FastTrack Schedule (8) Flashcards
This set entered on 6-1-14
5.30.14.8
USING THE PROJECT INFORMATION FORM
1. What is the PROJECT INFORMATION FORM?
It is where you set the project work calendar, define the PROJECT’S START DATE and view the FINISH DATE AND TIME.
- How can you have “Data” scheduled before the project start date?
The “PROJECT” is a SUBSET of the DATA IN YOUR SCHEDULE, and it is determined by your DEFINITION of the START DATE. Thus, there CAN BE DATA SCHEDULED before the PROJECT START DATE.
- How do you set the PROJECT CALENDAR?
From the CALENDAR DROP DOWN LIST (PROJECT menu–>PROJECT INFORMATION), select Standard, 24 hour, Night Shift, or the name of a custom work calendar you have created.
- Is there an option to have more than one calendar type in the same project?
INDIVIDUAL ACTIVITIES AND RESOURCES CAN HAVE THEIR OWN WORK CALENDARS.
- By looking at the GANTT CHART, how do you know a PROJECT’S START DATE?
There will be a VERTICAL LINE IN THE TIMLINE on the DATE AND TIME specified.