Energy and Atmosphere - EA Flashcards
<p>(EA - Fundamental Commissioning and Verification PRE) What stage in a project should a commissioning authority (CxA) be engaged?</p>
<p>By the Design Development phase</p>
<p>(EA - Fundamental Commissioning and Verification PRE) What qualifications must the CxA have?</p>
<p>- Have at least 2 projects experience (early design phase through 10 months of occupancy)- Must be independent of the design team for projects over 20,000sf</p>
<p>(EA - Fundamental Commissioning and Verification PRE) What does the CxA do?</p>
<p>- Review OPR, BOD, and project design- Develop and implement a Cx plan- Confirm incorporation of Cx requirements into the CD's- Develop construction checklists- Develop a system test procedure- Verify system test execution- Maintain an issues and benefits log through Cx process.Prepare for a final Cx report- Document all findings</p>
<p>(EA - Fundamental Commissioning and Verification PRE) What responsibilities do the three main stakeholders have?</p>
<p>Owner - Owner project requirements (OPR)Design team - Basis of design (BOD)CxA - Reviews these for completeness</p>
<p>(EA - Fundamental Commissioning and Verification PRE) What are the major Cx plan elements?</p>
<p>- Building occupancy schedule- Equipment run-time schedules- Setpoints for all HVAC equipment- Set lighting levels throughout the building- Minimum outside air requirements- Any changes in schedules (seasons, days of the week, etc.)- Mech &amp; Elec systems narrative- Preventative maintenance plan- A commissioning program</p>
<p>(EA - Fundamental Commissioning and Verification PRE) What are the minimum commissioned systems?</p>
<p>- HVAC &amp; R and associated controls- Lighting &amp; daylighting controls- Plumbing and domestic hot water systems- Renewable energy systems</p>
<p>(EA - Fundamental Commissioning and Verification PRE) What standards are referenced for this Prerequisite?</p>
<p>- ASHRAE 0-2005, The Commissioning Process- ASHRAE 1.1-2007, HVAC Process- NIBS 3-2012, Exterior Enclosure Technical Req.</p>
<p>(EA - Minimum Energy Performance PRE) Option 1, Whole Building Energy Simulation - What minimum percentage improvement should be demonstrated for new construction, major renovations, and core/shell compared to baseline energy usage?</p>
<p>- 5% NC- 3% Major Reno- 2% CS-5% Data CentersThese must be met before taking credit for renewable systems</p>
<p>(EA - Minimum Energy Performance PRE) Option 1, Whole Building Energy Simulation - What standard should be used to calculate the baseline building performance?</p>
<p>ANSI/ASHRAE/IESNA 90.1-2010</p>
<p>(EA - Minimum Energy Performance PRE) Option 2, Prescriptive Compliance: ASHRAE 50% - What types of projects use the Prescriptive Compiance for ASHRAE 50% Advanced Energy Design Guide for?</p>
<p>- Small to Medium Office buildings (<100,000sf)- Medium to Large Box Retail buildings (20,000sf-100,000sf)- For K-12 School Buildings- Large Hospitals (>100,000sf)</p>
<p>(EA - Minimum Energy Performance PRE) Option 3, prescriptive compliance: Advanced Buildings Core Performance Guide - What standard must be complied with?</p>
<p>- Mandatory and prescriptive provisions of ANSI/ASHRAE/IESNA 90.1 - 2010*building must be less than 100k sf to use Option 3</p>
<p>(EA - Minimum Energy Performance PRE) Option 3, prescriptive compliance: Advanced Buildings Core Performance Guide - What sections of the guide must be complied with?</p>
<p>Section 1) Design Process StrategiesSection 2) Core Performance RequirementsSection 3) Enhanced Performance Strategies: - 3.5 Supply Air Temperature Reset (VAV) - 3.9 Premium Economizer Performance - 3.10 Variable Speed Control*building must be less than 100k sf to use Option 3</p>
<p>(EA - Building-Level Energy Metering PRE) How can this prerequisite be achieved?</p>
<p>- Install building-level energy meters- Install submeters that can be aggregated to provide building-level dataEither of these must provide building energy consumption from electricity, natural gas, chilled water, steam, fuel, oil, propane, biomass, etc.</p>
<p>(EA - Building-Level Energy Metering PRE) Energy consumption data generated by meters must be shared with the USGBC for how long?</p>
<p>- Minimum of 5 years, beginning on the date the project accepts LEED certification*Energy consumption must be tracked at one-month intervals at a minimum</p>
<p>(EA - Building-Level Energy Metering PRE) What are the steps in building metering?</p>
<p>- Identify all energy sources that serve building- Determine scope of utility company metering- Determine number, type, and location of all meters- Track energy consumption data- Share whole-building energy consumption</p>
<p>(EA - Fundamental Refrigerant Management PRE) What standard is followed for this prerequisite?</p>
<p>EPA Clean Air Act, Title 6, Rule 608</p>
<p>(EA - Fundamental Refrigerant Management PRE) What is the main requirement for the prerequisite?</p>
<p>Don't use any chlorofluorocarbon (CFC) based refrigerants in the HVAC</p>