How do you incorporate uncertainty into planning the schedule?
With projects for which there is a high degree of uncertainty about the estimated duration for activities, it is possible to use three estimates for each activity (To, Tm, Tp)
What is the purpose and process of resource leveling?
Resource leveling, or smoothing, is a method for developing a schedule that attempts to minimize the fluctuations in requirements for resources. This method levels the resources so that they are applied as uniformly as possible without extending the project schedule beyond the required completion time. It is used when there is variation resource in requirements among activities.
Does resource leveling keep a project on schedule? If so, how?
Resource leveling keeps the project on schedule because activities are delayed only up to the point where all the positive Slack is used up, since any further delays would cause the project to extend beyond the project due date
What is the purpose and process of resource limited scheduling?
Resource limited scheduling is a method for developing the shortest schedule when the number or amount of available resources is fixed and cannot be exceeded. This method will extend the project completion time if necessary in order to keep within the resource limits.
Does resource limiting schedule and keep a project on the schedule? If so, how?
Resource limited scheduling does not necessarily keep the project on schedule. It may extend the schedule in order to keep within the resource limits.
What is a resource requirements plan?
Illustrates the expected utilization of resources by time period during the time span of the project.
What is the relationship between resource planning and the network diagram?
Using a network diagram, we can prepare a resource requirements plan that indicates what resources are required each day based on ES and EF times for each activity
What is the 2-step process for budgeting?
The project budgeting process has two steps. First, the project cost because estimate is allocated to the various work packages in the project Work breakdown structure. Second, the budget for each work package is distributed over the duration of the work package
Which activities of the first priority for corrective actions?
The activities with the least slack
3 Ways to reduce cost
1) analyze cost performance to determine which work packages may require a corrective action 2) decide what specific corrective action should be taken 3) revise the project plan, including estimated durations and cost, to incorporate the planned corrective action
Why manage cash flow?
The key to managing cash flow is to ensure that cash comes in faster than it goes out. This can be accomplished by asking the customer to: provide down payment, make equal monthly payments, provide frequent payments
What is the purpose of project crashing
It incrementally reduces the project duration with the smallest associated increase in incremental cost. It is used when the project schedule needs to be accelerated
What are the 5 assumptions of the time cost trade off a.k.a. project crashing
1) each activity has 2 pairs of duration and cost estimates: normal time and normal cost, crash time and crash cost
2) An activity’s duration can be incrementally accelerated from its normal time to its crash Time by applying more resources
3) An activity cannot be completed in less than its crash time, no matter how many additional resources are applied
4) the resources necessary to reduce an activity’s estimated duration from its normal crash time will be available when needed
5) within the range between an activity’s normal crash points, the relationship between time and cost is linear
What is risk?
An uncertain event, that if it occurs jeopardizes accomplishing the project objective
Why monitor risk?
Monitoring risk throughout the project enables project decisions to be based on current information about the project and its potential risks