Bid Item Format Flashcards
1
Q
What are the two bid item formats?
A
1) Lump Sum Bid
2) Schedule of Bid Item Bid
2
Q
What is the difference between the two formats?
A
The Schedule of Bid Item bid is more restricted
3
Q
List the horizontal breakdown:
A
- two labor components: labor & repair service labor
- two material components: permanent material & expendable material
- subcontractors
- equipment operating expense
- rental
4
Q
List the vertical breakdown:
A
- Direct Cost
- Indirect Cost
- Escalations
- Interest
- Contingency
- Markup
- Bond Fee