Estimating Flashcards

1
Q

What is a Conceptual Estimate

A
  • done when project is first conceived before the design begins
    -establishes rough budget for fiscal planning
  • calculated using major project features
  • refers to cost of similar facilities (with adjustments)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a Preliminary Estimate

A
  • done when conceptual design completed
    -need to estimate total budget for financial commitment
  • calculated based on historical rates (ex. for a building : total area x cost/m^2, bridge: total length x cost?m etc)
  • +- 20% accuracy, done by owner
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is an approximate Estimate

A
  • done when design is finalized, for more accurate financing required
  • use as guideline for bid selecting and monitor during construction
  • owner hires engineers or quantity surveyors to estimate cost
  • use unit costs and required amount of work for estimation
  • +- 5% accuracy, done by owner’s engineer/quantity surveyor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a detailed bid estimate?

A
  • done when design finalized and preparing for a bid
  • contractor provides estimate of project based off owner
    calculated using unit cost in work items and required amount of work
  • reflects contractor’s desire to win project
  • += 2.5-5% accuracy, done by GC
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What costs are under Direct vs Indirect costs and how much percent do each take?

A

Direct cost (65-90%):
- Labour cost
- Material cost
- Equiptment cost
- Subtractor cost

Indirect cost (10-35%):
- Project overhead
- Markup

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are Labor Costs

A

Direct Labor costs: costs that are paid to field workers

Indirect Labor costs: costs that are additional to direct costs (payroll taxes, insurance, fringe benefits etc), usually = 25-50% of direct labour cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are Material costs

A

All costs in procuring materials (delivery, storage, inspection)

Contractor must:
- produce own materials (use own estimate) OR purchase materials from manufacturer
- include cost for storage, handling and installation of owner supplied or designated materials (excluding cost for purchasing materials)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are Equipment Costs

A

All the costs of renting equipment

Diff Cost Rates:
- cost/hour (eg. tractors, scrapers)
- cost/unit installed ( eg. concrete mixing)
- cost/week or month (eg. scaffolds)

Accuracy of cost estimate depends on equipment importance
- Major equip = very detailed analysis
- Minor equip (power tools concrete vibrator) = standard cost allowance
- Minor equip (hand tools, water hose) = lump sum allowance as % of direct labour cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are Subcontract Costs

A

GC subcontractor portions of work to subcontractors

Cost of subcontractors finalized before final bid

GC must review and select SC (like owner selects GC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is Project Overhead cost

A

All costs that don’t pertain directly to construction workers (5-15% total project cost)

Refer to list in pg.17 of Lecture 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are Markup Costs

A

Subjective

  • 5-20% total project cost
    -corporate overhead, contingency and profit
  • reflects contractors appraisal b/w being lowest bidder and having a higher chance to make profit

Factors:
- desire for work
- competition
- market conditions
- relationship with owner
- magnitude of risks and opportunities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly