Formulas Flashcards

Formulas and Terms

1
Q

BAC

A

Budget at Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

EV

A

Earned Value
BAC x %work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

AC

A

Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

CV

A

Cost Variance
EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CPI

A

Cost Performance Index
EV / AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

PV (project)

A

Planned Value
BAC x %schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

SV

A

Schedule Variance
EV - PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

SPI

A

Schedule Performance Index
EV / PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

TCPI

A

To-Complete Performance Index
(BAC - EV) / (BAC - AC)
(BAC - EV) / (EAC - AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

VAC

A

Variance at Completion
BAC - EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

EAC

A

Estimate at Completion
AC + ETC
AC + BAC - EV or BAC - CV
BAC / CPI
AC + ((BAC - EV) / (CPI x SPI))

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Duration

A

Work x Rate / Resource

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

EAD
PERT distribution

A

Estimated Activity Duration
(a + 4(b) + c) / 6
a = minimum
b = most likely
c = max

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

EAD
PERT triangular

A

Estimated Activity Duration
(a + b + c) / 3
a = minimum
b = most likely
c = max

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

ETC

A

Estimate to Completion
(re-estimation of remaining work)
EAC - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

PV (financial)

A

Present Value
FV / (1 + r)^n
FV = Future Value
r = Interest rate
n = Number of periods

17
Q

Communication Channels

A

(N (N - 1)) / 2

18
Q

EMV

A

Expected Monetary Value
Probabilty x Impact

19
Q

EAD
Standard Deviation

A

Estimated Activity Duration
(c - a) / 6
c = max
a = min

20
Q

Total Float

A

Late Start (LS) - Early Start (ES)
Late Finish (LF) - Early Finish (EF)