E Administration and Observation Flashcards

1
Q

Define Liquidated Damages

A

An actual amount specified in the contract of the loss to the client if the construction is late.
Not for the architect to determine, but to advise the client to get further help if needed.
Needs to be for the actual loss suffered.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When to use Performance Bonds

A

If the value is greater than $1.5M then consider using them to protect the principal from contractor default.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How often should observation be carried out?

A

Depends on the type of building, the speed at which work is being done. Minimum average one per week.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What to do if the client doesn’t want observation?

A

Don’t accept responsibility for construction work you never see. Under no circumstances agree part way through construction to undertake observation or issue a PC certificate.
Don’t go to site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What if you are engaged for observation, but not administration?

A

Clearly document all examples of defective and incomplete work and report in writing to the client and contract administrator.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What should the specification say in regard to observation?

A

That the contractor should notify the architect when the main architectural elements of the design are ready for inspection. The architect should list the critical items in the specification, and require two days notice for observation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are you observing?

A

Materials and components for general compliance with the contract docs.
Reviewing samples of critical construction work.
Reviewing samples, standards, goods off site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What to do if the contractor is not delivering an acceptable standard of work?

A

Inform the client/administrator in writing.

Inform the client that you may need a more intense level of observation, and therefore adjustment of your fee.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Guiding Principal of the HSWA 2015

A

Workers and other persons should be given the highest level of protection against harm to their health, safety, and welfare from work risks so far as is reasonably practicable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the dispute resolution process under SCC?

A

Architect’s Decision
Mediation
Arbitration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the dispute resolution process under the CCA?

A

Adjudication

Arbitration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the dispute resolution process under AAS?

A

Mediation
Arbitration
Adjudication - of fees

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Describe Mediation

A

Mediator helps parties reach agreement - assisted negotiation.
The process is voluntary.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Describe Adjudication

A

Under the CCA

Independent person decides a dispute based on evidence. The outcome may not be final.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Describe Arbitration

A

Independent person decides a dispute based on available evidence. The outcome is enforceable, final and binding. It may overturn an adjudication.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Name of the Act created by government in response to leaky claddings.

A

The Weathertight Homes Resolution Service Act 2006

17
Q

What are VPRs?

A

Variation Price Requests

A request to the contractor to price for a contemplated change in the works. Price ONLY.

18
Q

What is an AD?

A

Architect’s Direction

Architect issues to contractor. Can include variations.

19
Q

Under SCC, when should the contractor begin work?

A

The date that the contractor is given possession of the site should be stated in the contract - time in days after notice of acceptance of Tender. The contractor must start within 5 days of this.

20
Q

How can you assess progress on site in regard to programme?

A
  1. Rule 11.3 - contractor to supply programme.
  2. As for this to be in simple bar format so it is easily legible.
  3. Include ‘Progress of Work’ on every meeting agenda.
  4. Request contractor to supply updated programmes showing actual progress achieved - critical in assessing EOTs.
21
Q

When is the contract complete?

A

When all of the items on the defects liability list have been remedied.

22
Q

Who is responsible to decide if Practical Completion has been achieved?

A

The architect.

23
Q

Tricky situation: Builder called back during defects period to fix some work and damages the painting while fixing. Who pays for the re-paint?

A

The issue is not whether the architect was right, but whether the architect acted in an appropriate manner.
Look through the conditions of contract, look carefully, don’t be rushed into a wrong decision.
The builder was required to make good the painting.