Foundation 6 Flashcards
Which is a PRINCE2 integrated element that offers checklists of activities and related responsiblities?
Processes
Which TWO are objectives of the ‘starting up a project’ process?
- To define the scope of the project to enable it to be initiated
- To assess the alternative ways of delivering a project
The Project Manager details quality standards and procedures that need to be followed on the project, together with information on tools and techniques that may need to be used. In which step of the quality management technique should this occur?
Describing the quality management approach
Approval for development specialist products is formally obtained as part of which process?
Direct a project
In which process is the project brief assembled?
Starting up a project
How does the managing a stage boundary process support the manage by stage principle?
Provides a review and decision point for the project board to determin whether to proceed to more detailed work
How does the authorization of initiation support the Define roles, responsibilities and relationship principles?
Confirms that all members of the project team have agreed their roles as outlined in the project brief
A new team member has just joined the project team and will be going on a site visit. In which step of the organizational design and development technique should this occur?
Develop of the project ecosystem
Who is accountable for the Business case for the duration of the project?
The project executive
Report highlights’ is an activity within which process?
Controlling a stage
Which statement correctly describes the relationship between project assurance and quality assurance?
Quality assurance provides assurance to the business layer where as project assurance provides assurance to the project’s stakeholders
The purpose of which practise is to to establish ways to monitor and compare actual achievements against those planned?
Progress
Which process creates the initiation stage plan as one of its products?
Starting up a project
What type of control is a highlight report?
Time-driven
The project manager needs to understand the project enviroment and define how to manage the risk on the project. In which step of the risk management technique should this be defined?
Identify
Identify the missing word(s) in the following sentence:
Culture is defined as ‘The set of [?], values, goals, and ways of working that characterize a group of people’.
Attitudes
What should be reviewed as part of ‘Authorize a work package’ activity?
The appropriate product descriptions
How are some of the seven aspects of project performance used when establishing business justification?
By understanding product quality requirements and how they impact on time, cost or sustainability targets
Why is the lessons report drawn up?
To provide a detailed lessons review of a specific lesson or a stage
The role to which Project Board members may delegate their assurance work is called quality assurance.
Quality assurance
Which is a purpose of a project brief?
To document a full and firm foundation for the initiation of the project
The PRINCE2 concept of stages equates to…
Commitment of resources
What type of control is a checkpoint report?
Time-driven
Who does the senior user represent when making decisions?
Those who benefit from using the project’s product