Exam 2 Budget/Cost Interpretations Flashcards

1
Q

Interpret the CPI

A

For every dollar spend through week x, only xx was earned

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Interpret CV

A

The value of work done through week x is xx less than what was actually expected

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Interpret method 1 of FCAC

A

If the project continues at the current rate of efficiency, then it will cost xx to complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Interpret method 2 of FCAC

A

If the remainder of the project operates at an efficiency of 100%, then it will cost xx

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Interpret TCPI

A

This is the efficiency rate that must be achieved for the rest of the project to be completed on time and budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Interpret CBC

A

The cumulative budget for the project is xx

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Interpret CAC

A

The total actual amount spent after week x is xx

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Interpret CEV

A

The total earned value of work after x weeks is xx

How well did you know this?
1
Not at all
2
3
4
5
Perfectly