Formulas Flashcards
Formula for Estimate to Complete
ETC=BAC-EV - for atypical variance, assumes future work to be performed as budgeted
ETC=(BAC-EV)/CPI or BAC-AC - for typical variance, assumes past perf to continue throughout.
ETC is the forecasted amount of money it will take to complete from this point going forward (vs. EAC which is the forecasted amount it will cost at the end of the project vs BAC which is the budgeted cost for the project set at the beginning of the project).
The distinctions are subtle, but if your EAC is higher than your BAC you may have risk or perf problem with the project (deviation from plan). They are equal at the start of the project but as perf metrics are factored in EAC and ETC change.
Formula for Estimate at Completion
EAC=BAC/Cumulative CPI - Assumes past performance will continue throughout (aka typical)
EAC=AC+Bottom-up ETC - use when original estimate is flawed.
EAC=AC+BAC-EV - Assumes future work perf as budgeted. (aka atypical)
Formula for Schedule Variance
SV=EV-PV
Scheduled Variance=Earned Value - Planned Value
Formula for Schedule Performance Index
SPI=EV/PV >1 is ahead of schedule
SPI = Earned Value / Planned Value
Formula for Cost Variance
CV=EV-AC
Cost Variance=Earned Value-Actual Cost
Formula for Critical Path
Start date + critical path duration - 1d = Finish date
Formula for TCPI
To Complete Cost Performance Index (TCPI)
TCPI [BAC] = ( BAC - EV ) / ( BAC - AC )
TCPI [EAC] = ( BAC - EV ) / ( EAC - AC )
Formula for Duration
Duration=(Quantity of work x Productivity rate) / # of resources
Number of communication channels
n(n-1)/2
PV
PV=BAC x (time passed/total schedule time)
Planned Value=Budget at completion x time passed/total schedule time
Planned Value represents the approved budget that has been allocated to complete a scheduled task during a specific time period at this point in the schedule AKA BCWS (Budgeted Cost Work Scheduled).
EV
EV=BAC x (Work completed/total work required)
Earned Value=Budget at completion x work completed/total work required)
Earned Value represents how much value should have been earned by work that has been completed up to this point in time. AKA BCWP (Budgeted Cost Work Performed)
Distortion vs. Distraction
Distortion - static or garbled message
Distraction - blinking light
FAIRNESS vs RESPECT vs HONESTY vs RESPONSIBILITY
Fairness - acting impartially and objectively
Respect - showing a high regard for others and resources you are entrusted with
Honesty - being truthful in your actions and conversations
Responsibility - the duty of taking ownership of decisions, actions, and their consequences
code of ethics vs. code of conduct
Code of ethics is aspirational principles you should follow (make decisions in the interest of safety/society),
Code of conduct is mandatory rules on what employees can and can’t do
change log vs. issue log
Change log documents and tracks the status of change requests. Issue log documents and tracks issues that may or may not become change requests.