In ECA-3.1 state the procedure transition if any SG pressure is decreasing in an uncontrolled manner -OR- any SG is completely depressurized and has not been isolated
Go to E-2 Faulted SG Isolation, Step 1
In ECA-3.1 state the procedure transition if any SG level increases in an uncontrolled manner.
Go to E-3 SGTR, Step 1
State procedure transition at Step 13 of ECA-3.1 if RWST level is <310,000 gallons
If RWST level is <310,000 gallons then check Figure ECA-3.1-1 and determine is level is less then expected. If less than expected then Go to ECA-3.2 SGTR with loss of Reactor Coolant - Saturated Recovery Desired, Step 1
This is to conserve water.
State Procedure transition in ECA-3.1 at step 13 if SG NR >96%
Consult with TSC and go to ECA-3.2, step 1
In ECA-3.3 SGTR without Pressurizer Pressure Control state procedure transition if ECCS flow has been terminated and subcooling <40F or RVLIS is less than required for plant conditions
Manually align valves and start ECCS pumps as necessary and go to ECA-3.1
In ECA-3.3 state procedure transition if an RCP can be started
Once an RCP is started then go back to E-3 at step 17 and use normal spray to depressurize RCS
In ECA-3.3 state procedure transition if a PORV becomes available
Once a PORV becomes available then go back to E-3, Step 18 and use PORVs to depressurize RCS
In ECA-3.3 state procedure transition if an SI pump and Charging pump becomes available
Once Aux spray is in service then go to E-3, Step 17b and use aux spray to depressurize RCS
In ECA-3.3 state the procedure transition if RCS subcooling is <40F
Go to ECA-3.1 SGTR with loss of Reactor Coolant-Subcooled Recovery Desired
In ECA-3.3 state the procedure transition if an adequate heat sink can not be established
Go to ECA-3.1 SGTR with loss of Reactor Coolant-Subcooled Recovery Desired
In ECA-3.3 state the procedure transition if RVLIS indication is not with in requirements
Go to ECA-3.1 SGTR with loss of Reactor Coolant-Subcooled Recovery Desired
In ECA-3.3 state caution about implementing FR-P
In ECA-3.3 do not implement FR-P until after performing step 15. (Charging and LTDN has been established)
In ECA-3.3 state the procedure transition if pressure control is established and PZR level is restored to >7%[28%]
Go to E-3
In ECA-0.1 state the caution about SI at the beginning of the procedure
If SI is actuated prior to Step 3 of ECA-0.1 then reset SI to permit manual loading of equipment
In ECA-0.1 state when FRPs should be implemented
FRPs can be implemented after the completion of Step 9 (placing non-operating equipment in standby)