Exercise 6: Planning Flashcards
1
Q
What are the goals of planning?
A
- Determine project duration
- Get accurate estimates
- Reduce the project time
- Find slack time
- Parallelize tasks
- Stay in the estimated project time
- Find critical activities
2
Q
Purpose of dependency diagrams
A
- Compute the project duration
- Determine activities that are critical to ensure a timely delivery
- Draw the dependency diagram
- Analyze the diagram
* Find ways to shorten the project duration
* Find ways to parallelize activities
* Analyze dependencies
- Analyze the diagram
- Two techniques are used
- Forward pass (determine critical path)
- Backward pass (determine slack time).
3
Q
Adjusting the estimation: 3-Point Method
A
- Disadvantage of PERT estimation: only one estimate per activity.
- Likelihood of being correct?!
- -> Cone of Uncertainty: estimation results can deviate from actual effort by a factor of 4.
- Estimation with PERT can be adjusted: use multiple estimates for each activity and calculate average and deviation.
- Estimate the best case, the likely case and the worst case.
- Effort for an activity i is calculated with the weighted average of the three estimates:
Ai = bci + 4*lci+wci / 6 - The standard deviation of estimation for activity i is: si = wci - bci / 6
- Effort of the whole project: Sum of Ai over N
4
Q
Estimation in Scrum: Planning Poker
A
- Estimation technique for complexity of user stories
- Entire development team participates in estimation
- Points are not equivalent to time units
- Points can be used to analyze team metrics
5
Q
Planning Poker: Rules
A
- Each member receives a set of cards containing modified Fibonacci numbers
0 1⁄2 1 2 3 5 8 13 20 40 100 - Scrum Master selects and reads a user story to discuss and defines the acceptance criteria
- Team discusses the complexity of the user story
- Each team member considers how many points the task should receive
- All team member’s suggestions are revealed simultaneously
- If estimates match –> done. Else, repeat steps 3-5 at most 2 times.
6
Q
Planning Poker: Pros and Cons
A
- Pros
- Team of experts leads to more accurate estimations than in traditional methods
- Distribution of workload according to skill: Developers who estimate few points are good candidates to implement the user story
- Developers having a role in what user stories they are responsible for in a sprint lead to a higher work motivation
- Cons
- Many people in a group may lead to long discussion
- Lazy developers want to overestimate tasks, in order to have less user stories assigned to them in a sprint
- People tend to want to average the amount of points, which limits the discussion and may not represent the actual difficulty of the task
7
Q
Tips for Planning Poker
A
- Keep discussions productive: Set a limited amount of time for each user story discussion. This helps teams learn to estimate more rapidly within agile planning.
- Break out into smaller sessions: Playing Planning Poker with a sub-set of the team is a good option if the number of user stories is too big.
- Choose the right time to play: Consider playing it several times; once at the kick off, and once before each Sprint.
- Write down the reason for the awarded points: If a user story receives too many points, make sure to note what were the Acceptance Criteria that led to that estimation.
- Consider the level of uncertainty: Does the implementation of this user story depend on too many unknown factors? If yes, maybe award more points.