FA4 Flashcards

1
Q

Developing Project Charter is under what Knowledge Area?
Group of answer choices

Project Schedule Management

Project Integration Management

Project Scope Management

Project Communication Management

A

Project Integration Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Project Schedule Management Includes the processes required to ensure timely and appropriate planning, collection, creation, distribution, storage, retrieval, management, control, monitoring, and ultimate disposition of project information.
Group of answer choices

True

False

A

FALSE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

An uncertain event or condition that, if it occurs, has a positive or negative effect on a project objectives is termed.
Group of answer choices

Risk

Random chance

A disaster

Hazard

A

Risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

_________________________ Includes the processes involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs so the project can be completed within the approved budget.
Group of answer choices

Project Resources Management

Project Communication Management

Project Cost Management

Project Risk Management

A

Project Cost Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which of the following stakeholders is least likely to influence a project?
Group of answer choices

Project manager

Project funder/sponsor

Labor union president

Customer representative

A

Labor union president

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which of the following is not one of the potential responses to a specific risk event?
Group of answer choices

Ignoring

Transferring

Sharing

Mitigating

A

Ignoring

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Scope defines the boundaries of a project.
Group of answer choices

True

False

A

TRUE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which of the following is NOT one of the guidelines for selecting and recruiting team members?

A) recruit talented and highly motivated people

B) select the best task for each person

C) promote harmony by selecting team members who will complement and work well with each other

D) Make the team as large as possible to assure that you have the resources to complete the project within the schedule.

A

D) Make the team as large as possible to assure that you have the resources to complete the project within the schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The project schedule should be developed with an understanding of the required tasks, task duration, and task prerequisites.
Group of answer choices

True

False

A

TRUE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The attempt to recognize and manage potential and unforeseen trouble spots that may occur when a project is implemented is known as
Group of answer choices

Scenario analysis

Risk management

Contingency planning

Risk forecasting

A

Risk management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Jose is looking at a document that outlines the specific tasks and sub tasks required to complete the writing of a technical support manual. The method that was probably used to develop the document is most likely
Group of answer choices

Work package

Work breakdown structure

Priority matrix

Organization breakdown structure

A

Work breakdown structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Individual processes in the process groups are often iterated prior to completing a phase or project. The number of process iterations and interactions between processes varies based on the need of the project
Group of answer choices

True

False

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

One key to successful project management is to commit to a fixed budget and schedule as early as possible and then stick to it.
Group of answer choices

True

False

A

FALSE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

______________________ Includes the processes involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs so the project can be completed within the approved budget.
Group of answer choices

Project Integration Management

Project Scope Management

Project Quality Management

Project Cost Management

A

Project Cost Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Linda has just been assigned a project to develop a new advertising campaign for an established product. Her first step should be to
Group of answer choices

Establish project priorities

Determine the required completion date

Verify the budget available

Define the project scope

A

Define the project scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Planning identifies the required tasks to complete the project based on the project goal.
Group of answer choices

True

False

A

TRUE

17
Q

_____________________ defines the boundaries of a project.

A

SCOPE

18
Q

Planning Process Group are required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project was undertaken to achieve.
Group of answer choices

True

False

A

TRUE

19
Q

__________________ Process Group performed to complete the work defined in the project management plan to satisfy project requirements.

A

EXECUTING

20
Q

The Project Management Process Groups composed of _______ process groups that are independent of the application areas, or industry focus.
Group of answer choices

Five

Seven

Six

Four

Ten

Three

A

Five

21
Q

The intended outcome of strategy/projects integration is/are

A. Clear organization focus

B. Best use of scare organization resources

C. Improved communication across projects and departments

Group of answer choices

A and C only

A, B, and C

A and B only

B and C only

A

A, B, and C

22
Q

Project stakeholders:
Group of answer choices

are limited to the project manager, the customer, and the sponsor.

are interested parties outside the performing organization.

all share a common desire to see the project completed successfully.

have needs that should be identified and considered.

A

have needs that should be identified and considered.

23
Q

Monitoring and Controlling Process Group required to track, review, regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes.
Group of answer choices

True

False

A

True

24
Q

The project manager’s challenge is to keep the project team focused on the remaining project activities and delivery to the customer until the project is complete.
Group of answer choices

True

False

A

TRUE

25
Q

The result of subdividing the work of a project into smaller and smaller work elements is called ________.

A

WORK BREAKDOWN STRUCTURE

26
Q

The most common circumstance for project closure is simply a ________ project.
Group of answer choices

Overbudget

Completed

Overdue

Under achiveing

A

Completed

27
Q

Which of the following is considered a project resource?

A) people

B) services

C) facilities

D) money

A

A, B, C, and D

28
Q

The primary purpose of the first step of defining a project is to identify the ________ for the end user and to focus project plans.

A

OBJECTIVE

29
Q

The first step in creating the necessary information to manage a project is to
Group of answer choices

Define the project scope

Verify the budget available

Assign team members to work on the project

Determine the required completion date

A

Define the project scope

30
Q

Project scope describes what you expect to deliver to your customers when the project is complete.
Group of answer choices

True

False

A

TRUE

31
Q

A Process Group is a set of processes associated with a particular topic in project management.
Group of answer choices

True

False

A

FALSE

32
Q

A project manager must demonstrate people management skills to coordinate, delegate, motivate, advise, appraise, and reward team members.
Group of answer choices

True

False

A

TRUE

33
Q

_____________________ Includes the processes necessary to purchase or acquire products, services, or results needed from outside the project team.
Group of answer choices

Project Resources Management

Project Procurement Management

Project Communication Management

Project Risk Management

A

Project Procurement Management

34
Q

________________________ performed to formally complete and close a project, phase or contract.
Group of answer choices

Initiating Process Group

Monitoring and Controlling Process Group

Closing Process Group

Executing Process Group

Planning Process Group

A

Closing Process Group

35
Q

__________________________ performed to define a new project or a new phase of an existing project by obtaining authorization to start the project or phase.
Group of answer choices

Planning Process Group

Monitoring and Controlling Process Group

Executing Process Group

Closing Process Group

Initiating Process Group

A

Initiating Process Group

36
Q

Cost overruns are not a reason for project failure.
Group of answer choices

True

False

A

FALSE

37
Q

The method used to collect information to use through all phases of the project life cycle is called
Group of answer choices

Priority matrix

Responsibility matrix

Organization breakdown structure

Work breakdown structure

A

Work breakdown structure

38
Q

Scope defines both the boundaries of what is included in the system, as well as what is considered outside of the project.
Group of answer choices

True

False

A

TRUE

39
Q

In the beginning the focus of risk management should be on risks that ________________________
Group of answer choices

Have the greatest cost impact

Are known

Have the greatest schedule impact

Impact the whole project

A

Impact the whole project