1
Q

Communication Channels

A

n(n-1)/2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Present Value

A

FV/(1+i)^n

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Triangular Distribution

A

(Optimistic + Most Likely + Pessimistic) / 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Beta Distribution (PERT)

A

(Optimistic + (4 x Most Likely) + Pessimistic) / 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Activity Standard Deviation

A

(Pessimistic - Optimistic) / 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Total Float (aka Slack)

A

LS - ES or LF - EF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Expected Monetary Value

A

Probability x Impact

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

EF (early finish)

A
EF = ES + DU -1
Forward = pick largest EF
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

LS (late start)

A
LS = LF - DU + 1
Backward = pick smallest LS
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Critical Path Method

A

Longest path through network w/ 0 float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Goldratt’s Theory

A

Theory of constraints.

Project no stronger than weakest link

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

NPV

A

PV/E(1+i)^n - Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly