Financial Contract Types Flashcards

1
Q

Cost VS Price

A

COST
- what it takes (dollars/resources) to produce particular product/service

PRICE
- what someone is willing to pay for product/service

  • usually PRICE > COST to give business profit
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Types of Financial Contracts

A
  • Lump Sum Contract
  • Unit Price Contract
  • Cost Plus Fee Contracts
  • Guaranteed Maximum Price (GMP) Contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Fundamental Ideas: avoiding risk <–> being competitive

A
  • risks that contractor can’t control –> pay risk premium to owner
  • risks that contractors can control –> manage risk
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Financial Contracts Risk Balance

A

Impose:
- high enough risk incentive so contractors does job efficiently
- low enough risk to have reasonably low bid
- according to contractor ability to tolerate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Derivative Results of Risks: Impact on Construction Timing

A
  • more risk on contractor = longer construction delay
  • owner can expedite –> pay higher price (risk premium) to contractor or shoulder risk
  • delay can have major costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Lump Sum

A

Firmly FIXED final PRICE:

HIGH RISK CONTRACTOR

  • owner knows actual cost of project before it begins
  • contractor required to achieve project at negotiated contract value
  • usually no fast track
  • usually high incentive to finish early at low cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Unit Price

A

QUANTITY X UNIT PRICE

HIGH RICK CONTRACTOR

  • prices for defined units
  • approx quantities provided by OWNER
  • payment based on installed quantities
  • used bc uncertainty in field quantities
  • used on heavy & highway contracts
  • contractor overhead must be in unit’s prices
  • lowest bidder selected
  • owner on site to measure quantitites
  • dependent on accuracy of estimation of quantities given by owner/designer

RISK ALLOCATION:
- price risk (unit price) –> CONTRACTOR
- length (quantity) –> OWNER

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost + Percentage Fee

A

HIGH RISK OWNER

  • owner pays
  • only used if pricing cant be calculated in any other way + urgency
  • no financial insurance of ultimate cost
  • little incentive to reduce costs
  • reward is same despite quality of work
  • allows collab at early stages of project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Cost + Fixed Fee

A

HIGH RISK OWNER

  • fee independent of the duration of project
  • only used if pricing cant be determined in alternative manner
  • no financial insurance of ultimate cost
  • little incentive to reduce costs, high incentive to finish early
  • promotes collab at early stages of project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

GMP - Variation of Cost + Fixed Fee

A
  • GMP is defined price for undefined product
  • contractor assumes any additional costs after ceiling point is reached
  • quality may be sacrificed to avoid increases in cost beyond GMP
  • GM shared savings –> below guaranteed max , savings are shared btwn owner & contractor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does the choice of contract type depend on?

A
  • accuracy of estimation
  • ultimate cost known since beginning
  • desired risk
  • priority of the goal (eg quick completion of work)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly