Formulas Flashcards
What is the PERT estimate formula?
(O +4M + P)/6 Example: If Optimistic is 2, most likely is 4 and pessimistic is 12 days the formula would be [2+(4*4) +12]/6 = 30/6 = PERT estimate is 5 days
What is the Free Float (FF) formula?
Free float is the Early Start (ES) of the successor activity minus the Early Finish (EF) of the activity you are calculating the Free Float (FF) for.
What is the Total Float (TF) formula?
The total float (TF) formula is the Late Start (LS) - Early Start (ES) of the activity you are calculating the TF for.
What is the Early Start (ES) formula?
Early Start formula is the maximum of all predecessor activities Early Finish (EF). Example: If Activity D is a successor of Activity B and Activity C, and Activity B has an EF of 12 Weeks and activity C has an EF of 6 weeks, the ES of Activity D would be 12. Since you can not start activity D until both B and C have finished.
What is the Early Finish (EF) formula?
Early Finish (EF) = Early Start (ES) + T where T equals the time estimated to complete the activity. Example: Say Activity Zed has an early start date of 3 and an estimated time of 5, that would be 3 + 5 = 8, giving Activity Zed an EF of 8
What is the Late Finish (LF) formula?
Late Finish (LF) = Is the minimum Late Start (LS) of all successor activities.
What is the Late Start (LS) formula?
Late Start (LS) = Late Finish (LF) - T, where T equals the time estimated to complete the activity. Note that you start with the project’s LF which is the same as the projects EF which would be calculated in your forward pass through.
What is the formula for Estimate at completion (EAC)?
Estimate At Completion(EAC) = Actual Cost (AC) + Estimate to Complete (ETC)
What is Planned Value (PV)
Planned Value (PV) is the target cost and schedule
What is Earned Value (EV)?
Earned Value (EV) is the actual schedule
What is Actual Cost (AC)?
Actual Cost (AC) is the actual cost
What are the Earned Value Management (EVM) metrics?
Planned Value (PV)
Earned Value (EV)
Actual Cost (AC)
What is Budget at Completion (BAC)?
Budget at Completion (BAC) equals the project’s cost baseline. There is no formula for calculating it, thus it is not often listed as a EVM metric.
What is Planned Value (PV)’s formula?
Planned Value (PV) = Planned%Complete x Budget at Completion (BAC)
What is the Cost Variance (CV) formula?
Cost Variance (CV) = Earned Value (EV) - Actual Cost (AC)