Electrical System (Ch. 2) Flashcards
1
Q
Three major loads
A
- Backup HYD pump (No 1 AC primary) will always be powered if required
- Mission avionics system (AC secondary). Tail rotor deice pwr is also on this bus
- Main rotor deice system (AC Monitor). Lowest priority.
2
Q
5 AC Electrical buses
A
- No. 1 AC Primary (backup hyd pump)
- No. 2 AC Primary
- AC Essential
- AC Secondary (mission pwr/tr deice)
- AC Monitor (main rotor deice)
3
Q
How is primary AC power supplied?
A
- By two oil cooled 30/45 kVA, 115-volt ac, 3 phase, 400Hz generators.
- driven by transmission accessory modules.
4
Q
Secondary ac power is supplied by ____
A
- an air-cooled 35-kVa, 115-volt ac, 3 phase 400 Hz generator driven by the APU
*
5
Q
What does the GCU do?
A
- Generator control unit
- connects each generator to the ac electrical bus system
- regulates generator output
- protects system composnents and circuitry against:
- overvoltage
- undervoltage
- feeder fault
- underfrequency
6
Q
When do you lose generators on ground?
in flight?
what percentage Nr is required for teh GCU to reconnect to the ac electrical distrib. system?
A
94% Nr
80% Nr
97% Nr
7
Q
What kind of battery is used?
A
24 volt dc Nickel Cadmium (NICAD) battery.
used to start APU and power Battery Utility Bus
8
Q
Two converters supply ____ ____ power.
what powers them?
A
- 28-volt dc
- powered by the No. 1 and No. 2 AC Primary buses.
9
Q
What does the battery analyzer/conditioner do?
A
- Monitors battery system for fault conditions, battery charge, internal temp, cell conditions, and charging.
- if a fault is sensed, it will automatically disconnect the dc loads from the battery, or the battery from the charging circuit.