Financial Contract Types Flashcards
Cost VS Price
COST
- what it takes (dollars/resources) to produce particular product/service
PRICE
- what someone is willing to pay for product/service
- usually PRICE > COST to give business profit
Types of Financial Contracts
- Lump Sum Contract
- Unit Price Contract
- Cost Plus Fee Contracts
- Guaranteed Maximum Price (GMP) Contract
Fundamental Ideas: avoiding risk <–> being competitive
- risks that contractor can’t control –> pay risk premium to owner
- risks that contractors can control –> manage risk
Financial Contracts Risk Balance
Impose:
- high enough risk incentive so contractors does job efficiently
- low enough risk to have reasonably low bid
- according to contractor ability to tolerate
Derivative Results of Risks: Impact on Construction Timing
- more risk on contractor = longer construction delay
- owner can expedite –> pay higher price (risk premium) to contractor or shoulder risk
- delay can have major costs
Lump Sum
Firmly FIXED final PRICE:
HIGH RISK CONTRACTOR
- owner knows actual cost of project before it begins
- contractor required to achieve project at negotiated contract value
- usually no fast track
- usually high incentive to finish early at low cost
Unit Price
QUANTITY X UNIT PRICE
HIGH RICK CONTRACTOR
- prices for defined units
- approx quantities provided by OWNER
- payment based on installed quantities
- used bc uncertainty in field quantities
- used on heavy & highway contracts
- contractor overhead must be in unit’s prices
- lowest bidder selected
- owner on site to measure quantitites
- dependent on accuracy of estimation of quantities given by owner/designer
RISK ALLOCATION:
- price risk (unit price) –> CONTRACTOR
- length (quantity) –> OWNER
Cost + Percentage Fee
HIGH RISK OWNER
- owner pays
- only used if pricing cant be calculated in any other way + urgency
- no financial insurance of ultimate cost
- little incentive to reduce costs
- reward is same despite quality of work
- allows collab at early stages of project
Cost + Fixed Fee
HIGH RISK OWNER
- fee independent of the duration of project
- only used if pricing cant be determined in alternative manner
- no financial insurance of ultimate cost
- little incentive to reduce costs, high incentive to finish early
- promotes collab at early stages of project
GMP - Variation of Cost + Fixed Fee
- GMP is defined price for undefined product
- contractor assumes any additional costs after ceiling point is reached
- quality may be sacrificed to avoid increases in cost beyond GMP
- GM shared savings –> below guaranteed max , savings are shared btwn owner & contractor
What does the choice of contract type depend on?
- accuracy of estimation
- ultimate cost known since beginning
- desired risk
- priority of the goal (eg quick completion of work)