Estimating Flashcards

1
Q

What are the 6 levels of estimates?

A

1) Conceptual Estimate
2) Alternative Design Estimate
3) Architect’s/Engineer’s Estimate
4) Contractor’s Bid Estimate
5) Alternative Construction Methods Estimate
6) Change Orders and Claims Estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Talk about Conceptual Estimate:

A
  • for project feasibility studies
  • owner’s general scope
  • estimate based on broad scope/gross units (bldg. - sq. ft. , road - miles/mm)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Talk about Alternative Design Estimate:

A
  • to evaluate alternative designs
  • refer to past cost experience w/ similar projects
  • relies on bid abstracts from past similar projects
  • unit prices
  • rough quantification of units
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Talk about Architect’s/Engineer’s Estimate:

A
  • design proceeds to 80-90% completion
  • based on QTO
  • relies on past bid abstracts
  • will likely not consider construction methods
  • If owner hires a cost consultant, then estimate would be more sophisticated
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Talk about Contractor’s Bid Estimate:

A
  • Most detailed estimate
  • based on contractor’s quantity take-off
  • will consider construction methods
  • based on contractor’s detailed cost records
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Talk about Alternative Construction Methods Estimate:

A
  • to identify cheaper way of getting the job done

- goal is to maximize profit