Formulas (Earned Value) Flashcards

1
Q

PV

A

Planned Value:

Value of work to be completed to point in time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

EV

A

Earned Value:

EV = sum of planned value of work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

AC

A

Actual Cost:

Cost of work completed at point in time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

BAC

A

Budget at Completion:

Value of total planned work (aka project cost baseline)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CV

A

Cost Variance:
Amount of deficit or surplus at point in time.
CV = EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

SV

A

Schedule Variance:
Amount project is +/- planned delivery date.
SV = EV - PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

VAC

A

Variance at Completion:
Estimated difference in cost at completion.
VAC = BAC - EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

CPI

A

Cost Performance Index:
Measure of cost efficiency.
CPI = EV/AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

SPI

A

Schedule Performance Index:
Measure of schedule efficiency.
SPI = EV / PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

EAC

A

Estimate at Completion:
Total anticipating spending (at start of project).
Typical variance EAC = BAC / CPI (excl abnorm events)
Atypical variance EAC = AC + BAC - EV (incl abnorm events)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

ETC

A

Estimate to Complete:
Expected cost to finish all remaining work.
ETC = EAC - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

TCPI

A

To Complete Performance Index:
Measure of cost performance required to achieve management goal with remaining resources.
Complete on plan TCPI = (BAC - EV) / (BAC - AC)
Complete on current EAC
TCPI = (BAC - EV) / (EAC - AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Burn Rate

A

AC / EV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Fixed Formula Status Reporting

A

30%/70%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly