking 22 months and costing over £100,000. The claimant argued the contract had been frustrated by the lack of availability of labour. The house of lords did not uphold this because there was no change in the significance of the obligation caused by an unforeseeable event. Non haec in foedera veni – it was not this that I promised to do. The operation of this approach requires the courts to decide what situations will make performance ‘radically different’
“there must be a change in the significance of the obligation that the thing undertaken would, if performed, be a different thing than that contracted for”.
Types of frustrating event
Ilegality
Pointless
Impossibility: destruction of subject matter, incapacity by either party, method on performance impossible, death of either party
Illegality
if something happened (new law / policy) which makes things impossible to perform. If you perform it is illegal.
Fibrosa v Fairbairn – case indicates that after a contract is formed, if a change in law makes its performance illegal, the contract will be frustrated. Case concerns a contract between English and polish companies for the purchase of machinery. In sept 1939 Germany invaded Poland and British declared war. Machinery which was due to be shipped to polish port was occupied by Germany. Contract was held to be frustrated because it was illegal to trade with the enemy.
Pointless
When something makes the performance of the contract pointless, for example booking accommodation to go and watch the rugby which is then postponed. Therefore pointless to go and stay in the accommodation because there is no rugby match on. This could be frustrated.
Krell v Henry – case indicates that a contract can be frustrated where a subsequent makes its performance pointless, although the contract is still technically possible to perform. Defendant contracted to rent a flat from the claimant for watching the coronation procession of the king. The coronation was postponed at the last moment due to the Kings illness. The defendant no longer wanted the room but the claimant sued for the rent. CoA held, although the contract was capable of physical performance, the contract was frustrated because the viewing of the procession was the foundation of the contract.
Destruction of subject matter
This is demonstrated in Taylor v Caldwell itself. If what is destroyed is fundamental to the performance of the obligation, then the doctrine will operate.
Taylor ran a music hall for a series of concerts. A week before the first show was to take place the hall was destroyed by fire. Taylor sued the hall owner for breach of contract as he was unable to use it for the concerts. The court held that in contracts in which performance depends on the continued existence of a given person or thing, a condition is implied that the impossibility of performance arising from the purging of the person or thing shall excuse the performance.
Incapacity of either party
If a contract envisages performance by a particular individual where no substitute is satisfactory, then the contract will generally be frustrated by the incapacity of the person concerned. This is seen in Condor v Barron Knights Ltd. Here the drummer of a band fell ill. He had agreed by contract to play for the defendants band for 7 nights a week however, the opinion of his doctor was that he would only be fit to work e or 4 nights a week. Court held that his contract of employment was discharged by frustration.
Robinson v Davison - Contract for a piano player to play at a concert. The pianist became ill and unable to perform, and the claimant suffered losses. He sued for breach of contract, but it was held that the contract had become impossible to perform and so was frustrated.
Method of performance becomes impossible
Nickoll and Knight v Ashton Edridge & Co, a contract for cotton seed to be shipped from Egypt to England. The contract specified that The Orlando was to carry the cargo. The ship became damaged and had to go in for repairs. As this was a stipulated method of performance, the contract was frustrated as this could not be done.
Limitations on frustration
Self-induced frustration
Foreseeable event
More onerous or expensive
Self-induced
A contract will not become frustrated by an event which is the fault of one of the parties. This is called self-induced frustration and the contract will not be discharged. An example of the is Maritime National Fish Ltd. The appellants chartered a ship for a year. Both parties were aware that due to the type of ship, it was illegal to use it without a licence. The charters were only granted 3 licences, when they required 5. They used the three for the ships that they already owned. They claimed the contract had been frustrated as the government had refused to grant more licences. However, the Privy Council held that the defendants were not discharged. It was their own election to use the licences with the other boats that had led to them being unable to use the chartered ship
Foreseeable event
It is assumed that the contract is made with the knowledge of what could reasonably happen in the future. Davis Contractors, Davis contracted to build 78 houses for Fareham in 8 months, at a price of £94,000. Due to shortages in skilled labour and materials, the work took 22 months and cost a lot more. Davis were paid the agreed price, however they argued that the contract had become frustrated and sought payment based on quantum meruit. HofL held the events were reasonably expected during a contract for building houses and should have been foreseen.
More onerous
A contract will not be frustrated simply because its performance has become more onerous or expensive than anticipated. Tsakiroglou & Co Ltd v Noblee Thorl GmbH, Contract to ship peanuts from Sudan to Hamburg in Nov/Dec 1956. On 2 Nov, the Suez Canal was closed to shipping. The defendant argued the contract had been frustrated. The defendant could have transported the peanuts in the contractually agreed time, going around the Cape of Good Hope, but would have taken much more time and cost a lot more. The court held that just because it is more costly or difficult to perform the contract, does not make it frustrated.