Formulas Flashcards

1
Q

Formula for Estimate to Complete

A

ETC=BAC-EV - for atypical variance, assumes future work to be performed as budgeted
ETC=(BAC-EV)/CPI or BAC-AC - for typical variance, assumes past perf to continue throughout.
ETC is the forecasted amount of money it will take to complete from this point going forward (vs. EAC which is the forecasted amount it will cost at the end of the project vs BAC which is the budgeted cost for the project set at the beginning of the project).

The distinctions are subtle, but if your EAC is higher than your BAC you may have risk or perf problem with the project (deviation from plan). They are equal at the start of the project but as perf metrics are factored in EAC and ETC change.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Formula for Estimate at Completion

A

EAC=BAC/Cumulative CPI - Assumes past performance will continue throughout (aka typical)
EAC=AC+Bottom-up ETC - use when original estimate is flawed.
EAC=AC+BAC-EV - Assumes future work perf as budgeted. (aka atypical)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Formula for Schedule Variance

A

SV=EV-PV

Scheduled Variance=Earned Value - Planned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Formula for Schedule Performance Index

A

SPI=EV/PV >1 is ahead of schedule

SPI = Earned Value / Planned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Formula for Cost Variance

A

CV=EV-AC

Cost Variance=Earned Value-Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Formula for Critical Path

A

Start date + critical path duration - 1d = Finish date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Formula for TCPI

A

To Complete Cost Performance Index (TCPI)
TCPI [BAC] = ( BAC - EV ) / ( BAC - AC )
TCPI [EAC] = ( BAC - EV ) / ( EAC - AC )

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Formula for Duration

A

Duration=(Quantity of work x Productivity rate) / # of resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Number of communication channels

A

n(n-1)/2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

PV

A

PV=BAC x (time passed/total schedule time)
Planned Value=Budget at completion x time passed/total schedule time
Planned Value represents the approved budget that has been allocated to complete a scheduled task during a specific time period at this point in the schedule AKA BCWS (Budgeted Cost Work Scheduled).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

EV

A

EV=BAC x (Work completed/total work required)
Earned Value=Budget at completion x work completed/total work required)
Earned Value represents how much value should have been earned by work that has been completed up to this point in time. AKA BCWP (Budgeted Cost Work Performed)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Distortion vs. Distraction

A

Distortion - static or garbled message

Distraction - blinking light

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

FAIRNESS vs RESPECT vs HONESTY vs RESPONSIBILITY

A

Fairness - acting impartially and objectively
Respect - showing a high regard for others and resources you are entrusted with
Honesty - being truthful in your actions and conversations
Responsibility - the duty of taking ownership of decisions, actions, and their consequences

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

code of ethics vs. code of conduct

A

Code of ethics is aspirational principles you should follow (make decisions in the interest of safety/society),
Code of conduct is mandatory rules on what employees can and can’t do

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

change log vs. issue log

A

Change log documents and tracks the status of change requests. Issue log documents and tracks issues that may or may not become change requests.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

responsibility

A

our duty to take ownership for the decisions we make or fail to make, the actions we take or fail to take, and the consequences that result.

17
Q

CPI

A

CV=EV/AC

Cost Variance=Earned Value/Actual Cost

18
Q

SPI

A

SPI=EV/PV

SPI=Earned Value/Planned value

19
Q

Three point estimates

A

w1(To) + w2(Tp) + w3(Tp) /total of weights

Ex. 1(1) + 1(4) +4(3)/6=Three point estimate

20
Q

ETC

A

ETC=EAC-AC

21
Q

Std Deviation on a PERT estimate

A

(P-O)/weight <=usually 6

(Pessimistic-Optimistic)/6

22
Q

EV formula

A

EV = Actual % complete * BAC
EV = 6/7 * BAC
in this case I was asked to evaluate a 7 week project on week 7, but it was a week behind hence 6/7

23
Q

Formula for Total Float

A

Float = Late Start (LS) – Early Start (ES)
or
Float = Late Finish (LF) – Early Finish (EF)

24
Q

Theory Z

A

Management Theory that says that giving workers jobs for life motivates them to perform their best.

25
Q

Administer Procurements is the same as

A

Control Procurements