D - Procurement Flashcards
What are some different construction contracts?
NZIA SCC
NBC (National Building Contract)
NZS3910
NZS3915
What is novation?
A form of design build contract.
In the context of the Agreement for Architects Services, „Novation‟ means replacing one party to the agreement (the Client) with another party (the Builder).
Design and documentation often limited to identifying the clients needs, intent, quality & price.
Contractor takes over the consultant agreements & responsibility to delivery project
What type of project delivery methods are there?
Traditional
(architect design, documents/ contractor constructs)
Design & Build
(contractor responsible design & construction)
Management
(contractor manages packages of work)
Guaranteed Maximum Price
(Agreed max sum)
Private Finance Initiative
(Single integrated supply team formed for project)
Partnering
(Collaborative mgmt)
What are some risks of novation?
- resources of the contractor to manage
- cost risk may impact design
- risk transfer
- check legal agreements with insurer & solicitor
- conflict between contractor & client needs as consultant
- fee & insolvency security
- copyright
What types of tender are there (long list)?
- Lump Sum
- Traditional with nominated subcontractors
- Subcontrator design
- Rates and margins (Cost plus)
- Labour only
- Staged/Packages
- Guaranteed maximum price
- Separate contractors
- Early Contractor involvement
- Direct negotiation
- Fast track
- 2 stage tender
How would you evaluate multiple tenders?
Like for like comparison
Weight against criteria - scoring cost and non cost attributes
What are things you must consider during tender?
FAIRNESS Honesty Legal obligations Ownership Intention to proceed No improper advantage = equality of conditions No collusion Clarity of evaluation criteria Confidentiality Conflict of interest
How does SCC vs 3910 define Principal?
Same - person named in the specific conditions
Hows does SCC vs 3910 define Contractor?
3910 - person whose tender has been accepted by the principal or the person so named in the contract.
SCC - person named in specific conditions
Hows does SCC vs 3910 define Engineer/Architect?
3910 - professional engineer, architect, surveyor or NATURAL PERSON named in the specific conditions or natural person subsequently appointed by the Principal.
SCC - Architectural practice named in the specific conditions
What is the NZIA SCC for?
Contract between principal & contractor for construction of contract works of any size or complexity where the ARCHITECT ADMINISTERS the contract on behalf of the Principal.
What is the NZIA SCC SF intended for?
Alterations or new building work of simple nature with relatively low value and completed within short contract period
What is NZS 3910 for?
Contract between principal & contractor for construction of contract works of any size or complexity where the ENGINEER to the contract ADMINISTERS the contract on behalf of the principal.
What is NZS3915 intended for?
Building & civil engineering construction where no person is appointed engineer to the contract
What is the Construction Contracts Act 2002 (amended 2015)?
Sets out:
- defaults for processing payment claims & payments
- dispute resolution
Applies to all NZ contracts, binds the Crown, cannot be contracted out of and affects all contract administration procedures.
What is the purpose of the CCA?
- facilitate regular & timely payments
- provide for speedy resolution of disputes
- provide remedies for the recovery of payments
How does the CCA specifically vary for Residential Construction Contracts?
- contractor unable to seek a charging order over the land
What is a performance bond?
A Document arranged between Principal & Contractor to provide protection against financial loss resulting from default of a party. NZIA recommend these for contractors over 1.5M
Discharged at practical completion.
Suggest that if this is needed for trust then it should be offered by both parties
Who should fill in the Insurance Schedules?
The Principal
Architects are not experts in insurance.
What is the stated period for submission of final payment claims under NZIA SCC or the CCA?
No stated period
SCC has location to state (ie 3months)
What are the standard rates for retentions (SCC)?
10% on first 200K
5% on next 800K
1.75% to max 200K
What are implied warranties under the Building Act?
All residential building work is covered by implied warranties.
These last for 10 years and cannot be contracted out of:
- all building work will be done properly, competently and according to the plans and specifications in your approved consent
- all materials used will be suitable and, unless stated in the contract, new
- the building work will be consistent within the building act and the building code
- the building work will be carried out with reasonable care & skill, and completed within the time specified or a reasonable time if no times specified
- the home will be suitable for occupant at the end of the work.
Plus there is a 12 month defect repair period.
Summarise the relevancy of the Consumer Guarantees Act?
Applies to services provided by the building industry but not to buildings. Work should be done with reasonable skill and care, materials fit for purpose and done in a timely manner.
Residential buildings are covered by implied warranties under the Building Act