FE Exam Formulas Ch. 14 Flashcards

1
Q

Purpose and Variables of…

A

Cost Variance

BCWP=Budgeted cost of work performed
ACWP=actual cost of work performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Purpose and Variables of…

A

Schedule Variance

BCWP=Budgeted cost of work performed
BCWS=budgeted cost of work scheduled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Purpose and Variables of…

A

Cost Performance Index

BCWP=Budgeted cost of work performed
ACWP=actual cost of work performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Purpose and Variables of…

A

Schedule Performance Index

BCWP=Budgeted cost of work performed
BCWS=budgeted cost of work scheduled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Purpose and Variables of…

A

Early Finish Date for an Activity

EF=Early Finish Date for an Activity
ES=earliest date that an activity can start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Purpose and Variables of…

A

Late Start for an Activity

LS=Late Start for an Activity
LF=late finish for an activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Purpose and Variables of…

A

Total Float or Flexibility of an Activity Start Date

LS=Late Start for an Activity
ES=earliest date that an activity can start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Purpose and Variables of…

A

Total Float or Flexibility of an Activity Start Date

LF=late finish for an activity
EF=Early Finish Date for an Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly