E - Admin & Observation of Contract Works Flashcards
What are the key aspects of Contract Administration? (x7)
Progress Reporting - construction, programme & budget Compliance Health & Safety Conflict Resolution Variations Document Managemnet Occupation & Handover
What should you be wary of when inspecting shop drawings?
Do not indicate approval other than in conforming with the design concept and in principle with the specifications & drawings.
Do not use terms “check”, “approve”, verify correctness etc.
What might be valid reasons for an Extension of Time under 3910?
- effect of any variation
- weather
- strike, lockout or industrial action
- loss of damage to Contract works or materials
- flood, volcanic or seismic events
- circumstances not reasonably foreseable by an experienced contractor at the time of tendering and not due to the fault of the contractor
- default by the principal
What is the timing for a progress claim?
Architect to issue schedule: 5 working days
Principal review: + 3 working days
Replacement schedule: + 2 days
Payment: 17 working days total
What are the release rates for retentions?
SCC: 40% at practical completion
3910: 50% at practical completion
What is the timing for the final payment claim?
Architect to issue schedule: 20 working days
Principal Review: +10 working days
Replacement Schedule: +5 working days
Payment: 45 working days total
Adjudication can take place 20 days after replacement schedule.
What must payment schedules include?
In writing
Dated
Identify claim & sum to be certified
Show manner of calculation
How do you deal with tax invoices?
2 options:
1/ Architect can do as Payment schedule
2/ Contractor issues following schedule
How would you assess off site goods?
Inspect the materials to verify they are:
- separated
- identified
- labelled
- secure
- of quantity claimed
What is a provisional sum?
A work or item monetary allowance. Provides to carry out specific part of the contract works to be paid for by the contractor. Includes contractors expenses & margins.
What is a prime cost sum?
A material monetary allowance. Purchase & supply of materials to be incorporated in the contract works. Does not include cost of installation. Includes reasonable cost to cover expense and margins.
What are the effects of extensions of time?
Insurance
Material fluctuations
How long does a contractor have to claim an EOT?
5-10 working days, or as soon as practicable, after the delay begins.
Must be in writing.
What are reasons for EOTs? (x13)
- consent or approval not obtained
- unforeseeable physical conditions
- contract works are suspended
- loss or damage to contract works
- variations
- weather that interferes with progress
- strike, lockout or industrial action
- delayed Architect’s Direction after contractor request in writing
- Principal delayed materials, works or services
- separate contractors act or omission
- death
- significance beyond contractors control
- work under contingency sum causes delay or requires additional time
What is the dispute resolution steps & timing under NZIA SCC?
1/ Refer contract
2/ Dispute 20 WD - architect decision
3/ Mediation 30 WD - dispute decision
4/ Arbitration 30 WD - if mediation fails
5/ Adjudication - at any stage by agreement
What is arbitration?
Contractually agreed formal dispute resolution.
Normally try mediation first
The arbitrator’s decision is binding and enforceable by a legal court.
What is adjudication?
A statutory deliberate process performed under the CCA to provide a temporary solution to encourage cashflow.
Can be undertaken at any stage by agreement. Suspends the dispute process
While the orders are only binding in the interim, they are often accepted by the parties without further legal proceedings being required
How should you address defects in relation to practical completion?
More than minor defects should generally be rectified before practical completion - could be scope to defer these items.
Minor defects can be listed prior to Practical complation. but money cannot be withheld.