E Administration and Observation Flashcards
Define Liquidated Damages
An actual amount specified in the contract of the loss to the client if the construction is late.
Not for the architect to determine, but to advise the client to get further help if needed.
Needs to be for the actual loss suffered.
When to use Performance Bonds
If the value is greater than $1.5M then consider using them to protect the principal from contractor default.
How often should observation be carried out?
Depends on the type of building, the speed at which work is being done. Minimum average one per week.
What to do if the client doesn’t want observation?
Don’t accept responsibility for construction work you never see. Under no circumstances agree part way through construction to undertake observation or issue a PC certificate.
Don’t go to site.
What if you are engaged for observation, but not administration?
Clearly document all examples of defective and incomplete work and report in writing to the client and contract administrator.
What should the specification say in regard to observation?
That the contractor should notify the architect when the main architectural elements of the design are ready for inspection. The architect should list the critical items in the specification, and require two days notice for observation.
What are you observing?
Materials and components for general compliance with the contract docs.
Reviewing samples of critical construction work.
Reviewing samples, standards, goods off site.
What to do if the contractor is not delivering an acceptable standard of work?
Inform the client/administrator in writing.
Inform the client that you may need a more intense level of observation, and therefore adjustment of your fee.
Guiding Principal of the HSWA 2015
Workers and other persons should be given the highest level of protection against harm to their health, safety, and welfare from work risks so far as is reasonably practicable
What is the dispute resolution process under SCC?
Architect’s Decision
Mediation
Arbitration
What is the dispute resolution process under the CCA?
Adjudication
Arbitration
What is the dispute resolution process under AAS?
Mediation
Arbitration
Adjudication - of fees
Describe Mediation
Mediator helps parties reach agreement - assisted negotiation.
The process is voluntary.
Describe Adjudication
Under the CCA
Independent person decides a dispute based on evidence. The outcome may not be final.
Describe Arbitration
Independent person decides a dispute based on available evidence. The outcome is enforceable, final and binding. It may overturn an adjudication.