Formulas (Earned Value) Flashcards
PV
Planned Value:
Value of work to be completed to point in time.
EV
Earned Value:
EV = sum of planned value of work
AC
Actual Cost:
Cost of work completed at point in time
BAC
Budget at Completion:
Value of total planned work (aka project cost baseline)
CV
Cost Variance:
Amount of deficit or surplus at point in time.
CV = EV - AC
SV
Schedule Variance:
Amount project is +/- planned delivery date.
SV = EV - PV
VAC
Variance at Completion:
Estimated difference in cost at completion.
VAC = BAC - EAC
CPI
Cost Performance Index:
Measure of cost efficiency.
CPI = EV/AC
SPI
Schedule Performance Index:
Measure of schedule efficiency.
SPI = EV / PV
EAC
Estimate at Completion:
Total anticipating spending (at start of project).
Typical variance EAC = BAC / CPI (excl abnorm events)
Atypical variance EAC = AC + BAC - EV (incl abnorm events)
ETC
Estimate to Complete:
Expected cost to finish all remaining work.
ETC = EAC - AC
TCPI
To Complete Performance Index:
Measure of cost performance required to achieve management goal with remaining resources.
Complete on plan TCPI = (BAC - EV) / (BAC - AC)
Complete on current EAC
TCPI = (BAC - EV) / (EAC - AC)
Burn Rate
AC / EV
Fixed Formula Status Reporting
30%/70%