FastTrack Schedule (12) Flashcards
This set entered on 6-1-14
- 31.14.4
- What are DOCUMENT PREFERENCES
Setting document preferences defines
a. the operation and formatting of currency
b. the behavior of bar and cursor tracking
c. the content of QuickLook balloons
d. and the archiving and privacy settings for the particular FastTrack Schedule file you are currently working with.
- Where do you find DOCUMENT PREFERENCES?
FASTTRACK SCHEDULE MENU–>DOCUMENT PREFERENCES
- What are the TABS in the DOCUMENT PREFERENCES?
a. General
b. Project
c. Currency
d. Tracking
e. QuickLook
f. AutoArchive
g. Privacy
- How do you set PROJECT PREFERENCES? (NOTE that it refers to PROJECT PREFERENCES, meaning the FILE you are working on, it is NOT a UNIVERSAL SETTING)
FASTTRACK
SCHEDULE MENU–>DOCUMENT PREFERENCES: PROJECT TAB.
- What options do you choose in the PROJECT PREFERENCES TAB of the DOCUMENT PREFERENCES dialog?
You can choose to set the work calendar and bar behavior options for your project
- PROJECT PREFERENCES: HOURS PER DAY. What is this?
Determines how many work hours there are in a Standard work calendar’s work day. If you want a work day to last from 9 AM - 5 PM rather than 8 AM - 5 PM, you would need to change the default setting from 8.00 hours to 7.00 hours, assuming a 1 hour lunch break.
- PROJECT PREFERENCES: HOURS PER WEEK. What is this?
Determines how many work hours there are in a Standard work calendar’s typical work week. If your company considers Saturday a work day, then you would want to adjust the default Hours per week total to reflect that.
- PROJECT PREFERENCES: LEAD/LAG CALENDARS. What is this?
Lets you choose which work calendar the lead/lag time of linked activities will use to determine a bar’s behavior.
- PROJECT PREFERENCES: FIXED DURATIONS SCHEDULING WHEN CREATING NEW BARS What is this?
Sets newly created activity bars to have a set, or fixed, duration.
- PROJECT PREFERENCES: IGNORE RESOURCE CALENDAR WHEN CREATING NEW BARS
When there is a conflict between the activity’s calendar and the assigned resource’s calendar, this will ignore the resource’s calendar and base the total work possible on the calendar indicated in that activity’s Information form.
- PROJECT PREFERENCES: APPLY EFFORT DRIVEN…
When a resource is assigned to an activity, the activity’s duration is determined by the amount of effort applied to that activity. This is the default behavior. You can set individual activities to be “Fixed Duration” by selecting that option in the activity’s Information form.