Exam 2 Budget/Cost Interpretations Flashcards
Interpret the CPI
For every dollar spend through week x, only xx was earned
Interpret CV
The value of work done through week x is xx less than what was actually expected
Interpret method 1 of FCAC
If the project continues at the current rate of efficiency, then it will cost xx to complete
Interpret method 2 of FCAC
If the remainder of the project operates at an efficiency of 100%, then it will cost xx
Interpret TCPI
This is the efficiency rate that must be achieved for the rest of the project to be completed on time and budget
Interpret CBC
The cumulative budget for the project is xx
Interpret CAC
The total actual amount spent after week x is xx
Interpret CEV
The total earned value of work after x weeks is xx