Tolerance for the project as a whole ideally should first appear in the ‘Project Definition’ section of which management product?
Project Brief
The project manager identifies that work to be undertaken by the team is dependent on activities outside the scope of the project. In which step of the planning technique should the criteria be captured?
Organizing work packages
Which report contains details of request for change
Highlight report
From the product listed, which product is produced during Starting up a project?
The lesson Log
Which statement describes project assurance, rather than quality assurance?
It is independent of the project manager but not the project
Which is a purpose of a project brief
To document a full and firm foundation for the initiation of the project
Which of these products is produced in Initiating a product?
Risk Register
Which of these is specific objective of ‘Authorize a stage or exception plan’ decision point?
Ascertain the performance of the project so date
Which one of these items listed is an element of a PRINCE2 plan
Monitoring, control and reporting arrangements
Which is NOT an aspect of leadership
Instructing the execution of tasks in line with agreed ways of working
Identify the missing word in the following sentence:
Quality [?] captures quality specifications for the project products
Planning
Which is the definition of co-creation
Involving users and key influencers in the design of deliverables and agreed ways of working to ensure they are embedded by the project and organizational ecosystems
Which activity can take place within the ‘managing a stage boundary’ process
Produce an exception plan
What are the three basic levels of plan outlined in PRINCE?
Programme, project and stage
Whose responsibility is it to set the overall tolerance levels for the project?
The business layer
Which is a possible responsibility of Project Assurance
Crating of the quality management approach
In which process are checks made for changes to the project management team?
Managing a stage boundary
When a major deviation to a stage plan is forecast, what contains the project Manager’s description of the deviation, its consequences and list of options?
Exception report
Which of these options is a key criterion for the ‘Receive completed work package’ activity in the controlling a stage process
Is the work completed and approved?
Controlling a stage handles what part of the project?
Day-today management of the project
What is a product flow diagram?
An illustration of the sequence and interdependencies between products
Which option most fully describes the Managing product delivery process
Agree work with the project manager, get it done and hand it back
Which process ensures continued business justification for the project?
Directing a project
What are the types of issues?
Off-specification, request for change and problem of concern