Foundation 6 Flashcards

1
Q

Which is a PRINCE2 integrated element that offers checklists of activities and related responsiblities?

A

Processes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which TWO are objectives of the ‘starting up a project’ process?

A
  1. To define the scope of the project to enable it to be initiated
  2. To assess the alternative ways of delivering a project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The Project Manager details quality standards and procedures that need to be followed on the project, together with information on tools and techniques that may need to be used. In which step of the quality management technique should this occur?

A

Describing the quality management approach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Approval for development specialist products is formally obtained as part of which process?

A

Direct a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

In which process is the project brief assembled?

A

Starting up a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How does the managing a stage boundary process support the manage by stage principle?

A

Provides a review and decision point for the project board to determin whether to proceed to more detailed work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How does the authorization of initiation support the Define roles, responsibilities and relationship principles?

A

Confirms that all members of the project team have agreed their roles as outlined in the project brief

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A new team member has just joined the project team and will be going on a site visit. In which step of the organizational design and development technique should this occur?

A

Develop of the project ecosystem

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Who is accountable for the Business case for the duration of the project?

A

The project executive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Report highlights’ is an activity within which process?

A

Controlling a stage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which statement correctly describes the relationship between project assurance and quality assurance?

A

Quality assurance provides assurance to the business layer where as project assurance provides assurance to the project’s stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The purpose of which practise is to to establish ways to monitor and compare actual achievements against those planned?

A

Progress

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Which process creates the initiation stage plan as one of its products?

A

Starting up a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What type of control is a highlight report?

A

Time-driven

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The project manager needs to understand the project enviroment and define how to manage the risk on the project. In which step of the risk management technique should this be defined?

A

Identify

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Identify the missing word(s) in the following sentence:
Culture is defined as ‘The set of [?], values, goals, and ways of working that characterize a group of people’.

A

Attitudes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What should be reviewed as part of ‘Authorize a work package’ activity?

A

The appropriate product descriptions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

How are some of the seven aspects of project performance used when establishing business justification?

A

By understanding product quality requirements and how they impact on time, cost or sustainability targets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Why is the lessons report drawn up?

A

To provide a detailed lessons review of a specific lesson or a stage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

The role to which Project Board members may delegate their assurance work is called quality assurance.

A

Quality assurance

21
Q

Which is a purpose of a project brief?

A

To document a full and firm foundation for the initiation of the project

22
Q

The PRINCE2 concept of stages equates to…

A

Commitment of resources

23
Q

What type of control is a checkpoint report?

A

Time-driven

24
Q

Who does the senior user represent when making decisions?

A

Those who benefit from using the project’s product

25
Notice of a potentially serious issue is received through an informal communication channel. In which step of the issue management technique should the Project Manager record this in an issue report?
Capturing issues
26
Which is NOT one of the five PRINCE2 integrated elements?
Plans
27
What are the five PRINCE 2 integrated elements?
Principles: The fundamental rules that guide the methodology. People: Roles and responsibilities within the project. Practices: Specific aspects of project management. Processes: A series of steps guiding the project through its lifecycle. Project Context: The environment in which the project operates
28
Which is a reason for reviewing the project brief during the Initiating a project process?
Provides details of the selected solution to be delivered by the project
29
Which option is extracted from the project brief to become part of the PID?
Project definition
30
Tailor to suite the project
> Use of terminology > Reflect the standards used in the industry > Alternative techniques or procedures for risk or issues practices > Reflect internal factors
31
Definition of Organizational ecosystem
The internal elements of an organization( including staff, board, owners, and other stakeholders) together with the organisations external relationships such as customers, suppliers, regulators, and competitors.
32
Definition of project ecosystem
Those elements of the business involved in or directly impacted by the project and the associated users and suppliers
33
Organizational Ecosystem
Also knows as "Business as Usual" - the normal, permanent elements of an organization
34
Project Ecosystem
Temporary organizational structure formed to deliver products
35
Definition of change management
Change management is the means by which an organization transitions from the current state to the target state
36
Definition of collaboration
People from across the project ecosystem working together to achieve the projects objectives
37
Definition of leadership
Motivating people to achieve a project objectves. On projects, this is best done through collaboration across the project ecosystem, persuading, influencing and co-creating with a focus on managing key relationships and seeking regular feedback to ensure team members remain aligned to the projects objectives and agree to joint ways of working
38
Definition of management
Instructing the execution of tasks in line with agreed ways of working. Co-creating ways of working with project team members (and stakeholders) significantly improves people's willingness to be managed in line with them
39
Definition of co-creation
A specific form of collaboration involing users and key influencers in the design of products and agreed ways of working to ensure they are adopted by the project and organizational ecosystem
40
People - Focused Activities
1. Leading Successful change 2. Leading successful Teams 3. Communication
41
Business objectives
The measurable outcomes that demostrate progress in relation to the organization's strategy and to which a project should contribute
42
Dis-benefits
The measurable declines resulting from an outcome, which would detract from one or more business objectives.
43
Business objectives
Demonstrate progress to an organization's mission, to which the project should contribute in some way
44
Do-Noting differently
carry on as you are, even if there is an aggressive new entrant in your marketplace
45
Purpose of the Business Case
Documents the business justification for the project
46
Benefits Management approach
Benefits the actions and benefits reviews that are required to ensure that the outcomes and benefits are achieved.
47
Sustainablitly management approach
TO define the actions, reviews, and controls what will be estableshed to ensure the that sustainablitily performance targets for the project are achieved
48
Sustainability tolerance
The permissable deviation in the sustainablility targets that is allowed before the deviation needs to be escalated to the next level of management
49
Benefits tolerance
The permissable deviation around expected benefits