Eddington Flashcards

1
Q

During Eddington, how did you assess contractors financial standing?

A
  • Requested within PQQ
  • Requested information relating to turnover & profit for last 3 years for applicant company and parent companies
  • Requested forecast turnovers for next financial year
  • Requested information regarding cash position for next 12 months
  • Ability to get Performance Bond
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What was the result of your findings from financial standings?

A
  • I advised my client sought specialist advise regarding in depth account reviews
  • I advised my client that the project for one of the contractors would represent a significant proportion of their anticipated turnover (£70m) which was a cause for concern
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why did you advise one of the contractors was not considered?

A
  • The project was significantly larger than their typical size. Their maximum project value to date was £27m
  • Programme was circa 40 weeks longer
  • Project would be a significant proportion of their anticipated turnover (£70m)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why did contractors withdraw from the process?

A
  • Contractors were not in a position to tender due to workloads
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Why was a two stage tender process used for Eddington?

A
  • My client wanted input on the buildability and design from the contractor. As a flagship project they were looking for integration of unique features - sub level games court, podium etc
  • Programme - wanted the project to be on construction phase as soon as possible, overlap of design and tender period
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

On Eddington, what was the tender opening procedure?

A
  • Occurred during lockdown of Covid-19
  • Received electronic submissions
  • Client and design team were invited to the tender opening virtually
  • Client attended along with 3 QS’s from Core Five
  • Tenders were open and recorded in the tender opening form reflecting numbers
  • Signed by present QS’s and client
  • Arithmetical checks followed - Alternative 2
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What were the objectives of reviewing the tenders on Eddington?

A
  • Identify any arithmetical errors
  • Assess any residual risks associated with each tender return
  • Ensure compliance and remove qualifications / exclusions e.g. one tenderer did not submit construction professional fee’s
  • Compare resourcing allowances to judge sufficiency - one tenderer appeared to have excessive levels of traffic marshalling however I determined through interviews the other tenderer had included this within general labour numbers and so ultimately was comparable
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How did the tender returns compare to your PTE on Eddington?

A
  • Ultimate number sat £300k above lowest and £2.5m below highest
  • Based on PQQ I had anticipated higher levels of prelims due to programme though these were then increased by impact of Brexit & Covid
  • I had anticipated higher risk by £500k
  • OH&P’s were lower than I had anticipated as they were looking to secure work following the pandemic
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What was the scoring matrix for Eddington?

A

Ranking from most important

  • Cost was most important
  • Project understanding, ethos, experience
  • Supply chain capabilities
  • Programme
  • H&S
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What was included in your tender report?

A
  • Exec summary
  • Contractor selection & tender issue
  • Tendering opening record
  • Evaluation of commercial
  • Evaluation of legal
  • Scenario analysis
  • Post tender interviews (supply chain discussions)
  • Conclusion & recommendation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What normalisation occurred on your projects?

A

On Eddington, reviewing the Stage 1 tender return, one contractor had particularly low insurance costs included compared to the other contractors
Normalised by adjusting to the highest cost tender and raised in post tender interview

How well did you know this?
1
Not at all
2
3
4
5
Perfectly