Ethics Test Flashcards

1
Q

It is consist in the omission of the diligence which is required by the nature of the obligation

A

Negligence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

It cleanses the contract of its defects, in legal effects a winner of one’s right to annul the voidable contract

A

Ratification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Awarded to vindicate or recognize the right of the plaintiff which has been violated and not necessary to indemnify him for any loss suffered

A

Nominal Damages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Required by public policy, for want on acts that must be suppressed.

A

Exemplary damages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Are those which may be recovered when the court finds that some pecuniary loss has been suffered but its amount cannot, from the nature of the case, be proved with certainty

A

Temperate damages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The period of time allowed the contractor by the client in addition to the stipulated contract time necessitated by a duly issued extra work or change order

A

Additional contract time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Complains regarding unethical practices against interior designers are directed to the:

A

Chairman, Specialty Board of Interior Design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A government entity created under P.D. No. 223 to administer, implement and enforce the various regulatory laws and policies of the government relative to various professions.

A

PRC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Design studies to describe a recommended solution of the problem in overall sense is a

A

Schematics

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Additional labor,materials, supplies and other incidentals necessary to complete works but not originally called for in the contract is

A

Extra work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The Professional Organization of Interior Design in the Philippines is the

A

PIID

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A written additional information, provision, and/ or other document issued by the client prior to the closing date for the receipt of bids, which is made an integral part of the tender and Contract Documents

A

Bid Tender

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Medium used for gauging and controlling construction activities

A

CPM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

A more comprehensive system of time scheduling and permits a more realistic analysis of the daily problems of construction project.

A

Timetable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The period of time allowed by the owner the delay suffered by the contractor due to courses beyond his control

A

Contract time extension

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

An agreement by virtue of which the owner of a credit transfer his credit and its accessory right to another who acquired the power to enforce it to the same extent or the assignor duly approved by the client

A

Deed of Assignment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

The stipulated period of time within which the contractor shall complete the contact works

A

Original Contract Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

A written notice to the contractor of the date on which he is to begin the prosecution of the works he has contracted

A

Notice to Proceed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

A written notice from the owner to the successful Bidder stating that its Bid as been accepted and that, in accordance with the terms of the tender/bid documents, he is required to enter into contract and to furnish the required performance bond and other stipulated documents

A

Notice to Proceed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

The amount of credit extended the contractor by a bank of the other financing institution to cover the projected expenditures for out of pocket equipment rentals, material, etc. in the amount prescribed by the owner

A

Credit line

21
Q

The Difference between schedule and actual accomplishment per approved PERT / CPM and approved revisions, thereof, usually indicated in percentage

A

Slippage

22
Q

The individual, partnership, firm or corporation, joint venture, association or syndicate having a direct contract with the contractor for furnishing service under the contract duly approved by the owner

A

Joint venture

23
Q

Graphical presentation of the work involved in the project

A

Schematics

24
Q

The person of firm whose proposal has been accepted and to whom the contract was awarded

A

Contractor

25
Q

It includes earthquake, flood, typhoon, cyclone and other cataclysmic phenomena of nature and all misfortunes, which human precedence could not foresee or prevent

A

Force majeure

26
Q

A right enforceable against specific property to secure payment of an obligation

A

Surety

27
Q

The duration of time allowed by the contract for the completion of the project in any stipulated portion thereof

A

Contract time

28
Q

The essential reason which moves the contracting parties to enter a contract

A

Cause

29
Q

Shop drawing are usually done and prepared at his own expense by the

A

Architect

30
Q

In case of discrepancies in the drawing and figures of interior, the matter shall be submitted immediately to

A

Interior Designer

31
Q

The meeting of minds between two person whereby one bind himself with respect to the other in terms of performances or compensation

A

Contract

32
Q

written or printed description of work to be describing qualities of materials and mode of construction

A

Schedule of materials & finishes

33
Q

The law that establishes rights as well as duties of an individual is

A

Substantive law

34
Q

It is the signification by one party to another of his willingness to enter into a contract with him to the terms specified

A

Offer

35
Q

Equivalent to threats and need not be physical force employing necessary means to inflict the threatened injury

A

Violence

36
Q

Building or structures intended to be used for the manufacture and/ or production of any kind of article or product shall observe adequate

A

Environmental safeguards

37
Q

Primarily responsible for the enforcement of the provisions of section code 201 and in charged of issuing building

A

Building Official

38
Q

It is issued by the building official within 30 days after final inspection and when building or structure has fully complied with the provisions of section 309

A

Certificate of occupancy

39
Q

Upon completion of the construction, the logbook duly signed and sealed is submitted to the Building Official by

A

Licensed Architect or Civil Engineer

40
Q

The Building Official shall issue the building permit applied for from payment of the required fees by the applicant, within

A

15 days

41
Q

Shall be provided with positive noise abatement devise to tone down the noise level of equipment and machineries to acceptable limits

A

Industrial establishment

42
Q

The noise abatement devices to tone down noise level of equipment and machineries is set down by the

A

Dept. of labor and the national pollution control commission

43
Q

A permanent roofed structure above a door attached to the supported by the building and projecting over a wall or sidewalk

A

Canopy

44
Q

Habitable rooms provided with artificial ventilation shall have ceiling heights not less than

A

2.40 meters

45
Q

Shall have a clear ceiling height not less 1.80 meters above and below it.

A

Mezzanine

46
Q

Minimum ceiling height of building with more than one storey shall be

A

2.70 meters

47
Q

Every marquee shall be so located as not to interfere with the operation of any exterior

A

Fire hydrant

48
Q

A movable shelter supported entirely from an exterior wall of a building and of a type of which can be retracted, folded , or collapsed against the face of a supporting building

A

Awning

49
Q

Any material or structure temporarily occupying , public property including fence, canopies, and walkways, shall be adequately lighted between.

A

Sunset and sunrise