Discharge of contract Flashcards
Discharge intro
There are several ways in which contractual obligations may be discharged. The relevant ways contracts may be discharged discussed here is by express agreement, performance or by breach. If both parties agree that neither of them wish to carry on with a contract that contains continuing obligations they may agree to bring it to an end early. In a bilateral agreement, the contract must be discharged by both parties. In unilateral agreements, the discharge is by one party. The focus here is on discharge by performance or by breach.
Case and facts for general rule for performance of contract
Cutter v Powell demonstrates this general rule. Mr Cutter contracted with a ship owner to act as septon mate on a ship for the whole journey from Jamaica to Liverpool for 13 guineas. He completed most of the journey but died before they arrived in Liverpool. Mrs Cutter didn’t receive any wages for her husband’s job for this journey. She sued the ship owner. The Kings Bench held because Mr Cutter contracted for the entire journey and failed to perform his widow was not entitled to any payment. This case was taken to lay down a general rule that in entire contracts, nothing is payable until the contract has been fully completed
Discharge by performance general rule
The general rule to terminate a contract through performance is that obligations must be completely performed.
Exceptions to discharge by performance
- Substantial performance
- Acceptance of partial performance
- Prevention of performance
- Severable obligations
Cases for substantial performance
Hoening v Isaacs
Bolton v Mahadeva
Substantial performance
This occurs where the majority of the contract has been performed.
Hoening v Isaacs
The defendants contracted with the claimant to decorate and furnish his flat for £750. The defendant paid £400 while the work was being carried, however he refused to pay the remaining £350 because of defects in the bookcase and wardrobe. This was found to be only minor details and the cost to correct was only £55. Court of appeal held the claimant was entitled to the contract price, less the price of correcting the defects because the contract was substantially.
Bolton v Mahadeva
This case indicates that the substantial performance exemption would not apply if there were significant defects. The claimant contracted with the defendant to install some central heating for the defendants house for £560. Upon completion the defendant refused to pay because the floor was defective and the system was ineffective. Although the cost of rectifying the defects were £174, the court of appeal found the claimant was not entitled to recover because the defects were so significant thereby there had been no substantial performance.
Acceptance of partial performance
If a party accepts partial performance, this may be sufficient to discharge the other party’s further obligations.
Acceptance of partial performance case
Sumpter v Hedges
Sumpter v Hedges
The need for acceptance is seen in Sumpter v Hedges. In this case, the plaintiff, a builder, contracted to build two houses and stables on the defendant’s land for £565. The plaintiff did work to the value of £333 and then abandoned the contract because he had no money. The defendant finished the buildings himself, using the building materials left by the plaintiff. The plaintiff brought an action to recover the value of the work he had done on the buildings. The court of appeal held that the plaintiff could not recover. The defendant had not voluntarily accepted their part performance.
Prevention of performance
This is when one party would not be able to perform because of the other parties breach of contract. The contract comes to an end without full performance.
Prevention of performance case
Planche v Colburn
Planche v Colburn
Planche v Colburn – Claimant agreed to write a book for the defendant as part of a series of children’s books. The agreed contract price was £100 to pay payable on completion. The claimant commenced the writing and had completed a good deal of it. However, the defendant then offered to publish the claimants book as one for adults instead. The claimant refused and sued the claimant for breach of contract to recover £50 for partial performance. Court held that the claimant was entitled to recover because the defendant had prevented the performance.
Severable obligations
A way to mitigate the harsh rule is to find that the contract is not entire but divisible into sections.